S-PL-3

SAFETY PLAN MINIMUM INSTALLATION AT BRIDGE ENDS
S-PL-3

(Click image to open PDF)

Latest Revision Note

03/01/2023    REPLACED S-PL-2 WITH S-GRS-7 AND S-GRS-7A ON GENERAL NOTE (D).

Related Standard Drawings

DRAWING DESCRIPTION REMARKS
S-GRC-4 GUARDRAIL CONNECTION TO BRIDGE RAILING CONCRETE PARAPET SEE DETAILS
S-GRC-6 GUARDRAIL CONNECTION TO BRIDGE ENDS FOR LOW SPEED ROADWAYS SEE DETAILS
S-GRC-SERIES SAFETY DESIGN AND GUARDRAILS : GUARDRAIL CONNECTIONS FOR DETAILS AND SPECIFICATIONS REGARDING INSTALLATION OF PROTECTIVE GUARDRAIL AT BRIDGE ENDS
S-GRS-7 SHORT – RADIUS GUARDRAIL SYSTEM (SRGS) INTRODUCING A NON-GATING ATTENUATOR
S-GRS-7A SHORT – RADIUS GUARDRAIL SYSTEM (SRGS) DETAILS INTRODUCING A NON-GATING ATTENUATOR
S-GRT-2 TYPE 38 GUARDRAIL END TERMINAL SEE DETAILS
S-GRT-2P EARTH PAD FOR TYPE 38 TERMINAL EARTH PAD REQUIREMENT
S-GRT-3 TYPE 21 GUARDRAIL TERMINAL SEE DETAILS
S-GRT-SERIES SAFETY DESIGN AND GUARDRAILS : GUARDRAIL TERMINALS FOR GUARDRAIL END TERMINAL DETAILS
S-PL-1 SAFETY PLAN AT ROADSIDE HAZARDS SHALL BE USED TO DETERMINE LENGTH OF NEED FOR GUARDRAIL
T-M-18 FLEXIBLE DELINEATOR DETAILS FOR FLEXIBLE DELINEATOR DETAILS

Related Item Numbers

ITEM NO. U/M DESCRIPTION
705-06.01 L.F. W BEAM GR (TYPE 2) MASH TL-3
705-06.20
EACH
TANGENT ENERGY ABSORBING TERM MASH TL-3
705-06.25
EACH
THRIE BEAM BRIDGE TRANSITION MASH TL-3
705-06.26
EACH
THRIE BEAM BRIDGE TRANSITION MASH TL-2
705-06.30
EACH
GR TERMINAL (ENERGY ABSORBING) MASH TL2

Archived Standard Drawings

DATES OF EACH ARCHIVED DRAWINGS ( THE INITIAL STANDARD DRAWING IS BOLD )
07-11-2013 | 10-10-2016 | 06-28-2019 | 06-15-2021 | 03-01-2023
If you find any mistakes, missing information or have a question, contact:
TDOT CADD Support
1200 James K. Polk Building
Nashville, TN 37243-1402
TDOT.CADDSupport@tn.gov

This Page Last Updated: April 17, 2023 at 11:11 AM