S-GRC-4

GUARDRAIL CONNECTION TO BRIDGE RAILING CONCRETE PARAPET
S-GRC-4

(Click image to open PDF)

Latest Revision Note

07/07/2023    GENERAL NOTE (J) WAS ADDED.

Related Standard Drawings

DRAWINGDESCRIPTIONREMARKS
D-FLU-2BRIDGE END DRAIN FLUME DETAILSWHEN BRIDGE END DRAIN FLUME IS REQUIRED, USE 12 INCH DEEP BLOCK-OUTS SEE STANDARD DRAWINGS FOR DETAILS
D-FLU-2ABRIDGE END DRAIN FLUME DETAILSWHEN BRIDGE END DRAIN FLUME IS REQUIRED, USE 12 INCH DEEP BLOCK-OUTS SEE STANDARD DRAWINGS FOR DETAILS
S-GR31-1W-BEAM GUARDRAILFOR ALL OTHER GUARDRAIL DETAILS AND MATERIAL PROPERTIES NOT SHOWN
S-GR31-1AW-BEAM BARRIER FASTENING HARDWAREFOR BLOCK-OUT DETAILS
S-GR31-1CGUARDRAIL GENERAL NOTES AND POST DETAILSFOR THRIE BEAM POST DETAILS
S-PL-1SAFETY PLAN AT ROADSIDE HAZARDSVARIABLE LENGTH INCREMENT TO MEET LON
S-PL-3SAFETY PLAN: MINIMUM INSTALLATION AT BRIDGE ENDSFOR MINIMUM INSTALLATION AT BRIDGE ENDS
S-SSMB-6FSINGLE GUARDRAIL ATTACHMENT TO SINGLE SLOPE 51” BARRIER WALLFOR CONNECTION TO CONCRETE MEDIAN BARRIER WALLS
STD-1-SERIES"NEW STRUCTURES" STRUCTURE STANDARD DRAWINGSFOR BRIDGE RAILING DETAILS

Related Item Numbers

ITEM NO.U/MDESCRIPTIONREMARKS
705-06.01L.F.W BEAM GR (TYPE 2) MASH TL3 
705-06.20EACHTANGENT ENERGY ABSORBING TERM MASH TL-3 
705-06.25EACHTHRIE BEAM BRIDGE TRANSITION MASH TL-3 

Archived Standard Drawings

DATES OF EACH ARCHIVED DRAWINGS ( THE INITIAL STANDARD DRAWING IS BOLD )
06-28-2019 | 02-28-2020 | 10-16-2020 | 06-15-2021 | 07-07-2023
If you find any mistakes, missing information or have a question, contact:
TDOT CADD Support
1200 James K. Polk Building
Nashville, TN 37243-1402
TDOT.CADDSupport@tn.gov

This Page Last Updated: June 6, 2025 at 1:11 PM