Middle Tennessee Scheduled Lane Closures Sept. 18-24, 2025
CHEATHAM & ROBERTSON COUNTY I-24
The resurfacing on I-24 from the Robertson County line, crossing through Robertson County to the Davidson County line.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures in both directions for milling and paving operations (MM 25 – 31.6).
DAVIDSON COUNTY I-24
The resurfacing on I-24 from I-65 to I-40.
• Nightly, 9 p.m. – 5 a.m. (excluding weekends), There will be alternating lane closures in both directions for milling and paving operations.
The surfacing on I-24 from Haywood Lane to the Rutherford County line.
• Nightly, 8 p.m. – 5 a.m. (excluding Saturday), There will be alternating lane closures in both directions for sign installation, degrassing, milling, and paving.
MONTGOMERY COUNTY I-24
The resurfacing on I-24 from east of SR 13 (US-79) to west of Trough Springs Road.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures in both directions for rumble strips, thermoplastic, and pavement markings (MM 5 – 11.63).
RUTHERFORD COUNTY I-24
Fiber installation.
• 9/21, 6 a.m. – 10 a.m., There will be a rolling roadblock for installation of fiber at Waldron Road.
The interchange improvement on I-24 at Medical Center Parkway, including grading, drainage, paving, retaining wall and more.
• 9/24, 8 pm. – 5 a.m., There will be temporary lane and/or ramp closures on the off-ramps from I-24 to Medical Center Parkway for traffic switches and to install barrier wall.
The I-24 ramp improvements at US 231 (S. Church Street, Exit 81), including grading, drainage, signals, lighting, and paving.
• 9/18, 8 p.m. – 5 a.m., There will be inside lane closures in both directions for installation of lighting under US 231. There will be a single right lane closure on I-24 eastbound at mile marker 81.6 for lighting work.
• 9/21 – 9/22, 8 p.m. – 5 a.m., There will be a closure of the I-24 Exit 81 westbound off ramp, and a single outside right lane closure on I-24 due to relocating barrier wall and striping.
Pavement repair.
• 9/18, 8 p.m. – 5 a.m., There will be a closure of the shoulder, lane 1 and 2 from mile marker 63-64 on I-24 eastbound.
DAVIDSON COUNTY I-40
The grading, drainage, construction of bridges, retaining walls, and paving on SR 255 and I-40 at the Donelson Pike Interchange.
• Nightly, 8 p.m. – 4 a.m. (excluding weekends), There will be alternating triple lane closures on I-40 in both directions for pavement markings. Ramps will be temporarily closed as needed.
The repair of the bridge on I-40 over the Harpeth River including grading, drainage, and paving.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures in both directions on I-40 for bridge repair work (MM 194 – 196).
The resurfacing on I-40 from 46th Avenue to near Jefferson Street including bridge expansion joint repair.
• Nightly, 8 p.m. – 5 a.m. (excluding Saturday), There will be alternating lane closures on I-40 in both directions for milling, paving, and bridge work. There will be intermittent, temporary ramp closures to and from I-440 and SR 155 as needed.
Bridge inspection.
• 9/21 & 9/22, 8 p.m. – 5 a.m., There will be a closure of the westbound right lane on Exit 215A for bridge inspection.
• 9/22, 8 p.m. – 10 p.m., There will be a single lane closure in both directions to inspect a pier cap on SR 155 over I-40.
Survey.
• Nightly, 8 p.m. – 5 a.m., There will be inside lane closures in both directions for drain cleaning and survey work (MM 211 – 212.8).
DICKSON & HICKMAN COUNTIES I-40
The resurfacing of I-40 in Dickson and Hickman Counties from the Humphreys County line to near East Piney Road.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures in both directions for paving operations (MM 160.4 – 168.8).
HICKMAN & HUMPHREYS COUNTY I-40
Core sampling (MM 147.5 – 148.5).
• Daily, 8 a.m. – 4 p.m., There will be temporary shoulder closures with lane shifts on ramps.
• Nightly, 7 p.m. – 5 a.m., There will be a temporary lane and shoulder closures on I-40 in both directions for core sampling.
• 9/22, 7 p.m. – 5 a.m., There will be intermittent ramp closures for core sampling.
HUMPHREYS COUNTY I-40
SmartWay Intelligent Transportation System installation and maintenance.
• Nightly, 7 p.m. – 6 a.m., There will be alternating lane closures in both directions for the installation of fiber.
The repair of bridges on I-40 over Squeeze Bottom Road and Buffalo River Bridge.
• Nightly, 7 p.m. – 5 a.m., There will be a temporary lane closure on I-40 in both directions as needed.
DAVIDSON COUNTY I-65
Resurfacing on I-65 from near Armory Drive to I-40.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures on I-65 in both directions for striping and texture coat application. There will be intermittent, temporary ramp closures at Wedgewood Avenue, I-440, and Armory Drive for striping and detail work (MM 79 – 85).
Drain inlet cleaning.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures in both directions for median drain inlet cleaning (MM 88 – 95).
The resurfacing on I-65 from I-40 to near the Cumberland River bridge.
• Nightly, 8 p.m. – 5 a.m. (excluding weekends), There will be alternating lane clousres in both directions for striping and traffic loop installation.
DAVIDSON AND SUMNER COUNTIES I-65
I-65 widening and improvements from near Rivergate Parkway to near US 31W (SR 41).
• Daily, 9 a.m. – 3 p.m., There will be alternating lane closures on SR 174 (Long Hollow Pike) and US-31W for bridge work (MM 95 – 99). One lane will remain open in both directions.
• Nightly, 8 p.m. – 5 a.m., There will be lane closures on I-65 in both directions for construction activities (MM 95 – 99). There will also be intermittent ramp closures at SR 174 (Long Hollow Pike) and US-31W (SR 41) as needed.
• Nightly, (excluding weekends), 8 p.m. – 5 a.m., East Cedar Street will be closed for bridge construction activities.
MARSHALL COUNTY I-65
Aerial utility work.
• 9/21, 6 a.m. – 9 a.m., There will be a rolling roadblock along I-65 in both directions for aerial fiber installation at Charlie Thomas Road.
ROBERTSON & SUMNER COUNTY I-65
Shoulder repair.
• Daily, 9 a.m. – 4 p.m., There will be a temporary shoulder closure in both directions to repair the unpaved shoulder drop-off (MM 104 – 121.4).
ROBERTSON COUNTY I-65
Aerial crossing.
• 9/21, 6 a.m. – 9 a.m., There will be a rolling roadblock for aerial crossing near the intersection with SR 109.
DAVIDSON COUNTY I-440
Survey.
• Nightly, 8 p.m. – 5 a.m., There will be inside lane closures in both directions for survey and drain cleaning (5.8 – 7.5).
BEDFORD COUNTY SR 10
Intersection improvements on SR 10 (US 231) at SR 82.
• Daily, 9 a.m. – 3 p.m., There will be a closure of the inside left turn lanes and inside acceleration lanes for grading operations.
DAVIDSON COUNTY SR 1
Safety improvements including signals.
• Daily, 9 a.m. – 3 p.m., There will be lane closures on Hamilton Church Road in both directions for construction activities. One lane will remain open at all times.
Survey on SR 1 (Broadway).
• 9/22, 9 p.m. – 5 a.m., There will be westbound lane closures at First Avenue North for survey work.
• 9/23, 9 p.m. – 5 a.m., There will be eastbound lane closures near 4th Avenue South for survey work.
• 9/24, 9 p.m. – 5 a.m., There will be westbound lane closures near 9th Avenue South for survey work.
• 9/25, 9 p.m. – 5 a.m., There will be eastbound lane closures on SR 1 (West End Avenue) near 19th Avenue North for survey work.
DAVIDSON COUNTY SR 6
The resurfacing on SR 6 (Rosa L. Parks/James Robertson Parkway) from Broadway to the bridge over Ellington Parkway.
• Nightly (excluding weekends), 8 p.m. – 5 a.m., There will be alternating lane closures in both directions for paving operations.
DAVIDSON COUNTY SR 11
The widening of US 31A (SR 11, Nolensville Pike) from North of the Mill Creek bridge to SR 254 (Old Hickory Boulevard) including bridges, retaining walls, signals, and lighting.
• Daily, 9 a.m. – 3 p.m., There will be temporary road closures on SR 11 and associated side roads for utility relocation, grading, and drainage (MM 1.7 – 4.2).
• Continuous, There will be a continuous closure of Brooklawn Drive for utility relocation, grading, and drainage work. A detour will be in place.
Utility relocation.
• Daily, 9 a.m. – 3 p.m., and Nightly, 8 p.m. – 5 a.m., There will be lane closures in both directions for relocation of existing facilities prior to a TDOT project (MM 23.32 – 24.49). The center turn lane will also be closed.
DAVIDSON COUNTY SR 24
Ditch cleaning.
• 9/18, 9 a.m. – 3 p.m, There will be a single lane closure in both directions for ditch cleaning medians (MM 5).
DAVIDSON COUNTY SR 45
The improvement of the intersection on SR 45 (Old Hickory Boulevard) and Myatt Drive.
• Daily, 9 a.m. – 3 p.m. (excluding weekends), There will be intermittent single lane closures in both directions along SR 45 for signal installation and striping work.
DAVIDSON COUNTY SR 65
• Daily, 9 a.m. – 3 p.m., There will be an eastbound lane and shoulder closure for patch paving near Whites Creek Pike.
DAVIDSON COUNTY SR 155
The resurfacing on SR 155 from south of the NERR underpass to north of McGavock Pike.
• Nightly, 8 p.m. – 5 a.m. (excluding Saturday), There will be lane closures in both directions for milling and paving operations.
Pavement repair.
• 9/22 – 9/24, 8 p.m. – 5 a.m., There will be lane closures in both directions for pavement repair (MM 24 -26.6).
• LOOK AHEAD: 9/25, 8 p.m. – 5 a.m., There will be a single eastbound lane closure for milling operations (MM 18).
Bridge inspection.
• 9/21, 8 p.m. – 10 p.m., There will be a single lane closure in both directions for inspection of a pier cap.
• 9/22 & 9/23, 8 p.m. – 5 a.m., There will be a single southbound lane closure at Exit 6A for bridge inspection.
DAVIDSON COUNTY SR 254
The resurfacing on SR 254 (Old Hickory Boulevard) from Cloverland Drive to Blue Hole Road.
• Nightly, 8 p.m. – 5 a.m. (excluding Saturday), There will be lane closures in both directions for manhole adjustments, milling and paving operations.
DAVIDSON COUNTY SR 255
The grading, drainage, construction of bridges, retaining walls and paving on SR 255 and I-40 at the Donelson Pike Interchange.
• Daily, 9 a.m. – 3 p.m. (excluding weekends), There will be alternating lane and intermittent ramp closures on Donelson Pike for milling and paving operations.
MNAA TARI Phase.
• Daily, 9 a.m. – 3 p.m. (excluding weekends), There will be intermittent lane closures on Donelson Pike for removal of barrier wall.
DAVIDSON COUNTY SR 265
Pavement repair.
• Daily, 9 a.m. – 3 p.m., There will be lane and shoulder closures for patch paving near Lebanon Pike.
DICKSON COUNTY SR 1
Installation of turn lane.
• Daily, 7 a.m. – 4 p.m., There will be lane closures in both directions for installation of a new turn lane at Piney River.
DICKSON COUNTY SR 46
The construction of a box beam bridge on SR 46 over Yellow Creek.
• Continuous, The bridge will be reduced to one lane to demo the existing structure and reconstruct the new bridge. Traffic will be controlled by temporary signals (MM 19.06).
MAURY COUNTY SR 50
The resurfacing on SR 50 from SR 99 to near Nicholas Long Drive.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures on SR 50 in both directions for milling and paving operations.
MONTGOMERY COUNTY SR 12
Pavement repair.
• Daily, 9 a.m. – 3 p.m. (excluding weekends), There will be lane closures in both directions for pothole patching (MM 0 – 24).
MONTGOMERY COUNTY SR 76
Crack sealing.
• Daily, 9 a.m. – 3 p.m., There will be lane closures in both directions for crack sealing (MM 9.70 – 13.20).
RUTHERFORD COUNTY SR 1
The grading, drainage, signals, and paving on US 41 near Jefferson Pike to near Sam Ridley Pike in Smyrna.
• Nightly, 8 p.m. – 5 a.m., There will be lane closures on SR 1 in both directions for traffic switches and to relocate barrier wall.
The resurfacing of US 41 (SR 1) from north of Florence Road to SR 268.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures in both directions on US 41 (US 70, SR 1) north of Florence Road to SR 268 for pavement work.
RUTHERFORD COUNTY SR 2
The resurfacing on SR 2 (US-41) from Kensington Square Court to south of Cedar Grove Road.
• Daily, 9 a.m. – 3 p.m., There will be temporary alternating lane closures in both directions.
RUTHERFORD COUNTY SR 96
Field testing.
• LOOK AHEAD: 9/29 – 10/2, 8 p.m. – 5 a.m., There will be an outside lane closure in the primary direction only for coring and FWD.
RUTHERFORD COUNTY SR 99
The grading, drainage, and construction of retaining walls, signals, and paving on SR 99 from Veterans Parkway to Cason Lane.
• Daily, 9 a.m. – 3 p.m., There will be temporary alternating lane closures in both directions.
RUTHERFORD COUNTY SR 102
The resurfacing on SR 102 from SR 96 to near Mercedes Drive.
• Daily, 9 a.m. – 3 p.m., There will be temporary alternating lane closures in both directions.
SMITH COUNTY SR 141
Roadway repair.
• Continuous, There is a complete closure of SR 141 in both directions (LM 14.68 – 13.77) until on or before 12/31/2025 due to emergency bank stabilization. A detour is in place (westbound to SR 53, eastbound to SR 96).
Cross drain replacement.
• 9/18 & 9/19, 6 p.m. – 3 a.m., There will be a closure of SR 141 at Flat Rock Road/Grant Highway (LM 3 – 4) in both directions for cross drain replacement. A detour will be in place at Trousdale Ferry Pike and Carthage Highway.
SUMNER COUNTY SR 6
The grading, drainage, construction of a concrete box bridge, paving, and signals on Walton Ferry Road/Old Shackle Island Road from Nokes Drive to Volunteer Drive in Hendersonville.
• Nightly, 8 p.m. – 5 a.m., There will be temporary lane closures on SR 6 in both directions for underground utility work (MM 2.95 – 3.10).
• LOOK AHEAD: 9/22 – 9/26, 8 a.m. – 8 p.m., There will be a daily closure of Walton Ferry Road between Cages Road and Campus Drive to through traffic for utility crossings. A detour will be in place to divert traffic onto Sanders Ferry Road and Imperial Boulevard.
The grading, drainage, signals, and paving for Project Woolhawk including SR 6 and SR 25.
• Continuous, There will be an eastbound shoulder closure and lane shift on SR 6 (US-31E) with barrier wall at the intersection of Airport Road for grading and a box culvert extension.
The miscellaneous safety improvements on US-31 (SR 6) from Rock Bridge Road to near Mount Vernon Road.
• Daily, 9 a.m. – 3 p.m., There will be temporary lane closures along SR 6 for safety improvements.
Fiber installation.
• Daily, 9 a.m. – 3 p.m., There will be a westbound right lane and shoulder closure at Church Street.
SUMNER COUNTY SR 52
Roadway repair.
• Daily, 9 a.m. – 3 p.m. (excluding weekends), There will be various lane closures in both directions for pothole patching (MM 0 – 21.42).
SUMNER COUNTY SR 386
The resurfacing on SR 386 from near Forest Retreat Road to near Saundersville Road.
• Nightly, 8 p.m. – 5 a.m., There will be lane closures on Vietnam Veterans Boulevard (SR 386) including Exits 6, 7, and 8 in both directions for striping operations.
WILLIAMSON COUNTY SR 6
Pavement repair.
• Daily, 9 a.m. – 3 p.m. (excluding weekends), There will be various lane closures for pothole patching (MM 0 – 21.42).
WILLIAMSON COUNTY SR 96
New turn lane installation.
• Daily, 9 a.m. – 3 p.m., There will be an eastbound right lane and shoulder closure for construction of a new turn lane (LM 11.57).
WILLIAMSON COUNTY SR 100
The construction of pedestrian facilities on SR 100 from Fairview Community Center to Bowie Lake Road.
• Daily, 9 a.m. – 3 p.m. (excluding weekends), There will be intermittent lane closures in both directions for sign installation work.
WILSON COUNTY SR 24
The grading, drainage, signals, and paving on SR 24 (US-70) from Terrace Hill Road to Adeles Garden Road.
• Daily, 8 a.m. – 2 p.m., There will be temporary lane closures and flagging operations on SR 24 for utility relocations and grading operations (MM 5.9 – 6.49).
• Continuous, There will be a westbound shoulder closure and lane shift with barrier wall along SR 24 at Terrace Hill Road for grading operations (MM 5.9 – 6.49).
WILSON COUNTY SR 109
Road widening milling and paving near Cedar Creek Lane.
• Daily, 9 a.m. – 3:30 p.m., There will be a closure of one lane and shoulder in each direction.
WILSON COUNTY SR 141
The grading, drainage, and construction of concrete box bridges and paving on SR 141 (Hartsville Pike) from north of Lovers Lane to SR 26 (US-70).
• Daily, 9 a.m. – 3 p.m., There will be temporary lane closures on SR 141 in both directions for utility relocation and paving operations (MM 10).
WILSON COUNTY SR 171
Intelligent Transportation System and signal improvements from Division Street to Central Pike.
• Daily, 9 a.m. – 3 p.m., There will be temporary lane closures and flagging operations in both directions for underground boring and conduit installation (MM 3.56 – 7.22).
Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity. Information in this report is provided to the Department of Transportation by the contractors. Most work is weather dependent and subject to change due to inclement weather. From your desktop or mobile device, get the latest construction activity and live streaming SmartWay traffic cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any landline or cellular phone for travel information or follow us on Twitter at www.twitter.com/TN511 for statewide travel. As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for your destination. Drivers should never tweet, text or talk on a cell phone while behind the wheel.