2019 Locally Let and Awarded Projects
Location | Type of Work | Contact | Posted - Bid Opening | Winning Contractor | Bid Amount |
---|---|---|---|---|---|
Lenoir City Loudon County |
Broadway St and B St Streatscape Project, including sidewalks, repaving, lighting, signing, and marking | Amber Scott City of Lenoir Jason Elliott Vaughn & Melton |
12/6/18 - 1/24/19 | Design and Construction Service, Inc. | $1,912,444.45 |
Sevierville Sevier County |
Greenway along Dolly Parton Parkway and Middle Creek, includes a pedestrian bridge, lighting, landscaping, and pedestrian amenities | Lee Davidson, RLS Lose Design |
12/13/18 - 1/24/19 | Whaley Construction, LLC | $591,711.00 |
Columbia Maury County |
Roadway and Streetscape Improvements for West 7th St | Scott Niesen, P.E. Ragan-Smith Assoc. |
12/19/18 - 1/23/19 | Sessions Paving Company | $6,238,803.85 |
Smyrna Rutherford County |
Widening of Weakley Ln / Swan Dr intersection to accommodate turn lanes | Tom Rose City of Smyrna |
12/19/18 - 1/24/19 | Sessions Paving Company | $1,100,924.00 |
White House Sumner County |
Sidewalks, retaining walls, and other improvements on US 31 from Oakland Ct north to the trialhead | Jason Reynolds, PE CSR Engineering |
12/21/18 - 1/24/19 | Sessions Paving Company | $1,358,648.00 |
Germantown Shelby County |
Resurfacing of Winchester Rd, From Forest Hill-Irene Rd to Eastern City Limits | Cathryn Perdue City of Germantown |
1/9/19 - 1/29/19 | Standard Construction Company | $1,480,339.85 |
Memphis Shelby County |
Traffic signal improvements to 7 signalized intersections at various locations | Randall Tatum City of Memphis |
12/28/18 - 1/30/19 | Pending Concurrence | |
Shelbyville Bedford County |
Signal installation at the intersection of US 231 and Palmer Dr | Lori Saddler City of Shelbyville |
1/7/19 - 1/31/19 | Stansell Electric Company, Inc. | $215,454.40 |
Savannah Hardin County |
Resrufacing of Harbert Dr from SR-203 to SR-15 | Tom Smith City of Savannah |
12/21/18 - 2/1/19 | Arrow Paving Company, INC. | $213,114.40 |
Fayetteville Lincoln County |
Fayetteville Square to Park - South Elk Street, From East Market Street to East of SR-273 (South Main Street, US-431) | Scott Collins City of Fayetteville |
1/10/19 - 2/5/19 | R. J. Watkins & Son Construction, Inc. | $582,517.35 |
Benton County | Bridge replacement: Lower Big Sandy over Ramble Creek, LM 15.72 | Laurie Poe A2H |
1/7/19 - 2/6/19 | Dement Construction Company | $921,792.19 |
Weakley County | Bridge replacement: Billingsby Road, Bridge over Campground Creek LM 1.14 | Laurie Poe A2H |
1/7/19 - 2/7/19 | Ford Construction Company | $544,401.70 |
Church Hill Hawkins County |
Kingsport Press Rd Resurfacing, from S.R. 1 to Greenland Park Rd | Jason Carder Mattern & Craig |
1/14/19 - 2/7/19 | Pending Concurrence | |
Tipton County | Bridge replacement: Holly Grove Rd Bridge over Adkinson Creek at LM 4.74 | Sanchali Nair A2H |
1/7/19 - 2/13/19 | Ford Construction Company | $693,277.08 |
Arlington Shelby County |
Widening of SR 1 (US 70) between SR 385 and Airline Rd; resurfacing, grading, signing, marking, and signals | Cathy Durant Town of Arlington |
1/28/19 - 2/21/19 | White Construction and Associates | $1,148,696.50 |
Millington Shelby County |
Astoria Ave reconstruction from North of Navy Rd to Hornet Ave | Jason Dixon City of Millington |
2/5/19 - 3/4/19 | Pending Concurrence | |
Loudon Loudon County |
Blair Bend Rd Resurfacing from SR-2 to Blair Bend Rd | Jack Qualls Loudon County |
2/12/19 - 3/5/19 | Pending Concurrence | |
Alcoa Blount County |
Greenway Trail Construction | Jeff Beckett Megan Brooks |
2/1/19 - 3/14/19 | Kings General Contractors, Inc. | $2,793,025.05 |
Springfield Robertson County |
Resurfacing and guardrail replacement William A. Batson Blvd. | Allan Ellis City of Springfield |
2/20/19 - 3/19/19 | Charles Deweese Construction, Inc. | $618,141.83 |
Germantown Shelby County |
Signalization at 3 locations: Poplar Pike at Hacks Cross Rd, Poplar Pike at S. Germantown Rd/Arthur Rd, and Poplar Ave at Kirby Parkwa | Tim Gwaltney City of Germantown |
2/20/19 - 3/21/19 | Desoto County Electric | $1,059,753.40 |
Church Hill Hawkins County |
Roadway milling and resurfacing, pavement markings, guardrail and terminals, signage | Jason Carder Mattern & Craig |
2/28/19 - 3/25/19 | Pending Concurrence | |
Sevierville Sevier County |
Greenway, sidewalks, bridge, signage, electrical Dolly Parton Pkwy and Middle Creek | Daniel Boutte | 3/5/19 - 3/26/19 | Whaley Construction, L.L.C. | $591,711.00 |
Winchester Franklin County |
Bible Crossing Rd Resrufacing | Yvonne Stewart City of Winchester |
3/4/19 - 3/28/19 | Tinsley Asphalt, LLC | $259,627.50 |
Savannah Hardin County |
Milling, resurfacing and striping of Harbert Dr. from SR-203 (Pinhook Dr.) to south of SR-15 (US-64/Wayne Rd.) | Tom Smith City of Savannah |
3/5/19 - 3/29/19 | Arrow Paving Company, INC | $213,114.40 |
Adamsville McNairy County |
Installation of 3 speed humps,p avement Markings, and signage | Steve Simon City of Adamsville |
3/5/19 - 4/1/19 | Nsite, Inc. | $30,846.75 |
Germantown Shelby County |
ADA curb ramps, sidewalks, pavement markings, signage Phase I and Phase II | Patrick W. Neal, PE | 3/7/19 - 4/2/19 | GCM, Inc. | $754,160.50 |
Loudon Loudon County |
Resurfacing Project for Blair Bend Rd. | Patrick Fiveash | 3/12/19 - 4/3/19 | APAC - Atlantic, Inc. | $846,504.86 |
Clarksburg Carroll County |
Signage Safe Routes to School | Mayor Howell Todd Bob Safin, PE |
3/5/19 - 4/10/19 | NSite, Inc. | $19,967.00 |
Crockett County | County Line Rd, bridge reaplacement over branch at LM 0.27 | Laurie Poe Project Coordinator |
3/4/19 - 4/10/19 | Dement Construction Company | $593,812.55 |
Loudon County | Street Lighting at the intersection of S.R. 72 and Tellico Parkway ( S.R. 44) | Becky Bottoms Cannon & Cannon, Inc. |
3/18/19 - 4/17/19 | Davis H. Elliot Construction Co., Inc. | $74,980.00 |
Millington Shelby County |
Roadway improvement for Astoria Ave. from N. of Navy Rd. to Hornet Ave. | John Greaud | 4/1/19 - 4/24/19 | Enscor, LLC | $2,375,850.00 |
Caryville Campbell County |
School signs and signals installation | Robert Stooksbury Mayor City of Caryville |
4/4/19 - 4/30/19 | Progression Electric, L.L.C | $35,590.56 |
Madisonville Monroe County |
School Signs and Signal Installation | Glenn Moser Greg Green |
4/5/19 - 5/1/19 | Progression Electric, LLC. | $42,767.10 |
Cleveland Bradley County |
Sidewalks, drainage, resurfacing | Kristi Powers David Sheely |
4/4/19 - 5/2/19 | Greenstar, LLC | $795,022.90 |
Collinwood Wayne County |
Sidewalk, concrete curb ramps and crosswalk striping along west side of 4th St. and east side of Trojan Dr. to Collinwood Elementary and Middle School | Ryan Maloney Griggs and Maloney, Inc. |
4/16/19 - 5/3/19 | Ward Construction | $201,540.00 |
Chattanooga Hamilton County |
Construction and signs | Ben Taylor | 4/12/19 - 5/9/19 | Pending Concurrence | |
Knoxville Knox County |
Replacement of the Jackson Ave. Bridge ramps connecting to Gay St. | George Daws | 4/15/19 - 5/9/19 | Bell & Associates Construction, L.P. | $6,454,537.80 |
Tazewell Claiborne |
Downtown Sidewalk Improvements - Phase II | Bill Fannon Greg Green |
4/11/19 - 5/14/19 | Whaley Construction, LLC | $436,295.75 |
Andersonville Anderson Count |
Andersonville Elementary Safe Route to School Sdewalk Project | Terry Frank Greg Green |
4/22/19 - 5/16/19 | Design and Construction Services, Inc. | $189,795.00 |
City of Church Hill Hawkins County |
Roadway milling and resurfacing, pavement markings, guardrail and terminals, and updated regulatory signage | Mattern & Craig Jason Carder, P.E. |
4/23/19 - 5/20/19 | Pending Concurrence | |
Fayetteville Lincoln County |
Sidewalk at Fayetteville Square Park - S. Elk St., from E. Market St. to E. of SR-273 | Scott Collins City of Fayetteville |
4/22/19 - 5/21/19 | R. J. Watkins & Son Construction, Inc. | $582,517.35 |
Nashville Davidson County |
Construction of sidewalk and multi-use paths on either side of Hart Ln. from Ellington Pkwy W. to Jere Baxter School consists of rock pre-splitting, excavation, slope and drainage construction, and milling land paving | Joseph Griffin, P.E. Ragan Smith Associates, Inc. |
4/30/19 - 5/23/19 | L&G Construction Company Inc. | $1,499,462.05 |
Mt. Juliet Wilson County |
Sidewalks, curb ramps, concrete driveway, pedestrian bridge, drainage, signage, erosion control, retaining wall, safety railing | Matthew White Zac Dufour |
4/30/19 - 5/24/19 | Sessions Paving Company | $1,368,804.65 |
Memphis Shelby County |
Traffic Signal Improvements | Randall Tatum | 5/01/19 - 6/05/19 | Pending Concurrence | |
Selmer McNairy County |
Sidewalk improvement with accessibility features for handicapped safety modifications and aesthetic landscaping | Kyle Bethay | 5/10/19 - 6/6/19 | NSite, Inc. | $455,951.00 |
Cleveland Bradley County |
Sidewalks, drainage, resurfacing | Kristi Powers David Sheely |
5/15/19 - 6/10/19 | B & W Contractors DBA Cherokee Construction | $ 749,014.00 |
Memphis Shelby County |
Construction of Wolf River Greenway Phase 4, paved 10' wide asphalt trail 1.3 miles, 19 space parking lot and trail amenities. And, additional trail head parking lot adjacent to existing Phase 3A trail segment. | Steve Hooper, P.E. ETI Corporation |
4/29/19 - 6/19/19 | ViktorHall Construction, LLC | $1,735,641.90 |
Hartsville Trousdale County |
Streetscape Project along E. Main St. including sidewalks, reconstruction of non-street parking areas, pedestrian lighting, streetscape features, and landscaping | Logan Reed Ragan-Smith Associates |
6/14/19 - 7/9/19 | Sessions Paving Company | $672,488.50 |
Germantown Shelby County |
Greenway Phase II includes a .5 mile connector trail extending W., connecting existing trailhead at Kimbrough trails at Nashoba Park, on E. end of existing trail, a 1 mile extension will provide connection from Cameron Brown Park E. along Wolf River to new trailhead and parking area | Tim Gwaltney Nick Taylor |
6/12/19 - 7/11/19 | Rose Construction, Inc. | $2,409,166.93 |
Mountain City Johnson County |
Multimodal Sidewalk Improvements | Sheila Shaw Vaughn & Melton Consulting Engineers |
6/19/19 - 7/18/19 | Summers-Taylor, Inc. | $539,206.50 |
Paris Henry County |
Road improvements, clearing, grading, paving, drainage, pavement markings, signage, epsc and traffic control . | Laurie Poe A2H |
6/24/19 - 7/18/19 | Pending Concurrence | |
Rockwood Roane County |
Sidewalks, asphalt greenway, curb ramps, board walk, & comfort stations | Becky Ruppe Administrator |
6/3/19 - 7/18/19 | McKinnon Construction Co., LLC | $1,531,647.50 |
Memphis Shelby County |
Street resurfacing to include: Airways Blvd. from Shelby Dr. to State Line, Mendenhall Rd. from Mt. Moriah Rd. to Knight Arnold Rd. Getwell Rd. from Park Ave. to Interstate 240; Cooper St. from Washington Ave. to Central Ave. | Janet Prejean City of Memphis |
6/17/19 - 7/24/19 | Standard Construction Company | $5,462,560.59 |
Mt. Juliet Wilson County |
Sidewalks, curb ramps, ADA improvements, concrete driveways, drainage, signage, erosion control, retaining wall, safety railing, culverts, and pavement markings | Matthew White Will Spaulding |
6/26/19 - 7/24/19 | Pending Concurrence | |
Bristol Sullivan County |
Sidewalk along Maryland Ave. between Maple St. & E. Cedar St. | Jacob Chandler City Engineer |
6/25/19 - 7/25/19 | Pending Concurrence | |
Sweetwater Monroe County |
Resurfacing of Sweetwater including Anderson St. (from Monroe St. to Chestnut St.) and High St. (from New Hwy 68 to Monroe St.) "high school connector" on S. High St. from Willow Creek Blvd. to S. Clark St. | Kip Mayton Wiser Consultants, LLC |
6/28/19--7/31/19 | Wilson Construction Group, LLC., | $582,832.37 |
Knoxville Knox County |
Construction of new greenway path | Micah Herren Public Building Authority |
6/27/19 -8/1/19 | Charles Blalock & Sons, Inc. | $793,473.10 |
Loretto Lawrence County |
Sidewalk, clearing, grubbing, removal of pavement, pavement repair, grading, sodding, instalation of curb & gutter, stairs & handrail at South Lawrence Elementary School along northern side of 2nd Ave. S. between Collier St. and Riddle St. | Houston Matthews Croy Engineering |
7/10/19-8/6/19 | Brad Slater Construction | $224,830.95 |
Elizabethton Carter County |
Installation of median & textured crosswalk along W. G St. Installation of flashing beacons at five intersections along the Tweetsie Trail | Jason Carder Mattern & Craig |
7/19/19-8/12/19 | Summers- Taylor, Inc. | $345,346.00 |
Bartlett Shelby County |
Paved pedestrian & bycicle greenway, including parking lot & pedestrian bridge | Russ Brasfield Barge Design Solutions, Inc |
7/18/19-8/15/19 | Pending Concurrence | |
Gallatin City Sumner County |
Sidewalk, ADA updates | Joe Griffin | 7/19/19-8/15/19 | Adam's Contracting | $298,182.50 |
Smyrna Rutherford County |
Widening of Sam Ridley Pkwy from E. of I-24 to W. of Old Nashville Hwy. Grading, drainage, base, paving, signalization, signing and striping | Tom Rose Town of Smyrna |
7/17/19-8/20/19 | Jones Brothers Contractors, LLC | $11,037,323.70 |
Lenoir City Loudon County |
Roadway Widening, installation of turn lane, and sidewalks. | Amber Scott, City Administrator | 7/31/19-8/21/19 | Pending Concurrence | |
Hendersonville Sumner County |
Traffic Management System Improvements including, but not limited to, fiber optic cable & appurtenances, conduit banks, traffic signal equipment, radios & antennas. | Sarah Lock | 7/29/19-8/22/19 | Pending Concurrence | |
Shelbyville Bedford County |
Pedestrian improvements public square, work includes sidewalk, crosswalk, curb ramps, etc. | Kip Mayton Wiser Consultants |
7/25/19-8/22/19 | Pending Concurrence | |
White County | Bridge demolition, bridge construction, grading & approaches, roadwork, guardrail installation, paving, pavement marking, erosion prevention & sediment control, and traffic control. The total project length is 0.156 miles. | Laurie Poe Project Coordinator |
7/31/19-8/28/19 | Summers-Taylor, Inc. | $1,388,072.00 |
LaGrange Fayette County |
Sidewalk Replacement | Mayor William Cowan Jr. | 7/30/19-9/5/19 | Nsite, Inc. | $294,197.00 |
Knoxville City Knox County |
ITS and Signal Improvements | Zachary Roberts, P.E. | 8/23/19-9/13/19 | Pending Concurrence | |
Chattanooga City Hamilton County |
Replacement of faded, damaged, obstructed, and/or nonstandard traffic signs throughout the City of Chattanooga | Ben Taylor | 8/29/19-9/19/19 | Pending Concurrence | |
Mt. Juliet City Wilson County |
Sidewalks, curb ramps, ADA improvemnets, concrete driveways, drainage, signage, erosion control, retaining wall, safety railing, culverts, pavement markings. | Matthew White Kimley-Horn/ Will Spaulding |
9/5/19-9/27/19 | $625,186.75 | |
Chattanooga City Hamilton County |
Common and borrow excavation, installation of new sidewalks, detached curbs, curb gutter, handicap ramps, driveway aprons, erosion control, topsoil and seeding, and traffic control. Other elements may include demolition and removal of existing sidewalks, storm drainage, and other misc items as needed. All according to Tennessee Department of Transportation Standards. The project is located on Caine Lane, Chattanooga, TN and approximately 3200 feet long. | Debbie Talley | 9/5/19-10/1/19 | Pending Concurrence | |
Chattanooga City Hamilton County |
The project consists of common and borrow excavation, installation of new sidewalks, detached curbs, curb gutter, handicap ramps, driveway aprons, erosion control, topsoil and seeding, and traffic control, demolition and removal of existing sidewalks, storm drainage, and other misc items as needed. Located in Chattanooga, TN and approximately 3100 feet long with 1472 10' wide roller compacted concrete path and 1600 12' wide boardwalk. | Debbie Talley | 9/3/19-10/1/19 | Pending Concurrence | |
Bartlett City Shelby County |
Paved pedestrian and bicycle greenway, including parking lot and pedestrian bridge. | Russ Brasfield | 9/10/19-10/3/19 | Bell & Associates Construction, L.P. | $935,662.00 |
Memphis City Shelby County | Traffic Signal Improvements | Randall Tatum | 9/11/19-10/9/19 | McCrory Electric | $266,243.35 |
Somerville City Fayette County |
Sidewalk construction including demolition, sidewalk, concrete paving, landscaping, trees and sod, pedestrian lighting, and concrete curb | Michele Winslow | 9/13/19-10/10/19 | NSite, Inc. | $852,502.00 |
Loretto City Lawrence County |
Sidewalk Construction | Kenny Shelton | 9/16/19-10/11/19 | Pending Concurrence | |
Brownsville City Haywood County |
The work to be done consists of milling and resurfacing, construct sidewalk and curb and gutter repair sidewalk, pavement marking, pedestrain signal improvement, signage, traffic control and EPSC installation and maintenance. | Laurie Poe | 9/23/19-10/17/19 | Pending Concurrence | |
Lobelville City Perry County |
Striping, concrete and asphalt demolition, curb, signage, curb ramps and sidewalks, pedestrian lighting, drainage, and landscaping. | Cristal Odom | 9/19/19-10/17/19 | NSite, Inc. | $730,000.00 |
Lakeland City Shelby County | Installation of curb and gutter, asphalt trail and boardwalk connectors. | Emily Harrell | 9/24/19-10/17/19 | Pending Concurrence | |
Martin City Weakley County | Demolition, striping, signage, sidewalks, crosswalks, curb ramps, handicap ramps, landscaping, pedestrain lighting. | Michele Winslow | 9/24/19-10/18/19 | Ford Construction Company | $1,772,794.80 |
Lafollette City Campbell County | Construction of new concrete curb and gutter, pedestrian ground markings, and landscaping at 3 downtown intersections. | Warren Lulg/Mike Asalon | 9/26/19-10/22/19 | Design and Construction Services, Inc. | $151,705.00 |
Knoxville City Knox County | This project includes I-275 business park access improvements; construction of new roadway from Blackstock Avenue and Fifth Avenue to Bernard Avenue, and roadway improvements to Marion Street from Bernard Avenue to Baxter Avenue. Project length = 0.538 miles. Completion time is on or before 450 days from notice to proceed. | George Daws | 9/24/219-10/23/19 | Pending Concurrence | |
Pigeon Forge City Sevier County | SR73 (Wears Valley Road) at US441 (Parkway) intersection improvements including grade, drain, base, pavement, sign, striping, and signalization. | Mark Miller | 10/3/19-10/23/19 | Pending Concurrence | |
Arlington City Shelby County | This project involves the widening of SR 205 (Airline Road) between I-40 and North Milton Wilson Boulevard, located in Arlington , TN. The road is being widened to 5 lanes with curb, gutter and sidewalks. The total project length is 0.741 miles. | Cathy Durant | 9/24/19-10/29/19 | White Construction | $2,616,633.11 |
Etowah City McMinn County | Concrete sidewalks, driveways, curb ramps and crosswalks | Tina Tuggle | 10/3/19-10/29/19 | McKinnon Construction Co., LLC | $463,709.00 |
LaFollette City Campbell County | Concrete sidewalks, driveways, curbs, and curb ramps. | Jimmy Jeffries | 10/3/19-10/30/19 | Twin K Construction, Inc. | $111,794.50 |
Union City Obion County | Milling, paving, concrete curb and gutter, drainage improvements, sewerage upgrades, demolition, curb ramp installation and striping | Michele Winslow | 9/26/19-10/31/19 | Ford Construction Company | $575,611.94 |
Sevierville & Pigeon Forge City Sevier County | Signal controller installation, controller cabinet modifications, signal head modifications, video detection installation, pavement marking and signing replacement and upgrades, curb ramp additions and modifications, accessible pedestrian system installation, and other miscellaneous intersection upgrades. | Brian Haas | 10/7/19-10/31/19 | Pending Concurrence | |
Humboldt City Gibson County |
Demolition, sidewalk installation, curb and gutter, signs, lighting, pavement marking and drainage structures. | Michele Winslow | 9/23/19-11/5/19 | Pending Concurrence | |
Germantown City Shelby County | This project involves the rehabilitation of five storm drainage crossings of the poplar avenue right-of-way within the corporate limits of the City of Germantown. | Laurie Poe | 10/17/19-11/8/19 | Pending Concurrence | |
Clarksville City Montgomery County | Heritage Park- Safe Routes to School is the construction of approximately 3,026 linear feet of sidewalk for the City of Clarksville connecting Heritage Skate Park to Kenwood Middle School in accordance with TDOT standard specifications. Demolition and reinstallation of associated sidewalks, drives and crosswalks to be included in construction. | Dana Tharpe | 10/22/19-11/14/19 | Adams Contracting, LLC | $292,937.00 |
Brownsville City Haywood County |
This project consists of the items related to the Brownsville Multimodal project. The project includes the following types of work. Sidewalk, landscaping, concrete & asphalt demolition, curb & gutter, pavement marking, retaining wall, handrails, minor drainage improvements. | Mayor William Rawls | 10/22/19-11/21/19 | Ford Construction Company | $593,826.85 |
Hendersonville City Sumner County | Traffic Management System Improvments including, but not limited to, fiber optic cable & appurtenances, conduit banks, traffic signal equipment, radios & atennas. | Sarah Y. Lock | 10/28/19-11/21/19 | Pending Concurrence | |
Loretto City Lawrence County | Construction of new sidewalk and ramps | Kenny Shelton | 10/28/19-11/22/19 | Brad Slater Construction | $395,920.50 |
Hendersonville City Sumner County | Management System Improvments including, but not limited to, fiber optic cable & appurtenances, conduit banks, traffic signal equipment, radios & atennas. | Sarah Y. Lock | 10/28/19-11/28/19 | Pending Concurrence | |
Atoka City Tipton County | Phase 2 of the Atoka Greenway will include the construction of a 10-foot wide asphalt trail from the end of Phase 1 of the Greenway at Elizabeth Drive, extending east along rhe creek and terminating at Pioneer Park for a total distance of approximately 1,134 linear feet. The project includes pedestrian lighting for the entire trail from Walker Park to Pioneer Park. Structures to allow for ADA access will include new crosswalks. | Debbie Pickard | 10/17/19-12/3/19 | Pending Concurrence | |
Lakeland City Shelby County | Installation of curb and gutter, asphalt trail and boardwalk connectors. | Emily Harrell | 11/7/19-12/5/19 | Enscor, LLC. | $1,221,637.00 |
Lawrenceburg City Lawrence County | TAP Project- sidewalks and other pedestrian improvements. | Will Owen | 11/14/19-12/11/19 | Pending Concurrence | |
Bristol City Sullivan County | Construction of sidewalks, curb and gutter, storm sewer, ADA upgrades, and pavement markings. | Randy Dodson | 11/8/19-12/12/19 | Summers-Taylor, Inc. | $622,622.00 |