Weekly Roadway Activity Report for TDOT Region 2 for September 6-12, 2018

Thursday, September 06, 2018 | 01:55pm

DISTRICT 27

 

CLAY COUNTY SR-53 bridge repair over the Obey River (LM 8.89):   No work is scheduled this week. Estimated project completion date is September 2018.
[Mid-State Construction Company, Inc./Moore/CNR284]

 

CUMBERLAND COUNTY I-40 West near MM 326, construction of a truck climbing lane, including grading, drainage, construction of retaining walls and paving:   The contractor continues to work on punch list items with no lane closures expected at this time. Work may involve periodic closures of the outside shoulder. The newly constructed truck climbing lane has been opened to motorists.  Estimated project completion date is September 2018.
[Rogers Group, Inc./Bradley/CNQ329]

 

CUMBERLAND COUNTY SR-101 (Peavine Road) grading, drainage, and paving from Firetower Road to Westchester/Catoosa Boulevard:   As grade work progresses, motorists should be alert for shifts in traffic patterns to allow for construction activities. Current activities include paving activities, utility relocation, grade work, storm drain, base stone, and curb and gutter. Temporary lane closures and traffic stoppages may be needed to support ongoing work. Motorists should reduce speeds on Peavine Road and be alert for construction personnel and equipment entering and exiting the roadway.  Estimated project completion date is November 2020.
[Rogers Group, Inc./Bradley/CNQ921]

 

CUMBERLAND COUNTY US-127 (SR-28) from Plateau Road (LM 22.68) to the bridge over Clear Creek (LM 30.50) and SR-298 from north of Redmond Lane (LM 6.75) to south of Roy McCoy Road (LM 12.38) resurfacing (microsurfacing):   Construction signs have been installed on SR 298 (Genesis Road) and SR 28 (US 127). Contractor has begun microsurfacing activities which require temporary lane closures with flaggers. Estimated project completion date is September 2018.
[Hudson Construction Company/Bradley/CNS018]

 

CUMBERLAND AND PUTNAM COUNTY I-40 resurfacing from Putnam County line to near the parking area, and from west of Exit 300 to the Cumberland County line:   Work on this project is complete and ready for final inspection. Estimated project completion date is September 2018.
[Rogers Group, Inc./Bradley/CNR314]

 

CUMBERLAND AND RHEA COUNTY The resurfacing (microsurfacing) on SR-68 from west of Wiley Ford Road (LM 5.23) to the Rhea County line (LM 12.55) and on SR-68 from the Cumberland County line (LM 0.00) to north of Possum Trot Road (LM 3.42):   Construction signs have been installed on SR 68 in Cumberland and Rhea Counties. Contractor has begun microsurfacing activities which require temporary lane closures with flaggers. Motorists need to be alert for construction personnel and equipment working on the roadway.  Estimated project completion date is September 2018.
[Hudson Construction Company/Bradley/CNS019]

 

FENTRESS COUNTY SR-28 Construction of an acceleration lane (LM 21) and safety improvements near the Jamestown City limits (LM 20.78) to the Pickett County line (LM 33.58):   Contractor is scheduled to complete guardrail installation on SR 28 between LM 20.78 and 33.58 this week. Contractor will use flaggers and shut SR 28 down to one lane to complete this work.  Estimated project completion date is October 2018.
[Superior Traffic Control, LLC/Moore/CNR144]

 

FENTRESS COUNTY SR-297 resurfacing (microsurfacing):   Contractor is scheduled to be onsite installing guardrail terminals on SR 297 in Fentress County between LM 0 to to 9. Intermittent lane closures will be used to accommodate this work. Estimated project completion date is September 2018.
[Hudson Construction Company/Moore/CNS098]

 

JACKSON COUNTY SR-56 Resurfacing from SR-53 (LM 10.94) to near bridge over Germany Branch (LM 17.75):   Contractor is scheduled to begin paving operations 09/06/18 between LM 10.94 to 17.75. Contractor will restrict SR 56 to one lane and have flaggers on site to facilitate this work.  Estimated project completion date is November 2018.
[Rogers Group, Inc./Moore/CNS177]

 

OVERTON COUNTY Utility Work on SR-52 (N. CHURCH ST.) both directions from LM 10.4 to LM 10.5:   Detour with barricades and signage for sewer work between E. 4th St. & intersection of Doak St. Beginning 8/20/18 Ending 9/20/18 from 8am to 3:30pm. [UO-2007050965-2018]

 

OVERTON COUNTY SR-136 Resurfacing from SR-85 (LM 9.21) to SR-52 (LM 16.6):   Paving operations are completed. Contractor is scheduled to cut in rumble stripes and place final pavement marking this week. Both of these operations will be mobile but brief stoppages may occur to facilitate this work. Motorists are encouraged to obey posted speed limit and watch for construction signs and equipment. Estimated project completion date is November 2018.
[Rogers Group, Inc./Moore/CNS178]

 

OVERTON COUNTY SR-52 grading, drainage, signals and paving from near Oakley-Allons Road (LM 6.58) to SR-111 (LM 10.23):   Contractor will be on site to perform miscellaneous work as required to complete project. Shoulder closures may be used to accommodate this work. Motorists should obey speed limit and watch for construction equipment. Estimated project completion date is September 2018.
[J & M Grading Division LLC/Moore/CNP114]

 

WHITE COUNTY The resurfacing on US-70 (SR-1) from LM 7.69 to LM 10.61; US-70 (SR-26) from LM 9.82 to LM 10.79; and SR-84 from US-70 (SR-1) LM 0.00 to LM 0.12 :   Contractor is currently replacing sidewalk along SR-1, and performing milling operations throughout the project. Motorist should expect temporary lane closures and traffic stoppages during this time. Flaggers will be present to assist with traffic control as needed. Motorists are advised to observe the posted speed limits when entering the work zone, and to be alert of all construction personnel, equipment and vehicles. Estimated project completion date is September 2018.
[Rogers Group, Inc./Cookeville/CNS917]

 

WHITE COUNTY US-70 (SR-26) intersection improvements at SR-111 in Sparta:   SR-26 eastbound is reduced to one lane near the SR-111 northbound off-ramp. The contractor will be installing new permanent signs and cleaning up the work site in the vicinity of the SR-26/SR-111 Northbound intersection. Motorists can expect temporary intermittent lane closures during this time. Motorists should be alert and use caution around construction personnel and equipment. Estimated project completion date is September 2018.
[Rogers Group, Inc./Cookeville/CNS904]

 

DISTRICT 28

 

BLEDSOE COUNTY The resurfacing (microsurface or thin mix overlay) on SR-30 from the Van Buren County line (LM 0.00) to east of Bob Sapp Road (LM 5.58):   The contractor will be spraying fog seal on the shoulders and installing thermoplastic lines and snowplowable markers. The road will be reduced to 1 lane controlled by flagging when workers are present. Estimated project completion date is September 2018.
[Hudson Construction Co./Voiles/CNS016]

 

BLEDSOE AND VANBUREN COUNTY SR-284 resurfacing from east of SR-111 to the four-way stop near Park Road:   Contractor will be installing snow plow-able markers and thermoplastic lines. Road will be reduced to one lane controlled by flagging and a pilot car. Estimated project completion date is September 2018.
[Tinsley Asphalt, LLC/Voiles/CNS017]

 

CANNON COUNTY TDOT Maintenance on SR-145 (AUBURNTOWN RD.) southbound from LM 0.1 to LM 9.0:   Bridge Repair will be sealing the cracks in the roadway from Woodbury to Auburntown on SR145 on Wednesday and Thursday, September 5th and 6th.

 

FRANKLIN COUNTY SR-127 the construction of a concrete bulb-tee beam bridge over the Elk River (LM 6.21), including grading, drainage and paving:   Work on this project continues. RESTRICTIONS: Bridge will be reduced to one 10.5’ lane and controlled with a temporary traffic signal until further notice. Estimated project completion date is December 2018.
[Simpson Construction Company, Inc./Hussein/CNR044]

 

FRANKLIN COUNTY SR-476 bridge repair over the Elk River (LM 3.39) and Hurricane Creek (LM 7.40):   The project is in progress. RESTRICTIONS: The bridge is reduced to one 9’ lane and controlled with a temporary traffic signal until further notice. Estimated project completion date is October 2018.
[Mid-State Construction Company, Inc./Hussein/CNQ930]

 

GRUNDY COUNTY I-24 sliplining of culverts at various locations between mile markers 129 and 134:   The contractor will be working on the sliplining project on I-24 of culverts at various locations between MM 129 and 134. This work will be taking place Monday - Friday 7 AM - 5 PM. During this time there will be no outside shoulder.  Estimated project completion date is September 2018.
[CHASE RELINE, INC./Hussein/CNR320]

 

GRUNDY COUNTY SR-50 slide repair at log mile 9.9:   Slide repair is underway on SR-50, in Grundy County from the 9.4 MM to the 10.0 MM. The roadway is reduced to one lane. Temporary traffic lights are controlling traffic. Estimated project completion date is September 2018.
[Maintenance/MAINT]

 

GRUNDY COUNTY SR-108 resurfacing from SR-56 (LM 12.02) to west of Eagle Lake Road (LM 15.00), including addition of a turn lane:   The contractor will be constructing an additional turning lane and resurfacing SR 108 at this location. There will be shoulder closures as the additional turning lane is constructed. When resurfacing operations begin, SR 108 will be reduced to one lane controlled by a flagging operation. Estimated project completion date is November 2018.
[Tinsley Asphalt, LLC/Voiles/CNS250]

 

MARION COUNTY I-24 miscellaneous safety improvements from SR-156 (MM 161) to the Georgia State line (MM 167):   Beginning August 19 and continuing through September 28th, the Contractor will be working on I24 East bound and West bound between the Tennessee Line in Hamilton County and Exit 161 in Marion County. The work will be conducted from Sunday night through Friday morning starting at 8PM Central and ending at 5AM Central Time each morning. The contractor will have intermittent lane closures throughout the night as they delineate the guardrail and installs new signs.  Estimated project completion date is October 2018.
[Superior Traffic Control/Voiles/CNS236]

 

MARION COUNTY I-24 WB resurfacing from the Grundy County line (MM 127) to east of the bridge over Cave Cove Creek (MM 134):   The resurfacing will continue on this project. The contractor will have lane closures in order to perform the necessary work. These closures will take place on the interstate nightly with State Trooper support on Sundays through Fridays between the hours of 7PM and 6AM. Motorists should use extreme caution and be alert to construction equipment and workers. Safety personnel will be present. Estimated project completion date is September 2018.
[Rogers Group, Inc./Hussein/CNS914]

 

MARION COUNTY TDOT Maintenance on I-24 both directions from MM 160.1 to MM 160.1:   Bridge Inspection I-24 over Nickajack Lake. Monday, September 10, 2018: Begin lane closure at 9:00 AM CST I-24 Eastbound Lanes, Bridge over Tennessee River (Milepost 160.14) (Close right lane) Tuesday, September 11, 2018: Begin lane closure at 9:00 AM CST I-24 Westbound Lanes, Bridge over Tennessee River (Milepost 160.14) (Close right lane)

 

MARION COUNTY TDOT Maintenance on I-24 eastbound from MM 160.0 to MM 161.0:   Bridge repair will be performed beginning Thursday, 09/6/18 through Wednesday,09/12/18 from 6 AM-5PM, weekdays, causing roadway to be reduced to one lane.

 

MARION COUNTY TDOT Maintenance on I-24 westbound from MM 144.4 to MM 145.2:   Resurfacing of the slow lane and shoulder will have traffic reduced to 1 lane. from 6 PM 09/11/18 to 6 AM 09/12/18 and from 6 PM 09/12/18 to 6 AM 09/13/18

 

MARION COUNTY TDOT Maintenance on I-24 westbound from MM 160. to MM 161.0:   Bridge repair will be performed beginning Thursday, 09/6/18 through Wednesday,09/12/18 from 6 AM-5PM, weekdays, causing roadway to be reduced to one lane.

 

MARION COUNTY TDOT Maintenance on SR-2 (US-HWY. 41) eastbound from LM 21.1 to LM 21.1:   BRIDGE INSPECTION: Wednesday, September 12, 2018: Begin lane closure at 9:00 AM CST SR-2, Bridge over Tennessee River (Log Mile 21.14) (Close eastbound shoulder)

 

MARION COUNTY SR-156 over Running Water Creek (LM 25.58) bridge rehabilitation:   SR-156 is reduced to one lane across Running Water Creek Bridge and controlled by a temporary traffic signal while bridge is repaired.  Estimated project completion date is October 2019.
[Mid-State Construction Company, INC/Voiles/CNS905]

 

SEQUATCHIE COUNTY US-127 (SR-8) resurfacing from the Hamilton County line (LM 0.00) to north of Progress Drive (LM 5.22):   The resurfacing operation is ongoing. The contractor will be working during daytime hours, and SR 8 will be reduced to one lane while workers are present. Estimated project completion date is September 2018.
[Rogers Group, Inc./Voiles/CNS103]

 

WARREN COUNTY Utility Work on SR-127 (SHELLSFORD RD.) southbound from LM 1.1 to LM 3.1:   Intermittent lane closures and delays, signage and flaggers will be present between Hwy 108 and Woodlee Ct. for installation of aerial and buried fiber. Beginning: 9/6/18 Ending: 10/8/18 between 9am and 3pm. [UO-2007051662-2018]

 

WARREN COUNTY SR-288 construction of a concrete bulb-tee beam bridge over Collins River (LM 4.97), including grading, drainage and paving:   The bridge is currently reduced to one 12-ft. lane to allow the contractor to construct the new bridge. While the bridge is down to one lane, traffic will be maintained and controlled by a temporary signal for the safety of the traveling public. Motorists should expect periodic delays and use caution in the work zone. RESTRICTIONS: Reduced to one 12-ft lane.
[Palmertree Construction Company, LLC/Parnham/CNQ270]

 

WARREN COUNTY SR-56 Resurfacing from SR-56 from north of Pike Hill Road (LM 15.43) to south of the Dekalb County line (LM 24.45):   Contractor will begin resurfacing operations on 9/10/18. This work will result in the road being reduced to 1 lane during day time hours. While work is ongoing, traffic will be controlled by a flagging operation and a pilot car, to assist the motoring public.  Estimated project completion date is September 2018.
[Tinsley Asphalt, LLC/Parnham/CNS226]

 

WARREN COUNTY SR-8 over Collins River (LM 8.14) Bridge Repair:   The bridge is currently reduced to one 11-ft. lane to allow the contractor to repair the existing bridge. While the bridge is down to one lane, traffic will be maintained and controlled by a temporary signal for the safety of the traveling public. Motorists should expect periodic delays and use caution in the work zone. RESTRICTIONS: One 11-foot lane. Estimated project completion date is August 2019.
[Jamison Construction/Parnham/CNS254]

 

DISTRICT 29

 

BRADLEY COUNTY SR 60 resurfacing from the Georgia State line (LM 0.0) to north of Helms Lane SE (LM 3.8):   The contractor will possibly have temporary lane closures as the contractor will be working on installing the permanent pavement markings on this project. During these activities, there will be a moving traffic control as work is being done. Estimated project completion date is November 2018.
[Talley Construction Company, Inc./Curtis/CNS175]

 

HAMILTON COUNTY I-75 North Exit 1 interchange reconfiguration project at mile marker 1:   Work on this project continues. There is now only one exit ramp that allows drivers to turn both east and west on Ringgold Road at a signalized intersection. Traffic has been shifted onto the newly constructed portion of Camp Jordan Pkwy., and the intersection (I-75 NB off-ramp and SR-8/Camp Jordan Pkwy.) is now controlled by a traffic signal. Estimated project completion date is September 2018.
[C.W. Matthews Contracting/City Of East Ridge/LCLPRGM]

 

HAMILTON COUNTY US-27 (I-124) widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:   Work on this project continues with numerous activities occurring in the median of US-27. Motorists should be alert for construction vehicles entering and leaving the left traffic lane in both the northbound and southbound directions. The 12th Street tie-in ramp to US-27 South has been temporarily closed. This closure will be in place through 09/18. Detours are posted. Motorists should exercise caution when traveling through the construction zone and pay close attention to the detour signage posted. The speed limit on US-27 in the construction zone remains 45 MPH. Weather permitting, the contractor may implement temporary lane/shoulder closures on weeknights between the hours of 7 PM and 6 AM. At least one lane will remain open in each direction on US-27. THP will assist with traffic control on the project as necessary. RESTRICTIONS: Northbound US-27 off-ramp Exit 1C to 4th Street is restricted to a maximum width of 11 Feet. Estimated project completion date is January 2020.
[Dement Construction Company, LLC/Micka/CNP230]

 

HAMILTON COUNTY TDOT Maintenance on I-24 both directions at MM 183.2:   Removal of concrete forms from 9PM 9/10/18 to 2AM 9/11/18. Left lane will be closed.

 

HAMILTON COUNTY TDOT Maintenance on SR-29 (US-27) southbound at LM 22.5:   Right lane will be closed for erosion repair on 9/12/18

 

HAMILTON COUNTY US-127 (SR-8) slope repair of Signal Mountain Blvd. at log mile 15.9:   During this report period, the contractor will have one lane closed while performing slope stabilization operations. Temporary traffic signals are in place on either end of the project to control traffic. Additionally the speed limit has been lowered to 20 MPH in the construction zone. Additional flaggers will assist with traffic control as needed.  Estimated project completion date is September 2018.
[GSI/Maintenance/MAINT]

 

HAMILTON COUNTY SR-153 resurfacing from I-75 (LM 0.00) to Shallowford Road (LM 2.60), including bridge deck repair:   This project will involve nightly lane closures (8 PM to 6AM) to support the project activities. This will involve both NB & SB lane closures, Sunday through Thursday. Estimated project completion date is November 2018.
[Wright Brothers Construction Company, Inc./Micka/CNS251]

 

HAMILTON COUNTY SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:   During this report period, the contractor will have intermittent lane closures between 9AM-2PM. This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Bel-Air Road. Flaggers will assist with traffic control as needed.  Estimated project completion date is October 2018.
[Jones Bros. Contractors, LLC/Pruett/CNN383]

 

HAMILTON COUNTY US-11/64 SR-2 (Brainerd Rd./Lee Hwy.) resurfacing from east of Moore Road (LM 13.85) to east of Airport Road (LM 15.84):   The contractor has begun lowering manholes and catch basins. This will take place Monday through Friday between 9AM and 3PM. This work may affect either direction of US-11/64 (Brainerd Road/Lee Highway) between Moore Rd. and Airport Rd. The contractor will begin milling and paving on September 4th, after which the contractor will have intermittent lane closures for resurfacing operations Sunday through Thursday from 8PM to 6AM. Flaggers will assist with traffic control as needed Estimated project completion date is November 2018.
[Wright Brothers Construction Co., Inc./Pruett/CNS228]

 

MCMINN COUNTY SR-30, grading, drainage and paving on SR-30 from Jackson Street to east of Knight Road in Athens:   Traffic along SR-30 through the project's length has been restricted to one lane in each direction with turning lanes provided at critical intersections and business access. This phase one construction activity has all traffic on the previous westbound side of SR-30. All businesses are provided with accessibility. Beginning Thursday, Sept.6th, there will be a lane closure at Park St. that could have a minor impact on SR-30 traffic.  No additional lane closures are scheduled this reporting period. Estimated project completion date is October 2019.
[Talley Construction Company, Inc./Micka/CNR078]

 

MCMINN COUNTY I-75 resurfacing from south of SR-30 (MM 48.69/LM 13.75) to north of County Road 267 (MM 55.44/LM 20.50):   There will be lane closures at night from 7 PM-6 AM Sunday- Thursday night as the contractor works on paving the roadway on I-75 in the Northbound lanes first then moving to the Southbound lanes. There will be State Troopers out on the project during working hours. The speed limit has been changed from 70 MPH to 60 MPH in the project limits. Estimated project completion date is September 2018.
[Rogers Group, Inc./Curtis/CNS056]

 

MCMINN COUNTY SR-305 resurfacing from west of US-11 (SR-2) (LM 2.86) to west of I-75 (LM 5.00):   Starting on either Saturday or Monday of this reporting period, the contractor will start working on this project. There will be a lane closed on this project starting at LM 4.7(Sunoco Store) and going South during this reporting period. As the contractor works, there will be temporary closures of side roads in the areas that the contractor will be working. The traveling public needs to be aware of the flaggers and the traffic control on this project. Estimated project completion date is November 2018.
[Rogers Group Inc./Curtis/CNS187]

 

POLK COUNTY US-64 (SR-40) construction of a concrete bulb-tee beam bridge over Branch and TOHA Old Line railroad (LM 24.85), including grading, drainage and paving:   The contractor has cut the embankment for the retaining wall. The Pinecrest Road intersection has been closed. There are posted detour signs for residents to get to their homes on Pinecrest Road. This road will be closed during the duration of the construction of the Retaining Wall on US64. There will be intermittent lane closures on the project as trucks will be entering the road and the contractor will be working on utility lines that cross US64. Estimated project completion date is May 2019.
[Talley Construction Company, Inc./Curtis/CNQ900]

 

RHEA COUNTY Utility Work on SR-30 (WASHINGTON ST.) both directions from LM 12.4 to LM 12.8:   Short term lane closure with flaggers present to perform utility relocation between White Oak/New Union Rd. & Sky Drive beginning: 8/31/18 Ending: 9/21/18 from 8am to 3pm. [Pin: 109410.02]

 

RHEA COUNTY SR-29 Improvement at Cawood Road (LM 27.3) including grading, drainage, and paving; resurfacing from south of Vanns Creek Road/Hoyal Road (LM 23.4) to north of Haskel Road (LM 25.3):   Work on this project is scheduled to begin on Monday, September 10th. Lane Closures affecting both SB & NB traffic (LM 2.3 to LM 2.5, 9AM - 3PM) will be required to support restriping & temporary barrier rail installation. This activity should be completed in a day but consideration for weather necessitates permission for lane closure through Wednesday, September 12th.  Estimated project completion date is November 2018.
[Rogers Group, Inc./Micka/CNS935 ]

 

RHEA AND BLEDSOE COUNTY US-27 (Rhea Co.) and SR-30 (Bledsoe Co.) resurfacing:   The project limits include SR-30 from east of Porch Rock Road (LM 16.43) to the Rhea County line (LM 18.43) in Bledsoe County and US-27 (SR-29) from north of Black Oaks Estates Drive (LM 2.50) to north of SR-60 (LM 4.90) in Rhea County. The work on the Bledsoe project is suspended until later in the month; all milling & paving complete. Work continues on the Rhea County project (SR29) project. This is be a nighttime operation from 8 PM to 6 AM requiring lane closures. Estimated project completion date is October 2018.
[Rogers Group Inc./Micka/CNS123]

 

REGION WIDE

 

REGION 2 TDOT Maintenance drainage work:   There will be possible short-term lane and shoulder closures at various locations in Region 2 in order to clean rock and debris from ditches on an as-needed basis. One lane will be maintained at all times.
[TDOT Operations/Maintenance/R2MAINT]

 

REGION 2 TDOT Maintenance mowing and brush removal:   There will be possible short-term lane and shoulder closures at various locations in Region 2 in order to perform contract mowing and brush removal on an as-needed basis. In addition to performing the work, regional Operations crews will also provide traffic control.
[TDOT Operations/Maintenance/R2MAINT]

 

REGION 2 TDOT Maintenance pothole repair and pavement patching:   There will be possible short-term emergency lane closures at various locations in Region 2 in order to repair potholes and patch pavement on an as-needed basis. Depending on location and severity these repairs may be done during the day or at night. In addition to performing the work, regional Operations crews will also provide traffic control.
[TDOT Operations/Maintenance/R2MAINT]

 

REGION 2 on-call cable barrier repair on various interstate and state routes:   The contractor may have short term shoulder closures in order to perform cable rail repair. Both travel lanes will remain open to traffic at all times on the Interstate during any work that is performed.  Estimated project completion date is December 2018.
[RMD Holdings, LTD DBA Nationwide Construction Group/Parnham/CNR262]

 

REGION 2 on-call guardrail repair and new guardrail installation on various interstate and state routes:   The contractor may have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly from 7PM to 6AM Sundays through Thursdays and daily on State Routes. At least one travel lane will remain open to traffic at all times on the Interstate, and flaggers will be present on State Routes during any work that is performed.  Estimated project completion date is June 2019.
[Cumberland Guardrail, Inc./Parnham/CNS928]

 

REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System:   The contractor may have short term shoulder and/or lane closures in order to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. Work hours are 9AM to 3:30PM. At least one travel lane will remain open to traffic at all times. Flaggers will assist with traffic control as needed. Estimated project completion date is October 2019.
[NABCO Electric Company, Inc./Pruett/CNQ287]

 

REGION 2 sweeping and drain cleaning on various interstate and state routes:   There will be mobile lane closures supporting a sweeping operation along regional interstates and highways through this reporting period. Additionally, there will be a drain cleaning operation requiring lane closures along SR-111 (Hamilton,LM 0.0 to 4.9 & Sequatchie,LM 4.2 to LM 8.4) & SR-153 (LM 7.1 to LM 10.85) during this period. Both the sweeping & drain cleaning activities will happen Sunday - Thursday (8PM - 6AM) There will be mobile lane closures supporting a sweeping operation along regional interstates and highways through this reporting period. Additionally, there will be a drain cleaning operation requiring lane closures along SR-111 (Hamilton, LM 0.0 to 4.9 & Sequatchie, LM 4.2 to LM 8.4), SR-153 (Hamilton, LM 2.8 to LM 10.85) & SR-29 (Hamilton, LM 25.7 to LM 30.0) during this period. Both the sweeping & drain cleaning activities will happen Sunday - Thursday (8PM - 6AM).  Estimated project completion date is February 2019.
[Blevins Enterprises, Inc./Micka/CNR292]

 

REGION 2 On-call concrete pavement repair:   From Friday 09/07/18 at 9 PM through Monday 09/10/18 at 6 AM Vulcan Materials Company will be repairing concrete pavement on I-75 Northbound from MM 6.59 to MM 8.9 in lane #2. They will be sawing, removing, and repairing the concrete pavement. From Friday through Monday morning lanes number 1 and number 2 will be closed. The lanes will be opened back up no later than 6 AM ET on Monday 09/10/18. Highway Patrol and a truck mounted attenuator w/ message board will be on site during the project. Estimated project completion date is March 2019.
[Vulcan Materials/Voiles/CNS233]

 

REGION 2 On-call signing:   The contractor will be working on I 24 East and West bound between 177.0 and 185.0 mile marker from Monday 9/10 through Friday 9/14 from 8 pm to 6 am each night. All closures not to exceed 2 miles in length and 1 closure at a time per direction of travel. THP will assist with traffic control.  Estimated project completion date is June 2019.
[Superior Traffic Control/Voiles/CNS194]

 

REGION 2 The relensing of snowplowable pavement markers on various Interstate and State Routes:   Starting on Thursday of this reporting period, the contractor will start work on SR29 in Hamilton County and will be working on the State Routes in Hamilton County.  Estimated project completion date is November 2018.
[K & S Markers, Inc./Curtis/CNS092]

 
RESTRICTIONS

FRANKLIN COUNTY - CNR044: Bridge will be reduced to one 10.5’ lane and controlled with a temporary traffic signal until further notice.

FRANKLIN COUNTY - CNQ930: The bridge is reduced to one 9’ lane and controlled with a temporary traffic signal until further notice.

WARREN COUNTY - CNQ270: Reduced to one 12-ft lane.

WARREN COUNTY - CNS254: One 11-foot lane.

HAMILTON COUNTY - CNP230: Northbound US-27 off-ramp Exit 1C to 4th Street is restricted to a maximum width of 11 Feet.

REGION 2 - CNR292: There will be mobile lane closures supporting a sweeping operation along regional interstates and highways through this reporting period. Additionally, there will be a drain cleaning operation requiring lane closures along SR-111 (Hamilton, LM 0.0 to 4.9 & Sequatchie, LM 4.2 to LM 8.4), SR-153 (Hamilton, LM 2.8 to LM 10.85) & SR-29 (Hamilton, LM 25.7 to LM 30.0) during this period. Both the sweeping & drain cleaning activities will happen Sunday - Thursday (8PM - 6AM).

Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity.

Information in this report is provided to the Department of Transportation by the contractors. Most work is weather dependent and subject to change due to inclement weather. All times are local.

From your desktop or mobile device, get the latest construction activity and live streaming SmartWay traffic cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any land-line or cellular phone for travel information, or follow us on Twitter at www.twitter.com/TN511 for statewide travel or Chattanooga area alerts @Chattanooga511 or any of TDOT's other Twitter pages. As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for your destination. Drivers should never tweet, text, or talk on a cell phone while behind the wheel.

In 2016, the Tennessee Department of Transportation lost three workers in the line of duty. All three were struck by passing motorists. Those tragedies bring the total number of TDOT lives lost to 112. We don't want to lose another member of our TDOT family. We're asking you to WORK WITH US. To learn more, go to the website at https://www.tn.gov/tdot/work-with-us/.