State Route 99 (New Salem Highway)

Rutherford County

The Tennessee Department of Transportation (TDOT) plans to improve State Route 99 (New Salem Highway) from Veterans Parkway (Southwest Loop) to SR 96 (Old Fort Parkway) in Rutherford County. The project consists of widening the two-lane roadway to a five-lane facility, allowing for a dedicated center turn lane.

The proposed improvements cover approximately seven miles but exclude the area within the I-24 interchange, as that section was previously widened under a separate project. Planned improvements will address safety, mobility, and operation of the route by enhancing access to both residential and commercial sites and by increasing roadway capacity to meet current and future traffic needs. SR 99 is an urban arterial route that was added to the state road system in 1931. Today, it connects the City of Murfreesboro to developing areas southwest of the city and beyond.

Due to the size of improvements to SR 99, TDOT split the project into three segments. One segment completed construction in 2021. The second segment, from I-24 to SR 96, is currently under construction. The final segment, from west of Veterans Parkway to Cason Lane, is identified for funding in TDOT's 10-Year Project Plan, with construction scheduled for Fiscal Year 2024.

Current Status: The segment from west of Veterans Parkway to Cason Lane is in the right-of-way (ROW) acquisition process. From I-24 to SR 96, construction is underway.

Estimated construction start: The segment from west of Veterans Parkway to Cason Lane is scheduled for construction in Fiscal Year 2024.

Estimated completion*: The segment from I-24 to SR 96: Summer 2024.

magnifying glass


History and Background

The existing route is a two-lane highway with turn lanes at various intersections. The proposed project will widen the roadway to five lanes with two 12-foot travel lanes in each direction, a 12-foot center turn lane, and 12-foot shoulders with curbs and sidewalks. The minimum right-of-way width will be 108 feet with permanent and temporary easements as needed.

Improvements along SR 99 have been divided into three sections:

From west of Veterans Parkway (SW Loop) to Cason Lane

The proposed project widens SR 99 approximately 2.4 miles, from west of Veterans Parkway to Cason Lane, including the widening of the existing box bridges on SR 99 over Armstrong Branch and on Old Salem Road over Puckett Creek. The existing signals at the Veterans Parkway and St. Andrews Drive intersections will be improved. Signal modifications at the Cason Lane intersection will be included in a separate widening project (from Cason Lane to I-24). This section is currently in the right-of-way acquisition phase.

From Cason Lane to I-24

The proposed project widens SR 99 approximately 2.0 miles, from west of Cason Lane to east of Warrior Drive near I-24, including the widening of the existing bridge over the West Fork Stones River. (NOTE: While the bridge is being widened, the existing greenway underneath will be closed.) The four existing signalized intersections within the project limits will be improved.

From I-24 to SR-96 (Old Fort Parkway)

The proposed project widens SR 99 from east of I-24, near West Molloy Lane / Middle Tennessee Boulevard, to the intersection of SR 96 (Old Fort Parkway). The existing signalized intersections within the project limits will be improved. Additional turn lanes will be provided at SR 96.  

pin


Key Project Milestones

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur on the improvements of the three sections of State Route 99 (New Salem Highway). Improvements along SR 99 have been divided into three sections.

West of Veterans Parkway (SW Loop) to Cason Lane

ROW Process

Currently Underway

Contract Award Date

Schedulded for Fiscal Year 2024

Cason Lane to I-24

Contract Award Date

March 2018

Completion Date

September 2021

I-24 to SR 96 (Old Fort Parkway)

ROW Process

Completed

Contract Awarded

November 202

Construction Estimated Completion Date

Summer 2024


Project Contacts

For questions regarding SR 99 from west of Veterans Parkway (SW Loop) to Cason Lane:
Bradley Martin, P.E.
TDOT Region 3 Project Development Manager
Phone: 615.350.4219
Email: Bradley.Martin@tn.gov

Rebekah Hammonds
TDOT Region 3 Community Relations Officer
Rebekah.Hammonds@tn.gov

Clint Carpenter (current construction)
Operations District Supervisor
Phone: 615.898.8005
Email: Clinton.Carpenter@tn.gov

For questions regarding SR 99 from I-24 to SR 96:
Jimme Bivens, P.E.
TDOT Roadway Design Division Assistant Director
Phone: 615.741.2725
Email: Jimmie.Bivens@tn.gov

*Subject to change