State Route 1 (US 431) Broadway Viaduct
Davidson CountyTimeline Update

Activity | Completion Date |
---|---|
Engineering Services / Consultant Selection | Spring 2021 |
Design Completion | June 2022 |
Construction Begins | Fall 2022 |
8-Week Complete Closure | July 2023 - August 2023 |
Construction Complete | October 2023 |
*All forecasted dates are subject to change.
PROJECT DELIVERY
Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. The following is a reflection of various aspects of the State Route 1 (US 431) Broadway Viaduct project as they have occurred or will occur.
In an effort to expedite project delivery, TDOT is considering using Accelerated Bridge Construction (ABC) techniques and completing the project under a Construction Manager/General Contractor (CM/GC) contract.
ABC uses innovative planning, design, materials, and construction techniques in a safe and cost-effective manner to reduce the onsite construction time of building, replacing, or rehabilitating bridges. It often uses precast or hybrid cast-in-place bridge elements.
The CM/GC project delivery method involves a contractor in the design and construction phases of the project. The partnership between TDOT, the Designer, and the Contractor reduces risks and improves constructability.
For more information on the CM/GC process for this project, visit the CM/GC SR 1 Project Davidson County information page under the Construction Division section of the TDOT website.