Roadway Activity Report for the Lower East and Upper Cumberland (August 14-20, 2025)

Thursday, August 14, 2025 | 02:30pm

                                                                                                      DISTRICT 27

CLAY COUNTY SR-52 [18.7-20.56] from South of Boyd Street to Near SR-53 resurfacing: The contractor has completed resurfacing. Intermittent lane closures will be used along with flaggers to control traffic through the work zone as the contractor completes the remaining incidental work. Motorists are encouraged to use caution and watch for construction equipment and personnel. [Rogers Group, Inc./Livingston/CNZ023]

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. The contractor has scheduled paving operations beginning on the north end of the project on the proposed alignment. The contractor has closed North Grace Hill Drive at the existing intersection of SR-28 (US-127) for construction activities. Motorists should utilize South Grace Hill Drive as the detour with appropriate signs. Traffic has been moved to temporary alignment on Plateau Road and permanent alignment on Potato Farm Road. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change. [Jones Bros. Contractors, LLC/Crossville/CNV009]

CUMBERLAND COUNTY I-40 [304-306] from Putnam County Line to near parking area resurfacing and bridge repair: The contractor is scheduled to begin milling and paving operations nightly at MM 304 to MM 307 from 7 PM to 6 AM beginning Wednesday, 08/13/25. During this work, one lane in each direction will be closed. Motorists should use caution as they approach the work zone and should prepare to encounter slow or stopped traffic.
 [Rogers Group, Inc./Cookeville/CNZ104]

CUMBERLAND COUNTY I-40 [317.86-322.37] from near Obed River to near SR-101 resurfacing: The contractor is performing nighttime resurfacing operations of I-40 from near the Obed River at MM317.8 to near SR-101 at MM322.3. This work will typically take place between Sunday night through Friday morning from 7PM to 6AM each night. Motorists should use caution when traveling through the area. [Rogers Group, Inc./Crossville/CNY241]

CUMBERLAND COUNTY SR-1 (US-70) construction of bridge over the Obed River (LM 12.7): Construction activities continue on SR-1 (US-70) over the Obed River bridge. SR-1 has been reopened. Construction crews will be working outside of the roadway to install utilities. Traffic should be cautious of construction equipment near the shoulders. Contractor may need to flag traffic to move equipment or vehicles across the road.
 [Whaley Construction, LLC/Crossville/CNX110]

CUMBERLAND COUNTY SR-1 [8.86-13.27] from Pomona Road to SR-24 resurfacing: The contractor continues resurfacing operations on SR-1 from near Pomona Road to SR-24 intersection. The contractor will utilize temporary lane closures and flaggers throughout the project. Signs will accompany any closures. Motorists should use caution when traveling through the work zone. [Rogers Group, Inc./Crossville/CNZ067]

CUMBERLAND COUNTY SR-28 (Main Street, US-127) downtown pedestrian improvement project between Lantana Road (Highway 70 East) and Neecham Street: Construction activities are ongoing along SR-28 (Main Street). The contractor is working on removing and replacing the concrete sidewalk and curb ramps from Lantana Road to West 2nd Street. Signs and flaggers may be utilized during lane closures and/or lane shifts. Motorists should use caution when traveling through the work zone. [Adams Contracting, LLC/Crossville/LP24_1]

CUMBERLAND COUNTY SR-298 [8.35-9.02] from north of Catoosa Canyon Dr to south of Obed Pines Rd construction of a small drainage structure: The contractor continues construction activities on Genesis Road (SR-298). Both lanes of Genesis Road (SR-298) at LM 8.35 to LM 9.02 have been closed and will be closed for the duration of the project with a posted detour route along SR-28 (US-127) and SR-62. The contractor will be working to replace a culvert underneath Genesis Road and installing retaining walls. RESTRICTIONS: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02. [J. Hill Excavating, LLC/Crossville/CNZ103]

CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Construction activities are in progress. Activities may require temporary lane closures and/or traffic stoppages on Interstate Drive (SR-462), as well as short term closures of city streets. Flagging operations will accompany these closures with appropriate signs. Motorists should use caution when traveling through the work zone. [Rogers Group, Inc./Crossville/CNV010]

CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor will continue work along the new alignment of SR 28. Flaggers are being intermittently used to control traffic through parts of the work zone. Motorists are encouraged to use caution and watch for construction equipment and personnel adjacent to the roadway. [Jones Bros. Contractors, LLC/Cookeville/CNV300]

DEKALB COUNTY SR-26 (SPARTA HWY.) Utility Work both directions from LM 26.35 to LM 29.75: Flagger assisted lane closures on SR-26 (Sparta Hwy) from the White County line to Billings Road / Johnson Chapel Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present,05/28/25 thru 08/30/25 from 8 am - 3 pm. [2024-410]

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading and construction activities throughout the project. Temporary lane closures and periodic traffic stoppages will be necessary for construction activities and motorists should be prepared to stop while traveling through the work zone. Motorists are encouraged to obey posted speed limit and to watch for construction equipment and personnel adjacent to the roadway. The West end of Old Liberty Road will be closed to through traffic due to construction activities. Motorists and EMS will need to use the East entrance of Old Liberty Road to gain access and follow detour signs. [Twin K Construction/Cookeville/CNV012]

FENTRESS COUNTY SR-52 [13.6-17.62] from east of the bridge over SR-28 (US-127) to SR-296 resurfacing: Intermittent lane closures will be used along with flaggers to control traffic through the work zone. Motorists are encouraged to use caution and watch for construction equipment and personnel. [Rogers Group, Inc./Livingston/CNZ031]
 [Rogers Group, Inc./Livingston/CNZ031]

PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. West Davis Road and Henley Drive remain closed at the intersection of SR-136 with detour signs to utilize Bunker Hill Road. SR-111 SB exit ramp to SR-136 is closed. The detour for this closure is for motorists to utilize I-40 to SR 136 and then use SR 136 to travel southbound. The contractor has also scheduled lane closures to be installed between 08/13/25 to 08/15/25 at the north end of the project near the I-40 overpass bridges. Jefferson Avenue will be closed down to one lane in each direction from near Bunker Hill Road to the end of the project at the I-40 overpass bridges. The turning lanes to I-40 eastbound and Bunker Hill Road will remain opened. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel and equipment adjacent to the roadway. [Rogers Group, Inc./Cookeville/CNV284]

PUTNAM COUNTY SR-136 (S. JEFFERSON AVE.) Utility Work both directions from LM 2.55 to LM 2.75: Northbound and southbound lane closures on SR-136 (S Jefferson Ave) between Spring Street Town Square to I-40. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/14/24 through 08/30/25 from 9 am - 2 pm. [2024-640]

PUTNAM COUNTY SR-84 (CALFKILLER HWY.) Utility Work both directions from LM 1 to LM 8.0: Flagger assisted lane closures on SR-84 (Calfkiller Hwy) from the White County line to Hidden Acres Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/24/25 thru 09/30/25 from 8 am - 3 pm. [2023-577]

PUTNAM COUNTY I-40 [300-304] from West of SR-24 to Cumberland County Line resurfacing and bridge repair: The contractor is scheduled to begin milling and paving operations nightly at MM 300 to MM 304 from 7 PM to 6 AM beginning Wednesday, 08/13/25. During this work, one lane in each direction will be closed. The contractor has also scheduled bridge repair work to begin Friday, 08/15/25 at 7 PM through Monday, 08/18/25 at 6 AM at MM 300 eastbound. During this work, one lane of I-40 will be shut down while the contractor performs work. Motorists should use caution as they approach the work zone and should prepare to encounter slow or stopped traffic.
 [Rogers Group, Inc./Cookeville/CNZ104]

WHITE COUNTY SR-1 (CROSSVILLE HWY.) Utility Work westbound from LM 18 to LM 19: Shoulder lane closures on SR-1(US-Hwy 70 W) from Love Joy Road to East of Eastland Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, personnel, and barrels/cones will be present, 07/10/25 thru 08/30/25 from 6 am - 4:30 pm. [2025-355]

 

                                                                                                        DISTRICT 28

BLEDSOE COUNTY SR-30 and SR-443, the grading, drainage, stream relocation, widening, and resurfacing on Summer City Road: The contractor will be performing grade work and widening on Summer City Road in Bledsoe County. This work will narrow the lanes at LM 2.0 and LM 4.3 and will leave both lanes open to traffic. Please slow down and use caution when driving through the work zone. [Rogers Group, Inc./Dunlap/CNY153]

COFFEE COUNTY I-24 (MM 117) construction of an overpass carrying Wattendorf Memorial Highway/AEDC Road, including grading, drainage, retaining walls, and paving: Drivers can expect short term flagging operations for trucks entering and exiting the work zone on Wattendorf Highway. Please use caution when traveling through the work zone. There will be nightly lane closures and rolling roadblocks on I-24 in both directions on 08/20 and 8/27 from 7PM to 6AM for beam setting operations. [Jones Bros. Contractors, LLC/Tullahoma/CNZ029]

COFFEE COUNTY I-24 resurfacing from east of SR-2 (US-41) (LM 8.9) to near SR-55 (LM 14.8), including bridge expansion joint repairs and thin epoxy overlay: Nightly alternating lane closures will continue on I-24 from 7PM-6AM for resurfacing operations. One lane in each direction will be maintained at all times. [Rogers Group, Inc./Tullahoma/CNY262]

COFFEE COUNTY I-24 (MM 105) construction of an overpass carrying SR-2 (US-41): Phase 2 of I-24 bridge replacement at Exit 105 will continue this week. SR-2 will be reduced to one lane utilizing traffic signal system. The temporary traffic signal will remain in effect until 10/16/25. [Bell and Associates Construction, LP/Tullahoma/CNX309]

COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 1 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. Contractor may use temporary lane shifts to complete storm structure installations. Phase 1 traffic shift has reduced lanes from 3 to 2 from Cedar Lane to near Grau Lane in order to continue bridge replacement and storm drainage work.
 [Dement Construction Company, LLC/Tullahoma/CNX912]

COFFEE COUNTY SR-55 repair of the bridge over the Little Duck River (LM 14.0): Lanes are reduced to one lane in each direction across the SR-55 bridge over the Little Duck River for bridge repair work. This lane reduction will be in place until work is complete in Fall 2025. [Mid-State Construction Company, Inc./Tullahoma/CNX412]

GRUNDY COUNTY SR-56 [5.42-7.81] from Montgomery Street to Des Church Road resurfacing: The contractor will have lane closures during daylight hours from 5AM to 9PM for paving operations as needed. Flaggers will be present during the lane closure operations, and at least one lane will remain open at all times. [Tinsley Asphalt, LLC /McMinnville/CNZ033]

MARION COUNTY SR-2 (DIXIE LEE AVE.) Utility Work both directions from LM 30.59 to LM 30.74: Flagger assisted lane closures on SR-2(Dixie Lee Ave) at the Sullivan's Landing TWRA Boat ramp. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 08/14/25 thru 08/20/25 from 9 am - 2 pm. [132273.00]

MARION COUNTY SR-283 (STATE HWY. 283) Utility Work both directions from LM 13 to LM 14: Shoulder lane closures on SR-27 (Griffith Hwy) from Mountain Cove Road to Ketner Mill Road / Ditch Gap Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, personnel, and barrels/cones will be present, 08/04/25 thru 08/20/25 from 9 am - 2 pm. [2025-481]

MARION COUNTY SR-283 (STATE HWY. 283) Utility Work northbound at LM 1.95: Flagger assisted northbound lane closure on SR-283 between Osceola Dr and Turner Road. Motorists should reduce speed and be prepared to stop. Flaggers, signage, barrels/cones will be present, 07/17/25 thru 08/22/25 from 9 am - 2 pm. [2023-751]

MARION COUNTY SR-156 repair of bridge over Tennessee River, LM 15.2: The contractor will be performing painting operations and structural repairs on the SR-156 bridge over the Tennessee River in South Pittsburg. This work will require a traffic shift leaving both lanes open to traffic. There will also be intermittent lane closures controlled by flaggers leaving one lane open. Please use caution when driving through the work zone. [Olympus Painting Contractors Inc./Dunlap/CNY063]

MARION COUNTY SR-27 (US-72) resurfacing from the Alabama State Line (LM 0) to north of SR-156 (LM 2.7): The contractor will be performing paving operations on SR-27 EB and WB in Bledsoe County from the Alabama state line to north of SR-156. This work will require single lane closures leaving one lane open in each direction during daytime work hours. Please use caution when driving through the work zones. [Tinsley Asphalt, LLC /Dunlap/CNZ036]

WARREN COUNTY SR-56 (SMITHVILLE HWY.) Utility Work both directions from LM 14.5 to LM 15: Flagger assisted northbound lane closure on SR-56 (Smithville Hwy) between Northwood Lane and Dunlap Drive. Motorists should reduce speed and be prepared to stop. Flaggers, signage, barrels/cones will be present, 08/18/25 thru 10/17/25 from 9 am - 2 pm. [2020-314]

WARREN COUNTY SR-1 (US-70S) bridge repair over SR-55 (LM 10.5): The contractor will have intermittent lane closures on SR-1 on both the EB and WB bridges with drums. Under the bridge on SR-55 Bypass the portable barrier rail is in place, closing the outside shoulders under the bridge. Lane closures under bridge will also be utilized for removal of concrete portable barrier rail in the near future. [Mid-State Construction Company, Inc./McMinnville/CNY196]

WARREN COUNTY SR-108 [2.83-11.49] from near S.R. 287 to South Chancery Street micro surfacing and bridge expansion joint repair: The contractor will have lane closures during daylight hours from 5AM to 9PM for paving operations as needed. Flaggers will be present during the lane closure operations, and at least one lane will remain open at all times. [Wiregrass Construction Company, Inc./McMinnville/CNZ043]

 

                                                                                                        DISTRICT 29

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will continue asphalt paving, final pavement markings, and finishing work throughout the project. Intermittent flagging operations will take place as needed for various work activities. Motorists are advised to use caution in the work zone and watch for flaggers assisting with traffic control. [Summers-Taylor, Inc./Cleveland/CNV130]

BRADLEY COUNTY I-75 [15.35-19.309] from MM 31 to MM 35 (McMinn County Line) resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorist should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations. [Wright Brothers Construction Company, Inc./Chattanooga West/CNY261]

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly Lane closures will occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. These closures may temporarily reduce traffic to a single lane. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. (Note: Overhead sign work will resume on I-75 (North and South) and on I-24 (East and West) between Sunday, August 17th and Thursday, August 21th. Nightly between 9 PM and 6 AM, traffic on interstates may be reduced to a single lane and/or rolling roadblocks used to temporarily stop traffic (15 minutes or less) while crews install signs or overhead structures. The entrance ramp from South Terrace (between S. Moore Road and McBrien Road) onto I-24 East is temporarily closed for approximately 3 weeks to facilitate road work that cannot be done under traffic. A new entrance ramp from South Terrace (between Belvoir Avenue and S. Moore Road) has been opened and detours to this new entrance ramp have been posted. The I-24 West entrance ramp at Germantown Road is closed for noise wall installation work that will continue for the next 2 to 4 weeks. Detours are posted for the ramp closure to an alternative entrance.) It may be necessary to do short duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrail, attenuators, etc. Portions of the left lane on North and South Terrace between Germantown Road and Spring Creek Road will remain closed for the installation of drainage structures, sanitary sewers, retaining and noise wall construction. The entrance and exit ramps to I-24 between Belvoir Avenue and Moore Road are currently closed (Note: A new entrance ramp from North Terrace to I-24 West is now open in this area. A new entrance ramp and exit ramp to I-24 East from South Terrace has been opened. Please look for detour signs giving directions to access these new ramps.). RESTRICTIONS: I-24 Ramps between Belvoir Ave. and S. Moore Road are closed. Entrance ramp from Germantown Road to I-24 West is closed.  [Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]

HAMILTON COUNTY SR-17 (BONNY OAKS DR.) Utility Work both directions from LM 8.00 to LM 8.32: Flagger assisted lane closures on SR-17 (Bonny Oaks Dr) between the Churchill Rd and Youngstown Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 08/14/25 thru 08/20/25 from 9 am - 2 pm. [2025-515]

HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work southbound from LM 16 to LM 17: Shoulder lane closures on SR-2 (Lee Hwy) from the entrance of Sam's Club to south of Van Ness Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, personnel, and barrels/cones will be present, 08/11/25 thru 08/22/25 from 9 am - 2 pm. [2025-477]

HAMILTON COUNTY SR-27 (ROSSVILLE BLVD.) Utility Work both directions at LM 6.73: Law enforcement and flagger assisted lane closures on SR-27 (Rossville Blvd) at the intersection of 37th St. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 08/07/25 through 8-29-25 from 9 am - 2 pm. [2025-436]

HAMILTON COUNTY SR-321 (OOLTEWAH-RINGGOLD RD.) Utility Work both directions from LM 5 to LM 7: Flagger assisted lane closures on SR-321 (Ooltewah-Ringgold Road) from Caddo Lane / Cavalier Way to Church Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 07/31/25 thru 08/20/25, from 9 am - 2 pm. [2025-435]

HAMILTON COUNTY SR-8 (RINGGOLD RD.) TDOT Contractor both directions at LM 5.04: Routine inspections of the Bachman Tunnels are scheduled for the overnight hours of Monday 8/18/25 and Tuesday 8/19/25. The north bore will be closed from 8 PM on 8/18/25 until 5 AM on 8/19/25. The south bore will be closed from 8 pm on 8/19/25 until 5 am on 8/20/25. Follow detour signs. Traffic will be detoured via Westside Drive, Shadowlawn Drive and South Seminole Drive.

HAMILTON COUNTY I-124 (US-27) from I-24 Interchange to South of the Tennessee River Bridge: Daily lane closures are possible between 9 AM and 3:30 PM as the contractor work along the ramps and 4th Street. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control. [Stansell Electric Company, Inc./Chattanooga East/CNY900]

HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps and Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman’s Jewelers and Texas Roadhouse. The contractor has implemented a traffic shift on Hamilton Place Blvd. shifting NB and SB traffic to the east side of the existing roadway from near the I-75 SB on-ramp to near Bams Drive for the installation of storm drainage. The contractor will maintain 1 lane of traffic in each direction throughout this area. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel.
 [Summers-Taylor, Inc./Chattanooga West/CNX358]

HAMILTON COUNTY SR-2 [11.33-11.92] from Dodds Ave to Seminole Drive tunnel rehabilitation: There will be nighttime flagging operations to allow the contractor to finish final pavement striping. The flagging operations will be between the hours of 8PM and 6AM. [Stansell Electric Company, Inc./Chattanooga East/CNY192]

HAMILTON COUNTY SR-2 [11.86-11.63] from McCallie Tunnel to McCallie Tunnel Maintenance: The McCallie Tunnels will be cleaned 08/20/2025 from 8 PM to 6 AM, weather permitting. The contractor will clean one side at a time and flag traffic during the work. Motorists clean expect delays. [Diamond Specialized, Inc./Chattanooga West/CNZ133]

HAMILTON COUNTY SR-2 [2.73-3.19] from Wauhatchie United Methodist Church to Brown's Ferry safety improvements: The contractor will be working on safety improvements along this route. This work will require nightly lane closures between the hours of 8PM and 6AM Sunday through Thursday. [APAC - Atlantic, Inc./Chattanooga East/CNZ107]

HAMILTON COUNTY SR-29 [20.72-25.756] from SR-111 to Old Dayton Pk. Resurfacing: Contractor is planning to install signs this reporting period. This work will take place during the day from the shoulders. [Rogers Group, Inc./Chattanooga West/CNZ034]

HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, for bridge and grading work. The flagging operations will be performed on 08/14/25, 08/15/25, 08/18/25, 08/19/25 and 08/20/25 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for bridge work, delivery of materials and equipment.
 [Wright Brothers Construction Company, Inc./Chattanooga East/CNT336]

HAMILTON COUNTY SR-8 [10.14-11.96] from Frazier Ave to Signal Mountain Blvd resurfacing: The contractor will be resurfacing Cherokee Blvd and Dayton Blvd (SR-8) between Frazier Ave and Signal Mtn Blvd. This work will be performed at night between the hours of 8pm and 6am. The traveling public can expect delays with lane closures and flaggers present. There will be temporary detours utilizing US-27 and Manufactures Road between 8/17/25 and 8/19/25. These detours are necessary to complete paving over the railroad on Dayton Blvd. There will be NO OVERNIGHT ON-STREET PARKING during the duration of this project. [APAC - Atlantic, Inc./Chattanooga East/CNZ138]

HAMILTON COUNTY SR-8 [11.67-11.75] from Stringers Ridge Tunnel to Stringers Ridge Tunnel Cleaning: The Stringers Ridge Tunnel will be closed 08/20/2025 from 8 PM to 6 AM for cleaning. A detour will in effect during the closures to direct traffic to alternative routes. This work is weather permitting. [Diamond Specialized, Inc./Chattanooga West/CNZ133]

HAMILTON COUNTY SR-8 [5.04-5.27] from Bachman Tubes to Bachman Tubes Tunnel Cleaning: The Bachman Tunnel will be closed 08/21/2025 from 8 PM to 6 AM for cleaning. A detour will in effect during the closures to direct traffic to alternative routes. This work is weather permitting. [Diamond Specialized, Inc./Chattanooga West/CNZ133]

HAMILTON COUNTY SR-8 [8.97-10.14] from MLK to Frazier Avenue resurfacing: Contract crews will be working on Market Street overnight from Sunday through Friday, between 8:00 PM and 6:00 AM local time, to minimize daytime traffic impacts. There will be no designated on-street parking during this work. This designation enables crews to resurface the entire asphalt roadway, including parking areas, while protecting nearby vehicles and ensuring safe, efficient operation of heavy equipment throughout the project. Drivers should obey the posted no parking signs. Violators are subject to tickets and/or towing. Drivers should expect lane closures and short detours around city blocks during overnight hours. There will also be a short daytime lane closure between 6th Street and 7th Street to allow the contractor to complete concrete repairs at the CARTA bus stop. [APAC - Atlantic, Inc./Chattanooga East/CNZ107]

MCMINN COUNTY SR-2 (US-HWY. 11) Utility Work both directions from LM 16.81 to LM 19.61: CR-255 & Burn Rd Flagger assisted lane closures on SR-2 (US-11) betweenCR-255 & Burn Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 08/11/25 thru 08/29/25 from 9 am - 2 pm. [2024-374]

MCMINN COUNTY SR-30 (TENNESSEE AVE.) Utility Work both directions from LM 19 to LM 21: Flagger assisted lane closures on SR-30 from Cooper Street to Sable Road to 6th Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/06/25 thru 08/29/25 from 9 am - 2 pm. [2025-228]

MCMINN COUNTY I-75 [0-2.06] from MM 35 (Bradley County Line) to MM 37 resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations. [Wright Brothers Construction Company, Inc./Chattanooga West/CNY261]

MCMINN COUNTY I-75 [2.06-4.32] from MM 37 to MM 39.5 resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations. [Wright Brothers Construction Company, Inc./Chattanooga West/CNZ109]

MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the Northbound and Southbound traffic will be reduced to one lane and controlled by traffic signals. County road 567 will be closed to traffic (LOCAL TRAFFIC ONLY) and detoured to SR039. This closure is necessary to perform the bridge replacement. The lane restriction will remain in place until the bridge replacement is completed. [Whaley Construction, LLC/Chattanooga East/CNX069]

MCMINN COUNTY SR-39 from west of Cook Drive to SR-30 and from SR-310 to the Monroe County Line: During this reporting period, the contractor will complete punch list work on SR-39. Motorists should be aware of workers in the area performing this work. Intermittent lane closures and flagging operations around the work area will be necessary.
 [Rogers Group, Inc./Cleveland/CNZ038]

MEIGS COUNTY SR-60 (STATE HWY. 60) Utility Work both directions from LM 0 to LM 1: Flagger assisted lane closures on SR-60 from the Hamilton County line to CR-121 (McInturff Rd) Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 08/12/25 thru 08/20/25 from 9 am - 2 pm. [2025-546]

POLK COUNTY SR-68 construction of bridge over Brush Creek (LM 16.4): During this update period, the contractor will continue sodding and final pavement markings. A temporary traffic signal system is active on SR-68 near LM 16.4. The northbound lane of SR-68 will be closed in the area controlled by the temporary traffic signal system. Motorists are advised to reduce speed and use caution in the work zone. [Wright Brothers Construction Company, Inc./Cleveland/CNX347]

POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period the contractor will continue construction on the SR-68 North bridge. All SR-68 traffic is using the existing SR-68 South bridge while construction occurs on the new SR-68 North bridge. All SR-40/SR-68 interchange traffic will utilize the SR-68 South interchange ramps. A temporary 3-way stop has been implemented at the intersection of the SR-40 interchange ramp and SR-68. Motorists are encouraged to slow down when entering the construction zone and look out for new stop signs on SR-68 near the SR-40/SR-68 interchange. [Wright Brothers Construction Company, Inc./Cleveland/CNZ042]

RHEA COUNTY SR-29 [14.66-19.879] from Boofer Lane to Metzger LN Resurfacing: Paving operations will continue during this reporting period. The contractor will utilize temporary lane closures from 7AM to 6PM during paving operations. Motorists should use caution while traveling on this route and pay attention to all construction signage.
 [Rogers Group, Inc./Chattanooga West/CNY118]

RHEA COUNTY SR-30 repair of bridge over Tennessee River: The contractor will be making repairs under the Tennessee River Bridge. The remaining work will require the contractor to shut the roadway down to one lane using flaggers or temporary traffic signals. Watercraft users should use caution when accessing the TWRA boating ramp under the bridge in Rhea County. The contractor will have equipment and materials in the area of the access road for the boating ramp.
 [Mid-State Construction Company, Inc./Chattanooga East/CNY201]

 

                                                                                                       REGION WIDE

REGION 2 The on-call concrete pavement repair at various locations on various Interstate and State Routes: The contractor will be repairing concrete pavement on the ramps at I-24 exit 127. All 4 ramps on I-24 at exit 127 will be worked on. This work will require the narrowing of each ramp with a minimum open lane width of 10 feet. Please use caution when driving through the work zones. [Bluegrass Contracting Corporation/Dunlap/CNY295]

REGION 2 Dynamic Message Sign (DMS) Life Cycle Replacement: Shoulder closures will be in place at Bradley I-75 NB at MM 27.2, McMinn I-75 SB at MM 42.2, and Marion County I-24 WB at MM 156. Trucks will be entering and exiting the work zone during daytime hours. [Davis H. Elliot Construction Company, Inc./Chattanooga East/CNX413]

REGION 2 The drain cleaning on various Interstate and State Routes: Drain cleaning operations are planned on various routes throughout Region 2. This is a mobile operation along the shoulders with impacts to adjacent traffic lanes. Temporary lane closures maybe utilized to complete this work. These operations will occur at night Sunday through Thursday between 8 PM and 6 AM. [Sweeping Corporation of America, Inc./Chattanooga West/CNY226]

REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed. [Reynolds Fence and Guardrail, Inc./McMinnville/CNZ112]

REGION 2 The sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes.
 [Sweeping Corporation of America, Inc./Chattanooga West/CNY210]

REGION 2 Various Interstate and SRs - Cable Barrier Repair: The contractor will have short term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed.
 [LU, Inc./McMinnville/CNY183]

REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic. Flaggers will assist with traffic control as needed. [Lumin8 Transportation Technologies, LLC/Chattanooga East/CNX270]

                                                                                                     RESTRICTIONS

CUMBERLAND COUNTY - CNZ103: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02.

HAMILTON COUNTY - DB2101: I-24 Ramps between Belvoir Ave. and S. Moore Road are closed. The entrance ramp from Germantown Road to I-24 West is closed.

                                                                                                               ###