I-40 Over 8th Avenue Bridges

i40 8th ave bridges - v4

The Tennessee Department of Transportation (TDOT)  is planning the replacement of the four Interstate 40 Bridges over 8th Avenue near mile marker 210 in Nashville. To expedite this work, the bridges will be replaced by Accelerated Bridge Constructon (ABC) methods. 

Current Status: This project has been awarded for construction.

Construction Start: Fall 2026.

Estimated completion*:  Summer 2028.

Funding Type: Fully state funded.

magnifying glass


History and Background

Every two years, TDOT performs a comprehensive inspection and subsequent evaluation of all public bridges across the state in order to determine the status of their working condition and operating limits. These inspections and evaluations are to ensure that bridges are in accordance with the Federal Highway Administration (FHWA) National Bridge Inspection Standards (NBIS). The proposed project is needed to address the various structural deficiencies for each of the four bridges, as described by the TDOT Engineering Division, Structures Section, and in the most recently available inspection reports.

TDOT will be using an Alternative Delivery: Construction Manager/General Contractor (CM/GC) method for this bridge replacement project. This delivery method involves a contractor in the design phase to mitigate risk, improve the construction schedule, and streamline the design process.

cone

Traffic Impacts

When construction begins, weekly lane closure reports can be viewed here: https://www.tn.gov/tdot/news/

This project will be completed in two phases, with Phase 1 beginning in September 2026. Both phases include 8th Avenue beneath the bridges experiencing continuous lane closures for approximately 10 months for each phase. During both phases, 2 northbound lanes and one southbound lane will remain open. Sidewalks will be closed throughout the duration of the project. 

Following this extended closure, the project will utilize Accelerated Bridge Construction (ABC) techniques, allowing each bridge to be replaced during three weekend closures, with traffic fully restored during weekday periods. These weekend closure dates will be posted in the coming months. 

8th Ave Bridge Closures-v2_Lane Closures
8th Ave Bridge Closures-v2_Sidewalk Closure
pin


Key Project Milestones*

*Subject to change.

Milestone Timeline
Substructure Work - Phase 1 Fall 2026 - Fall 2027
Two Full I-40 & 8th Avenue Weekend Closures Fall 2027
Misc. Work  Winter 2027 - Spring 2028
Final Full I-40 & 8th Avenue Weekend Closure Spring 2028
map

Project Imagery & Visuals

globe

 

Environment

This solely state-funded highway project qualified for an environmental evaluation under the Tennessee Department of Transportation's current environmental procedures. This evaluation has been documented in a Tennessee Environmental Evaluation Report.

paper

 

Project Materials

Click here for details on TDOT's Alernative Delivery website.

Project Contacts

Feroze Rashid
TDOT Project Manager 
Email: Feroze.Rashid@tn.gov

Erin Zeigler
TDOT Region 3 Regional Communications Officer (Media)
Phone: 629.277.2458
Email: Erin.Zeigler@tn.gov

Halen Tyler
TDOT Region 3 Communications Specialist (Media/Website)

Phone: 629.239.8524
Email: Halen.Tyler@tn.gov

 

*Subject to change