Interstate 40: Bridges over Buffalo River and Squeeze Bottom Lane

Humphreys County
Humphreys I-40 Bridges

The Tennessee Department of Transportation (TDOT) is constructing improvements to Interstate 40 in Humphreys County. The improvements include resurfacing work on I-40 and replacement of the bridges over the Buffalo River and Squeeze Bottom Lane.

Current Status: Phase 1 construction, which includes resurfacing of I-40 from east of the Buffalo River bridge to just west of the Squeeze Bottom Lane bridge, is currently underway in preparation for implementation of traffic shifts.

Construction start: Summer 2024

Estimated completion*: January 2029

Funding Type: State and Federal

cone

 

Traffic Impacts

There will be temporary lane closures in both directions on I-40 for roadway maintenance as needed (MM 140 -142). One lane will remain open.

A traffic shift is scheduled for Thursday, September 4, moving westbound traffic to the inner median so crews can work on the outside lanes.

magnifying glass

 

History and Background

The 1.96-mile project on Interstate 40 in Humphreys County, from near Exit 137 to near Exit 143, consists of widening the roadway and replacing two bridges. The planned improvements are designed to replace the two bridges and improve future capacity of I-40.

globe

 

Environment

As part of the environmental review process for this project, TDOT has documented commitments to environmental mitigation and remediation measures. View the commitment document here.

pin

 

Key Project Milestones

Milestone Timeline*
Construction of Median: Bridge over Squeeze Bottom Lane November 2024 - May 2025
Construction of Median: Bridge over Buffalo River September 2024 – July 2025
Bridge over Squeeze Bottom Lane: Westbound August 2025 – December 2025
Bridge over Buffalo River: Westbound
August 2025 – August 2026
Bridge over Squeeze Bottom Lane: Eastbound
December 2026 – May 2027
Bridge over Buffalo River: Eastbound
December 2026 – February 2028
paper

 

Project Materials

Incident Management Plan
 

Project Contacts

Lee Rogers
TDOT Region 3 - District 38 Manager

Phone: 931.766.7544
Email: Lee.Rogers@tn.gov

Erin Zeigler
TDOT Region 3 Regional Communications Officer (Media)
Email: erin.zeigler@tn.gov
Phone: 629.277.2458

 

*Subject to change