Roadway Activity Report for parts of East and Middle Tennessee (April 6-13, 2022)

Friday, April 08, 2022 | 10:16am



CUMBERLAND COUNTY SR-28 (US-127) bridge
construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road
(LM 22.7): Construction signs and erosion control
measures have been installed. The contractor continues grading activities
which will include embankment fill, storm drain installation, and placement
of graded solid rock. Temporary lane closures and/or periodic traffic
stoppages will be necessary for construction activities. Utility relocations
for gas, water, sewer, and electric are in progress. Motorists should use
caution while traveling through the work zone and be aware of reduced speed
zones.

[Jones Bros. Contractors, LLC/Crossville/CNV009]


CUMBERLAND COUNTY I-40 Permitted Work eastbound
at MM 320: Buc-ee’s contractor to continue work along
Exit 320 Eastbound Off-Ramp along the outside shoulder. Ramp lane width is
reduced. Drivers should reduce speed when exiting I-40.

CUMBERLAND COUNTY SR-24 (US-70 N.) Utility Work
both directions from LM 14.71 to LM 15.84: Mobile
lane closures along SR-24 between Eureka Drive and Maryetta Street. Motorists
should reduce speed and be prepared to stop. Trucks, signage, cones, and
flaggers will be present, 03/24/22 through 04/29/22 from 8 am – 3 pm.
[2022-148]

CUMBERLAND COUNTY SR-24 (US-70 N.) Utility Work
both directions from LM 5.67 to LM 14.71: Mobile
lane closures along SR-24 between Little Randolph Road and Eureka Drive.
Motorists should reduce speed and be prepared to stop. Trucks, signage,
cones, and flaggers will be present, 03/24/22 through 04/29/22 from 8 am – 3
pm. [2021-731]

CUMBERLAND COUNTY SR-298 (GENESIS RD.) Utility
Work both directions from LM 10.26 to LM 13.74: Mobile
lane closures along SR-298 between Potato Farm Road and Roy Taylor Road.
Motorists should reduce speed and be prepared to stop. Trucks, signage,
cones, and flaggers will be present, 03/10/22 through 04/27/22 from 8 am – 3
pm. [2021-801]

CUMBERLAND COUNTY SR-462 from SR-28 (US-127N /
LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Interstate
Drive is closed from Stout Drive to Genesis Road. The detour is posted with
temporary traffic signals at the intersection of Woodlawn Road and Genesis
Road. Grade work and utility relocation activities for water and sewer are in
progress. Construction activities are also in progress for the adjoining
Buc-ee's project. Activities will require temporary lane closures and/or
traffic stoppages on Interstate Drive and Genesis Road as well as short term
closures of City streets. Motorists should use caution while traveling
through the work zone and be aware of reduced speed zones on Interstate
Drive.

[Rogers Group, Inc./Crossville/CNV010]


CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127)
widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): Contractor
will be continuing work on the bridge repair located on SR 28 at LM 30.50 in
Cumberland County. Motorists are encouraged to use caution and obey posted
speed limit through the work zone. Contractor also will be mobilizing
equipment along SR 28 in Cumberland County to begin work clearing along the
new alignment. Motorists are encouraged to use caution through the work zone
and watch for construction equipment adjacent to roadway.

[Jones Bros. Contractors, LLC/Moore/CNV300]

DEKALB COUNTY SR-26 (US-70) grading, drainage,
and construction of retaining walls and paving from near SR-53 (LM 2) to near
SR-96 (LM 6.1):  Contractor continues roadside grading
operations, installing erosion control measures, and water, gas, and electric
line relocation. This will result in intermittent lane closures. Blasting
operations may also result in brief road closures. Motorists are advised to
use caution and be alert to all construction signage while traveling through
the work zone.

[Twin K Construction/James/CNV012]

DEKALB AND WARREN COUNTY SR-56 construction of
bridges and paving from south of Warren-Dekalb County line (LM 24.5) to East
Bryant St. (LM 2.9): The contractor will shift traffic from SR-56
onto the new alignment section between LM 24.4 in Warren County through LM
1.0 in Dekalb County on 04/12/22. Traffic utilizing Sink Creek Road will be
detoured onto the new alignment. Motorist should follow posted signs in the
area. The contractor will continue installing concrete box culverts and
drainage structures. Grade work, bridge work, paving operations, and utility
work on the new roadway alignment are ongoing. The contractor will utilize
flagging operations throughout the project for grading operations. Traffic is
shifted onto the detour between SR-288 and Old Blue Springs Road for the
contractor to complete grade work in the area. Traffic shifts in Smithville
will remain from South College Street to the end of project to allow
contractor to complete work. Motorists should use caution through the area
while flaggers are present to direct traffic. The speed limit has been
reduced to 45 mph in the construction zone. Motorists should use caution in
this area

[Jones Bros. Contractors, LLC/Harris/CNT011]

FENTRESS COUNTY SR-85 slide repair project: Roadway
at 6.4 MM is reduced to one lane and is controlled by traffic lights.

[TDOT/Maint - Crossville/MAINT]

OVERTON COUNTY SR-111 (BYRDSTOWN HWY.) Utility
Work both directions from LM 15.65 to LM 17.53: Shoulder
and single lane closures from Garrett Mill Road to Big Springs Road.
Motorists should reduce speed and be prepared to stop. Trucks, signage,
cones, and flaggers will be present, 03/31/22 through 04/14/22 from 8 am – 3
pm. [2022-185]

OVERTON COUNTY SR-111 (COOKEVILLE HWY.) Utility
Work both directions at LM 4.94: Temporary lane closures and traffic stoppages
between Park Road and West Howard Road. Law enforcement will be on-site to
assist along with message boards trucks and signage. Motorists should be
prepared to stop and use caution traveling through work zone area and be
aware of equipment and personnel. 04/11/2022 from 8:30 am - 02:30 pm.
[2022-048]

OVERTON COUNTY SR-85 (HILHAM HWY.) Utility Work
both directions from LM 4.52 to LM 3.2: Mobile lane closures along SR-85 between Old
Standing Stone Road and Jerry Bilbrey Lane. Motorists should use caution and
be aware of personnel and equipment when traveling through the work zone.
Signage, cones, and flaggers will be present, 02/17/22 through 04/17/22 from
9 AM and 2 PM. [2021-457]

PUTNAM COUNTY SR-136 construction from north of
the SR-111 interchange to south of the I-40 interchange: The
contractor continues grading activities throughout the project. Temporary
lane closures and/or periodic traffic stoppages will be necessary for
construction activities including installation of barrier rail. Utility
relocations for gas are in progress. Motorists shall use caution while
traveling through the work zone and be aware of construction personnel.

[Rogers Group, Inc./James/CNV284]


PUTNAM COUNTY SR-135 (BURGESS FALLS RD.)
Utility Work both directions from LM 3.25 to LM 5.57: Shoulder
and single lane closures from Cane Creek Road to the intersection of
Cookeville Boatdock Road and Burgess Falls Road. Motorists should reduce
speed and be prepared to stop. Trucks, signage, cones, and flaggers will be
present, 02/17/22 through 05/17/22 from 9 am – 2 pm. [2021-771]

PUTNAM COUNTY SR-164 (S. Chestnut St) at LM 0.3
and SR-84 (S. Holly St) at LM 9.7 railroad crossing improvements: Contractor
will be on site installing erosion control measures throughout project and
will be beginning work on installing the new signal footers. Motorists are
encouraged to use caution through the work zone and watch for construction
equipment and personnel adjacent to the roadway.

[Stansell Electric Company, Inc./Moore/CNV072]


PUTNAM COUNTY SR-24 (US-70N) construction at
the intersection of SR-56 (LM 11.6) in Baxter: Contractor
will be on site installing erosion control measures. Motorists are encouraged
to use caution through the work zone and to watch for construction equipment
and personnel adjacent to the roadway.

[Rogers Group, Inc./Moore/CNV098]

PUTNAM COUNTY SR-24 (US-70N) slide repair near
LM 30.1: The contractor has installed barrier rail and
will continue retaining wall construction. Traffic will be reduced to one
lane and controlled by temporary traffic signals at each end of the project.
Be prepared to stop when traveling through the work zone.

[Rogers Group, Inc./James/CNU359]

DISTRICT 28

BLEDSOE COUNTY SR-101 Utility Work both
directions from LM 0 to LM 9.44: Mobile lane closures along SR-101 between
intersection of SR-30 / SR-101 and ending at intersection of SR-101 / Brewer
Road. Motorists should use caution and be aware of personnel and equipment
when traveling through the work zone. Signage, and flaggers will be present,
02/03/22 through 04/20/2022 from 9 AM and 2:30 PM. [2021-358]

CANNON AND WARREN COUNTY SR-1 (US-70S) bridge
repair and paving from east of Lincoln Lane (LM 11) in Cannon County to Robinson
Road (LM 9.4) in Warren County: The contractor is scheduled to resume
resurfacing work on 04/11/22. This work will include lane closures throughout
the project. Motorist should use caution in the area

[American Pavements, Inc./Harris/CNV075]

COFFEE COUNTY SR-2 (US-41) at SR-55
(McMinnville Highway) intersection improvements in Manchester (LM 14.7): Project
activity progression will continue daily with various roadway construction
activities being performed. Motorists should proceed with caution through the
area and be aware of signage, personnel, and equipment.

[Rogers Group, Inc./Hussein/CNU006]

COFFEE COUNTY I-24 TDOT Bridge Maintenance
eastbound at MM 124.6: Region 2 Bridge Repair will be performing
maintenance on the Betsy Willis Road bridge over I-24 at exit 124, Monday,
4/11/22, from 9AM-3PM CST. Eastbound Traffic on I-24 will be affected.

COFFEE COUNTY SR-55 (MCMINNVILLE HWY.) TDOT
Bridge Inspection westbound at LM 14.03: Bridge
Inspection will be working at the bridge over Little Duck River. Motorists
should reduce speed and be prepared to stop. Trucks, signage, cones, and
flaggers will be present, 04/07/22 from 8:30 am – 2:30 pm.

COFFEE COUNTY SR-127 bridge construction over
Bradley Creek (LM 4.7): Construction work on this project will
continue this week. SR-127 at MM 4.66 will be closed until 09/30/2022 to
support bridge construction work over Bradley Creek. A detour route will be
provided via Prairie Plains Road and Miller Crossroads Road during
construction work, signs and message boards are in place to show the detour
route. Motorist should be alert to the new traffic pattern and encouraged to
use caution and be alert to construction personnel and equipment

[Dement Construction Company, LLC/Hussein/CNV303]

COFFEE COUNTY SR-2 (US-41) repair of bridge
over Blue Spring Creek (LM 21.0): Construction work on this project will
continue this week. The roadway will be reduced to one lane and control with
traffic signal. One lane will be open to traffic with the restriction of all
wide loads, the maximum lane width is 12’. Motorist should be alert to a new
traffic pattern and encouraged to use caution and be alert to construction
personnel and equipment.

[Mid-State Construction Company, Inc./Hussein/CNV145]

FRANKLIN COUNTY SR-50 (LYNCHBURG HWY.) TDOT
Bridge Maintenance both directions at LM 1.57: Bridge
Repair will be working at the bridge over Elk River. Motorists should reduce
speed and be prepared to stop. Trucks, signage, cones, and flaggers will be
present, 04/11/22 from 8:00 am – 3:00 pm

FRANKLIN COUNTY SR-56 (SHERWOOD RD.) Permitted
Work both directions at LM 0.1: Work on the CSX Railroad crossing will require
closure of the roadway from 4/08/2022 until 4/11/2022. A detour will be
posted. RESTRICTIONS: Roadway closed with detour

FRANKLIN COUNTY SR-15 (US-41) intersection
improvement at University Avenue (LM 27.9): Project
activity will continue daily. The roadway will be reduced from 4-lanes to
2-lanes. Motorists should proceed with caution through the area and be aware
of signage, personnel, and equipment.

[Dement Construction Company, LLC/Hussein/CNV062]

GRUNDY COUNTY SR-108 (MAIN ST.) TDOT
Maintenance both directions from LM 3.3 to LM 3.5: Traffic
is reduced to one lane with traffic signals. Work is being done to support
the roadway over failed pipes underneath.

GRUNDY COUNTY SR-399 (BAKERTOWN RD.) Utility
Work both directions from LM 0 to LM 4.61: Mobile
lane closures from the intersection of SR-108 and SR-399 to the Sequatchie /
Grundy County Line (near Lovell Road). Motorists should reduce speed and be
prepared to stop. Trucks, signage, cones, and flaggers will be present,
03/24/22 through 04/22/22 from 9 am – 3 pm. [2021-139 & 2021-596]

GRUNDY COUNTY SR-2 (US-41) TDOT Maintenance
both directions from LM 7.2 to LM 7.4: SR 2 Grundy County is reduced to one lane of
traffic for survey work on a slide. Traffic signals are in place

[TDOT/Maint - Dunlap/MAINT]

GRUNDY COUNTY SR-56 slide repair between LM
26.3 and LM 26.6: The road will remain one lane controlled by a
temporary traffic signal while contractor completes slide repairs in the
area. Motorists should use caution in the area.

[Dement Construction Company, LLC/Harris/CNU355]

MARION COUNTY I-24 (US-64) rockfall mitigation
westbound between MM 136.2 and MM 140.3: The
contractor will be working on I-24 WB at MM 141 – 140, MM 139.0 – 137.0, and
MM 136.0 – 135.0. On Tuesday April 12 the contractor will be blasting rock on
I-24 WB at MM 137.0. This work will require a slow roll to slow traffic down
long enough to blast the rock and clean up the road if necessary. The slow
roll and blasting will begin at 11:00 AM CT and only last as long as it takes
to clear the road. Tennessee Highway Patrol and a truck mounted attenuator w/
message board will be on site during this work. The other remaining works
sites will remain open. Please use caution when traveling through the work
zones.

[Wright Brothers Construction Company, Inc./Voiles/CNV912]

SEQUATCHIE COUNTY SR-28 (HWY. 28) Utility Work
both directions from LM 1.73 to LM 2.98: Mobile
lane closures along SR-28 between Stove Cave Road and Frank Tate Road.
Motorists should reduce speed and be prepared to stop. Trucks, signage,
cones, and flaggers will be present, 03/24/22 through 06/01/22 from 9:30 am –
2:30 pm. [2022-128]

SEQUATCHIE COUNTY SR-8 (HWY. 8) Utility Work
both directions from LM 23.32 to LM 24.15: Mobile
lane closures along SR-8 between Dennis Road and Dogwood Drive. Motorists
should reduce speed and be prepared to stop. Trucks, signage, cones, and
flaggers will be present, 04/07/22 through 05/12/22 from 9:00 am – 2:30 pm.
[2022-172]

VAN BUREN COUNTY SR-30 (STATE HWY. 30) TDOT
Maintenance both directions from LM 15.4 to LM 15.6: Traffic
is reduced to one lane with traffic signals for slide repairs

WARREN COUNTY SR-380 (SPARTA ST.) Permitted
Work both directions at LM 2.6: Work on the Caney Fork & Western Railroad
bridge will require closure of the roadway from 3/31/2022 until 4/15/2022. A
detour will be posted. RESTRICTIONS: Roadway closed with detour.

DISTRICT 29


BRADLEY COUNTY SR-60 widening from the 4-lane
north of I-75 (LM 17.2) to SR-306 (LM19.9): During
this reporting period, the contractor will be performing earthmoving
operations and removal of structures. Crews will also be working on
foundations for a new bridge over Candies Creek. Brief, intermittent lane
closures are possible on SR-60 during daylight hours as this work occurs.
Motorists should expect daily lane closures Monday through Friday 9 AM to
3:30 PM at Georgetown Rd (SR-60) and Villa Drive to support the installation
of a new gas line. Motorists are advised to reduce speed in the work zone,
watch for flaggers assisting with traffic control and for trucks
entering/leaving the highway.

[Summers-Taylor, Inc./Wagner/CNV130]

BRADLEY COUNTY SR-2 (N. LEE HWY.) Utility Work
northbound at LM 14.10: Shoulder and single lane closures between
Hardwick Grove Dr NE and Commons Lane NE. Motorists should reduce speed and
be prepared to stop. Signage, cones, and flaggers will be present, 04/11/22
through 04/13/22 from 9 am – 3 pm. [2022-204]

BRADLEY COUNTY SR-311 (DALTON PK. S.E.) Utility
Work both directions from LM 5.41 to LM 5.3: ROAD
CLOSURE and DETOUR on Dalton Pike SE between Baldwin Road and Blackburn Road
from 9 am Monday through 4 pm Friday with the road reopening over the
weekend. Motorists should reduce speed and follow the detour signage.
Businesses and residences will be accessible in the detour area. Signage,
cones, and flaggers will be present, 04/11/22 through 05/02/22. [2021-816]

BRADLEY COUNTY I-75 at Exit 33 (SR-308,
Lauderdale Highway) bridge work and ramp upgrades:  There
are lane shifts in both the Southbound and Northbound lanes from MM 31 to MM
33. The lanes will be reduced to two 11-foot lanes in both directions as work
goes on this project.

[Wright Brothers Construction Company, Inc./Curtis/CNV124]

BRADLEY COUNTY SR-312 (HARRISON PK.) TDOT
Maintenance both directions from LM 3.1 to LM 3.2: TDOT
Maintenance forces have reduced SR-312 to a single lane controlled by a
temporary traffic signal due to a storm drainpipe failure. This closure will
remain in place until the pipe can be replaced.

[TDOT/Maint - Benton/MAINT]

HAMILTON COUNTY I-24 interchange improvement at
SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): Williams
Street is closed to all traffic at the I-24 underpass to support the
installation of new storm drainage structures for the new frontage road.
Traffic will still be able to access the ramps to I-24 and US-27, but no
through traffic will be allowed on Williams Street between West 21st Street
and West 25th Street. Traffic will detour around the closure via West 21st
Street and Broad Street. Signs will be posted. The contractor will be working
on new bridge construction, storm drainage structures, and utility
relocation. Chestnut Street is closed at the I-24 underpass and will remain
closed until the construction of bridge #2 is complete. Detour routes are
posted.

[Wright Brothers Construction Company, Inc./Curtis/CNU011]

HAMILTON COUNTY I-75 at I-24 Interchange
Reconstruction: Contractor will be working on ROW fencing and
should have no impact on traffic.

[C.W. Matthews Contracting Company, Inc./2001/DB1801]

HAMILTON COUNTY I-75 at I-24 Interchange
Reconstruction Phase 2: Geotechnical investigations will continue.
Shoulder closures are possible on I-24 with lane closures on North and South
Terrace as well. Additionally, there will be lane closures on I-75 at night
between 9PM and 6AM.

[TDOT/Maj Prj - Blevins/DB2101]

HAMILTON COUNTY I-75 concrete repair from MM
6.6 to MM 12.8: During this reporting period, there is a
possibility on Monday through Wednesday that the shoulder will be closed
periodically from MM 6.6 to MM 12.8 Northbound and Southbound.

[Summers-Taylor, Inc./Curtis/CNW046]

HAMILTON COUNTY SR-17 (GLASS ST.) Utility Work
northbound at LM 6.25: Shoulder closure between Awtry Street and
Campbell Street. Motorists should reduce speed and be aware of personnel. If possible,
recommend motorists to find an alternate route. Signage, cones, and flaggers
will be present, 03/28/22 through 04/13/22 from 9 am – 3 pm. [2022-071]

HAMILTON COUNTY SR-27 (ROSSVILLE BLVD.) Utility
Work both directions at LM 5.66: Shoulder and single lane closures between
Foust Street and E. 27th Street. Motorists should reduce speed and be
prepared to stop. Signage, cones, and flaggers will be present, 03/31/22
through 04/13/22 from 9 am – 2 pm. [2022-164]

HAMILTON COUNTY SR-319 (HIXSON PK.) Utility
Work both directions from LM 18.51 to LM 18.71: Shoulder
and single lane closures between Thatcher Road and Armstrong Road. Motorists
should reduce speed and be prepared to stop. Signage, cones, and flaggers
will be present, 04/11/22 through 04/22/22 from 9 am – 3 pm. [2022-025]

HAMILTON COUNTY SR-8 (TAFT HWY.) Utility Work
both directions from LM 22.01 to LM 22.2: Shoulder
and single lane closures between Fairmount Road and Dowler Lane. Motorists
should reduce speed and be prepared to stop. Signage, cones, and flaggers
will be present, 02/15/22 through 04/20/22 from 9 am – 2 pm. [2021-636]

HAMILTON COUNTY SR-317 (Apison Pike)
improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton
Lane: Lane closures and flagging operations will be
required on SR-317, Apison Pike, to install power poles and transfer lines.
The flagging operations will be performed on 04/07/22, 04/08/22, 04/11/22,
04/12/22, and 04/13/22 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last
about 2 hours per location. The contractor will have intermittent flagging
operations during daytime non-peak hours for utility work, delivery of
materials and equipment. A portion of Tucker Road has been closed from
Spalding Drive to 5400 Tucker Road to allow for grading and utility
operations.

[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]

HAMILTON COUNTY SR-319 (Amnicola Highway)
bridge repair over SR-153: Contractor will be performing bridge repair
operations on the Amnicola (SR-319) bridge over SR-153. During this project,
SR-319 will have lane closures in place. During repair operations at least
one lane of traffic shall remain open in both directions. Motorists are
advised to use caution in this vicinity and remain aware of construction activities.

[Mid-State Construction Company, Inc./Osbonlighter/CNV053]

HAMILTON COUNTY The construction of an S.I.A.
to VW: The contractor will be performing operations
at the intersection connecting the S.I.A. route, Ferdinand Piech Way, & Volkswagen
Dr. The new 4-way signalized intersection has begun operation & traffic
has been shifted to the new alignment. Ferdinand Piech Way will still be
closed to through traffic. Traveling public should be cautious of the new
traffic pattern in effect including a lowered speed limit. The traveling
public should also be alert to the entrance and exit of construction vehicles
& staff on and around the jobsite and the connecting roadways. Flaggers
may be onsite directing traffic.

[Talley Construction Company, Inc./Osbonlighter/CNU221]

MCMINN COUNTY SR-310 bridge repair over
Conasauga Creek (LM 4.4): During this reporting period, the contractor
will be working on placing new asphalt overlays on the bridge. SR-310 is
reduced to a single lane controlled by a temporary traffic signal to support
this work. Motorists are asked to reduce speed in the work zone and obey all
traffic signals and related signage. RESTRICTIONS: 10-foot horizontal
clearance

[Southern Constructors, Inc./Wagner/CNV301]

MEIGS COUNTY SR-304 repair of bridge over Big
Sewee Creek (LM 4.8): Contractor will be performing bridge repair
operations on the SR-304 bridge over Big Sewee Creek. During this project,
SR-304 will have lane closures with 10ft width restrictions. A detour will be
in place redirecting SR-304 truck traffic onto Watts Bar Hwy & SR-58.
During repair operations, only one lane of traffic shall remain open for
local traffic. A temporary traffic signal shall be in place to direct traffic
thru the construction zone.

[Mid-State Construction Company, Inc./Osbonlighter/CNV305]

POLK COUNTY SR-315 (TELLICO-RELIANCE RD.) TDOT
Bridge Inspection both directions from LM 0.0 to LM 0.2: On
Tuesday, 04/12/22 and/or Wednesday, 04/13/22, a flagging operation will take
place on the bridge over the Hiwassee River. The operation will occur between
8 AM and 5 PM.


POLK COUNTY SR-33 (HWY. 411) TDOT Bridge
Inspection both directions from LM 1.9 to LM 2.2: On
Tuesday, 04/12/22 and/or Wednesday, 04/13/22, one lane will be closed each
direction on the bridges over the Hiwassee River. The closures will be in
place between 8 AM and 5 PM.

POLK COUNTY SR-40 (US-HWY. 64) TDOT Bridge
Inspection both directions from LM 24.8 to LM 25.0: On
Tuesday, 04/12/22 and/or Wednesday, 04/13/22, a flagging operation will take
place on the bridge over the railroad and branch. The operation will occur
between 8 AM and 5 PM.

POLK COUNTY SR-40 (US-64) bridge over the Ocoee
River: During this reporting period, the contractor
will be working on the construction of the new bridge deck and the relocation
of water lines. Brief intermittent lane closures are possible on US-64
(SR-40) Monday through Friday 8 AM to 5:30 PM as the contractor works to
relocate utility lines on the project. Motorists are asked to reduce speed in
the work zone and watch for trucks entering/leaving the highway.

[Charles Blalock and Sons, Inc./Wagner/DB1802]

RHEA COUNTY SR-378 resurfacing from SR-29
(US-27 / LM 0.0) to west of SR-29 (US-27 / LM 1.61) and SR-30 from east of Railroad
Street (LM 8.7) to near SR-29 (US-27 / LM 9.2): During
this reporting period, there will be intermittent lane closures on both
SR-378 and SR-30 during the day as the contractor works on this project.
Expect possible long delays as flaggers will be directing traffic on this
project.

[Rogers Group, Inc./Curtis/CNV100]

RHEA COUNTY The grading, drainage, construction
of bridges, paving and signals on a S.I.A. route serving Nokian Tyres: :
Construction activity at the Nokian Tyres SIA project continues just North of
Dayton, TN. The traveling public should be alert to construction vehicles
entering and exiting the site. SR-29 traffic has been moved back in its
normal traffic pattern.

[Dement Construction Company, LLC/Curtis/CNU014]

REGION WIDE

REGION 2 preventative and unscheduled
maintenance of Chattanooga SmartWay Intelligent Transportation System: The
contractor may have short term shoulder and/or lane closures to perform
preventative or unscheduled maintenance to the local SmartWay Intelligent
Transportation System. At least one travel lane will always remain open to
traffic. Flaggers will assist with traffic control as needed.

[NABCO Electric Company, Inc./Osbonlighter/CNT354]

REGION 2 TDOT Maintenance drainage work: There
will be possible short-term lane and shoulder closures at various locations
in Region 2 in order to clean rock and debris from ditches on an as-needed
basis. One lane will be maintained at all times.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 TDOT Maintenance pothole repair and
pavement patching: There will be possible short-term emergency
lane closures at various locations in Region 2 in order to repair potholes
and patch pavement on an as-needed basis. Depending on location and severity
these repairs may be done during the day or at night. In addition to
performing the work, regional Operations crews will also provide traffic
control.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 TDOT mowing operations: There
will be possible short-term lane closures at various locations on interstates
and state routes in Region 2 in order to perform mowing activities on an
as-needed basis. In addition to performing the work, regional Operations
crews will also provide traffic control.

[TDOT/Maintenance/R2MAINT]

REGION 2 The on-call guardrail repair and new
guardrail installation on various Interstate and State Routes: The
contractor may have short term shoulder and/or lane closures in order to
perform guardrail repair. These closures will take place on the interstate
nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through
Friday on state routes. At least one travel lane will remain open to traffic
at all times on the interstate, and flaggers will be present on state routes
during any work that is performed

[Cumberland Guardrail, Inc./Harris/CNV112]

REGION 2 The on-call concrete pavement repair
on various interstates and state routes: During
the daytime the contractor will be repairing concrete pavement on the SR-111
on and off-ramps to SR-1 in White County. Half the width of the ramps will be
closed during construction. Please slow down and use caution when driving
through the work zone.

[Vulcan Construction Materials, LLC/Voiles/CNU373]


REGION 2 The random on-call cable barrier
repair on various Interstate and State Routes: The
contractor may have short term shoulder closures in order to perform cable
rail repair. Both travel lanes will always remain open to traffic on the
interstate during any work that is performed

[LU, Inc./Harris/CNV272]

REGION 2 The sweeping and drain cleaning on
various Interstate and State Routes: There will be an area wide sweeping operation
on selected regional state routes and interstates. This activity will be
supported by a mobile lane closure. Hours of activity are Sunday through
Thursday night between 8 PM and 6 AM during this reporting period.

[Blevins Enterprises, Inc./Curtis/CNV302]

RESTRICTIONS

FRANKLIN COUNTY - : Roadway
closed with detour

WARREN COUNTY - : Roadway
closed with detour.

MCMINN COUNTY - CNV301: 10-foot horizontal clearance

Motorists
are encouraged to use caution and obey reduced speed limits in all TDOT work
zones, regardless of lane closure activity.

Information in this report is
provided to the Department of Transportation by the contractors. Most work is
weather dependent and subject to change due to inclement weather. All times are
local.