DISTRICT 27
CLAY COUNTY SR-52 [18.7-20.56] from South of Boyd Street to Near SR-53 resurfacing: The contractor has completed resurfacing. Intermittent lane closures will be used along with flaggers to control traffic through the work zone as the contractor completes the remaining incidental work. Motorists are encouraged to use caution and watch for construction equipment and personnel.
[Rogers Group, Inc./Livingston/CNZ023]
CLAY, CUMBERLAND, DEKALB, PICKETT, PUTNAM, AND WHITE COUNTY The ADA curb ramp upgrades on various State Routes: The contractor will be at various locations in Clay, Pickett, Cumberland, Dekalb, Putnam, and White Counties performing cleanup work and restoring natural ground that was disturbed during construction. During this work, sidewalks closures may be used, and temporary lane closures may be briefly installed. The locations of the work include Clay County on SR-52 from LM 18.69 to 20.56, Pickett County SR-325 from LM 4.23 to 8.08, Cumberland County SR-28 from LM 12.61 to 14.96, Dekalb County SR-26 from LM 13.25 to 15.90, Putnam County SR-135 from LM 9.75 to 13.39 and SR-24 from LM 17.92 to 20.77, and White County SR-289 from LM 0.00 to 2.61. [MarCor Construction, Inc./Cookeville/CNY252]
CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Hubert Conley Road at the intersection of SR-28 has been reopened. The contractor has closed North Grace Hill Drive at the existing intersection of SR-28 (US-127) for construction activities. Motorists should utilize South Grace Hill Drive as the detour with appropriate signs. Traffic has been moved to temporary alignment on Plateau Road and permanent alignment on Potato Farm Road. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change.
[Jones Bros. Contractors, LLC/Crossville/CNV009]
CUMBERLAND COUNTY SR-1 (US-70) construction of bridge over the Obed River (LM 12.7): Construction activities continue on SR-1 (US-70) over the Obed River bridge. SR-1 has been reopened. Construction crews will be working outside of the roadway to install utilities. Traffic should be cautious of construction equipment near the shoulders. Contractor may need to flag traffic to move equipment or vehicles across the road.
[Whaley Construction, LLC/Crossville/CNX110]
CUMBERLAND COUNTY SR-1 [8.86-13.27] from Pomona Road to SR-24 resurfacing: The contractor continues resurfacing operations on SR-1 from near Pomona Road to SR-24 intersection. The contractor will utilize temporary lane closures and flaggers throughout the project. Signs will accompany any closures. Motorists should use caution when traveling through the work zone. [Rogers Group, Inc./Crossville/CNZ067]
CUMBERLAND COUNTY SR-28 (Main Street, US-127) downtown pedestrian improvement project between Lantana Road (Highway 70 East) and Neecham Street: Construction activities are ongoing along SR-28 (Main Street). The contractor is working on removing and replacing the concrete sidewalk and curb ramps from Lantana Road to West 2nd Street. The contractor will be pouring concrete beginning from Lantana Road to West 2nd Street. During this time, the contractor will utilize flaggers, and the road will be reduced to one lane for a period of time. Once operations are completed for the day, traffic will be reopened to two lanes. The shoulder parking along this area has been closed. Signs and flaggers may be utilized during these lane closures and/or lane shifts. Motorists should use caution when traveling through the work zone. [Adams Contracting, LLC/Crossville/LP24_1]
CUMBERLAND COUNTY SR-298 [8.35-9.02] from north of Catoosa Canyon Dr to south of Obed Pines Rd construction of a small drainage structure: The contractor continues construction activities on Genesis Road (SR-298). Both lanes of Genesis Road (SR-298) at LM 8.35 to LM 9.02 have been closed and will be closed for the duration of the project with a posted detour route along SR-28 (US-127) and SR-62. The contractor will be working to replace a culvert underneath Genesis Road and installing retaining walls. RESTRICTIONS: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02. [J. Hill Excavating, LLC/Crossville/CNZ103]
CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Construction activities are in progress. Contractor plans to close the westbound lanes on Interstate Drive (SR-462) at the intersection of Genesis Road beginning on 07/07/25. Additionally, the turn lanes from Genesis Road to Interstate Drive will be closed. This will allow the contractor to work on the concrete island at the intersection. Motorists should be cautious of the change in traffic especially at the intersection of Old Jamestown Hwy. Activities may require temporary lane closures and/or traffic stoppages on Interstate Drive (SR-462), as well as short term closures of city streets. Flagging operations will accompany these closures with appropriate signs. Motorists traveling west on Interstate Drive should be mindful of the "Right Turn Only" lane at the intersection of Stout Drive. Motorists should use caution when traveling through the work zone. [Rogers Group, Inc./Crossville/CNV010]
CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor will continue work along the new alignment of SR 28. Flaggers are being intermittently used to control traffic through parts of the workzone. Motorists are encouraged to use caution and watch for construction equipment and personnel adjacent to the roadway. [Jones Bros. Contractors, LLC/Cookeville/CNV300]
DEKALB COUNTY SR-26 (SPARTA HWY.) Utility Work both directions from LM 26 to LM 29.75: Flagger assisted lane closures on SR-26 (Sparta Hwy) from the White County line to Billings Road / Johnson Chapel Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 05/28/25 thru 08/30/25 from 8 am - 3 pm. [2024-410]
DEKALB COUNTY SR-26 (W. BROAD ST.) Utility Work both directions from LM 16 to LM 18: Shoulder and lane closures on SR-26 (W. Broad Street) between Dry Creek Road and Wal-Mart entrance. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, personnel/flaggers, and barrels/cones will be present, 06/19/25 thru 07/16/25 from 8 am - 3 pm. [2023-710]
DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading and construction activities throughout the project. Temporary lane closures and periodic traffic stoppages will be necessary for construction activities and motorists should be prepared to stop while traveling through the work zone. Motorists are encouraged to obey posted speed limit and to watch for construction equipment and personnel adjacent to the roadway. The West end of Old Liberty Road will be closed to through traffic due to construction activities. Motorists and EMS will need to use the East entrance of Old Liberty Road to gain access and follow detour signs. [Twin K Construction/Cookeville/CNV012]
FENTRESS COUNTY SR-52 [13.6-17.62] from east of the bridge over SR-28 (US-127) to SR-296 resurfacing: Intermittent lane closures will be used along with flaggers to control traffic through the work zone. Motorists are encouraged to use caution and watch for construction equipment and personnel. [Rogers Group, Inc./Livingston/CNZ031]
[Rogers Group, Inc./Livingston/CNZ031]
JACKSON COUNTY SR-53 (GRANVILLE HWY.) TDOT Maintenance southbound at LM 12.5: SR53 will be reduced to one lane from 6/30/25 thru 7/18/25 to repair a slide area at the 12.5MM. Traffic signals will be in place. Motorists are encouraged to slow down, use caution, and be prepared to stop.
OVERTON COUNTY SR-52 resurfacing from east of SR-294 (LM 12.2) to near Dogwalk Road (LM 18.3): The contractor has completed resurfacing. Intermittent lane closures will be used along with flaggers to control traffic through the work zone as the contractor completes the remaining incidental work. Motorists are encouraged to use caution and watch for construction equipment and personnel. [Rogers Group, Inc./Livingston/CNZ039]
OVERTON COUNTY SR-52 [10.96-11.28] from Near Henson St. to Robert St. Resurfacing: The contractor has completed resurfacing. Intermittent lane closures will be used along with flaggers to control traffic through the work zone as the contractor completes the remaining incidental work. Motorists are encouraged to use caution and watch for construction equipment and personnel.
[Rogers Group, Inc./Livingston/CNZ039]
OVERTON COUNTY SR-85 [11.17-11.91] from SR-111 to SR-52 resurfacing: The contractor has completed resurfacing. Intermittent lane closures will be used along with flaggers to control traffic through the work zone as the contractor completes the remaining incidental work. Motorists are encouraged to use caution and watch for construction equipment and personnel.
[Rogers Group, Inc./Livingston/CNZ039]
PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. West Davis Road and Henley Drive remain closed at the intersection of SR-136 with detour signs to utilize Bunker Hill Road. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel.
[Rogers Group, Inc./Cookeville/CNV284]
PUTNAM COUNTY SR-136 (S. JEFFERSON AVE.) Utility Work both directions from LM 2.55 to LM 2.75: Southbound lane closures on SR-136 (S Jefferson Ave) between Spring Street Town Square to I-40. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/14/24 through 07/30/25 from 9 am - 2 pm. [2024-640]
PUTNAM COUNTY SR-84 (CALFKILLER HWY.) TDOT Maintenance northbound from LM 3.0 to LM 4.0: SR84 will be closed Monday-Saturday 7:00AM-5:00PM from 6/26/25 thru 7/19/25 to repair a slide area near the 3.2MM, with the exception of the holiday weekend when one lane will re-open at 12PM noon Thursday 7/3/25 and will remain open until Monday morning at 7:00AM when the regular schedule will resume. All other times the roadway will be reduced to one lane with signals. Motorists are encouraged to slow down and use caution when in the area. RESTRICTIONS: Horizontal clearance will be restricted to 10FT. NO TRACTOR TRAILERS.
PUTNAM COUNTY SR-84 (CALFKILLER HWY.) Utility Work both directions from LM 1 to LM 8: Flagger assisted lane closures on SR-84 (Calfkiller Hwy) from the White County line to Hidden Acres Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/24/25 thru 07/30/25 from 8 am - 3 pm. [2023-577]
PUTNAM COUNTY SR-24 [23.27-29.89] from Hitchcock Drive to Mill Creek Road Resurfacing: The contractor will be continuing milling and paving operations. During this work, lane closures will be utilized with one lane shut down. Flaggers will be present to control the flow of traffic through the work zone. Motorists are encouraged to use caution as they approach the work zone, and they should be prepared to stop. [Rogers Group, Inc./Cookeville/CNZ041]
WHITE COUNTY SR-26 (SMITHVILLE HWY.) Utility Work both directions from LM 0 to LM 1: Flagger assisted lane closures on SR-26 (Sparta Hwy) from the DeKalb County line to Jay Hutchings Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 05/28/25 thru 08/30/25 from 8 am - 3 pm. [2024-410]
DISTRICT 28
BLEDSOE COUNTY SR-30 and SR-443, the grading, drainage, stream relocation, widening, and resurfacing on Summer City Road: The contractor will be performing grade work and widening on Summer City Road in Bledsoe County. This work will narrow the lanes at LM 2.0 and LM 4.3 and will leave both lanes open to traffic. Please slow down and use caution when driving through the work zone. [Rogers Group, Inc./Dunlap/CNY153]
COFFEE COUNTY I-24 (MM 117) construction of an overpass carrying Wattendorf Memorial Highway/AEDC Road, including grading, drainage, retaining walls, and paving: Drivers can expect short term flagging operations for trucks entering and exiting the work zone on Wattendorf Highway. Please use caution when traveling through the work zone.
[Jones Bros. Contractors, LLC/Tullahoma/CNZ029]
COFFEE COUNTY I-24 resurfacing from east of SR-2 (US-41) (LM 8.9) to near SR-55 (LM 14.8), including bridge expansion joint repairs and thin epoxy overlay: Nightly alternating lane closures will continue on I-24 from 7PM-6AM for resurfacing operations. One lane in each direction will be maintained at all times.
[Rogers Group, Inc./Tullahoma/CNY262]
COFFEE COUNTY SR-53 (WOODBURY HWY.) Utility Work both directions at LM 0.1: Flagger assisted lane closures on SR-53 (Woodbury Hwy) at the intersection with SR-2 (Murfreesboro Hwy). Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 07/09/25 from 6 am - 2 pm, with a rain date of 07/10/25. [2025-099]
COFFEE COUNTY SR-53 (WOODBURY HWY.) Utility Work both directions from LM 6 to LM 7: Flagger assisted lane closures on SR-53 (Woodbury Hwy) at the intersection with Goode Pond Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 07/08/25 from 9 am - 2 pm, with a rain date of 07/09/25. [2025-189]
COFFEE COUNTY I-24 (MM 105) construction of an overpass carrying SR-2 (US-41): Phase 2 of I-24 bridge replacement at Exit 105 will continue this week. SR-2 will be reduced to one lane utilizing traffic signal system. The temporary traffic signal will remain in effect until 10/16/25. There will be alternating lane closures on I-24 from 7PM-6AM on 07/07 thru 07/10 nightly. One lane in each direction will remain open at all times.
[Bell and Associates Construction, LP/Tullahoma/CNX309]
COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 1 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. Contractor may use temporary lane shifts to complete storm structure installations. Phase 1 traffic shift has reduced lanes from 3 to 2 from Cedar Lane to near Grau Lane in order to continue bridge replacement and storm drainage work.
[Dement Construction Company, LLC/Tullahoma/CNX912]
COFFEE COUNTY SR-55 repair of the bridge over the Little Duck River (LM 14.0): Lanes are reduced to one lane in each direction across the SR-55 bridge over the Little Duck River for bridge repair work. This lane reduction will be in place until work is complete in Fall 2025.
[Mid-State Construction Company, Inc./Tullahoma/CNX412]
COFFEE COUNTY SR-55 [13.79-15.32] from US-41 to north of Interstate Drive resurfacing: Lane closures for final pavement markings will continue nightly until complete from 7PM to 6AM. One lane in each direction will be maintained at all times.
[Volunteer Paving, LLC/Tullahoma/CNY267]
FRANKLIN COUNTY SR-130 (OLD TULLAHOMA RD.) Utility Work both directions from LM 2 to LM 5: Flagger assisted lane closures on SR-130 (Old Tullahoma Road) at the intersection with Hurricane Road / Blue Creed Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 07/07/25 thru 07/11/25 from 9 am - 2 pm. [2025-180]
FRANKLIN COUNTY Old Decherd Road over Wagner Creek (LM 0.3) construction of a bridge: Old Decherd Road is closed at Wagner Creek for bridge replacement. A signed detour is in place. The road closure will be in place for the duration of the project through July 17th, 2025. RESTRICTIONS: Old Decherd Road at Wagner Creek is closed.
[Dement Construction Company, LLC/Tullahoma/CNY068]
MARION COUNTY SR-156 repair of bridge over Tennessee River, LM 15.2: The contractor will be performing painting operations and structural repairs on the SR-156 bridge over the Tennessee River in South Pittsburg. This work will require a traffic shift leaving both lanes open to traffic. Please use caution when driving through the work zone.
[Olympus Painting Contractors Inc./Dunlap/CNY063]
MARION COUNTY SR-27 (US-72) resurfacing from the Alabama State Line (LM 0) to north of SR-156 (LM 2.7): The contractor will be performing paving operations on SR-27 EB and WB in Bledsoe County from the Alabama state line to north of SR-156. This work will require single lane closures leaving one lane open in each direction during day time work hours. Please use caution when driving through the work zones. [Tinsley Asphalt, LLC /Dunlap/CNZ036]
WARREN COUNTY SR-55 (S. CHANCERY ST.) Utility Work both directions from LM 1 to LM 3: Flagger assisted lane closures on SR-55 (S. Chancery Street) from Mayfield Lumber Drive / Chris Lane to George Huggins Drive / Bridge Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 07/07/25 thru 08/18/25 from 9 am - 2 pm. [2021-223]
WARREN COUNTY SR-1 (US-70S) bridge repair over SR-55 (LM 10.5): The contractor will maintain the closure of one lane on SR-1 on both the EB and WB sides on the bridges with drums. Under the bridge on SR-55 Bypass the portable barrier rail will remain in place long term, closing the outside shoulders under the bridge. Lane closures under bridge will also be utilized for texture coating the bridge with proper signing.
[Mid-State Construction Company, Inc./McMinnville/CNY196]
DISTRICT 29
BRADLEY COUNTY I-75 at Paul Huff Parkway Interchange modifications: During this reporting period, the contractor will continue work on permanent signs. Intermittent flagging operations and temporary lane closures may be necessary. Motorists are advised to reduce speed and use caution in the work zone.
[Summers-Taylor, Inc./Cleveland/CNX362]
BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will continue asphalt paving and final pavement markings. Intermittent flagging operations will take place throughout the project during various work activities. Night work is expected to occur as needed between the hours of 8 PM and 6 AM. The speed limit in the work zone has been reduced to 35 mph. Motorists are advised to use caution in the work zone and watch for flaggers assisting with traffic control.
[Summers-Taylor, Inc./Cleveland/CNV130]
BRADLEY COUNTY SR-60 (25TH ST. N.W.) Utility Work both directions from LM 13 to LM 16: Shoulder and lane closures on SR-60 (25th Street N.W.) between N. Ocoee Street and Harris Circle NW. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, personnel/flaggers, and barrels/cones will be present, 06/26/25 thru 07/09/25 from 9 am - 2 pm. [2025-266]
BRADLEY COUNTY SR-60 Utility Work both directions from LM 6 to LM 7: Flagger assisted lane closures on SR-60 from Leamington Lane SE to Red Hill Valley Road SE. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 07/09/25 thru 07/10/25 from 8 am - 2 pm. [2025-154]
BRADLEY COUNTY SR-2 [0-6.2] from Hamilton County Line to Boss Road microsurfacing: The contractor will continue microsurfacing operations on SR2 from the Hamilton County line (LM 0) to Boss Road (LM 6.2). The contractor will flag two (2) mile sections and a pacing vehicle will guide traffic through the workzone during microsurfacing operations. Flagging will begin 8AM each day. Traffic delays are expected during this work.
[Asphalt Paving Systems, Inc./Chattanooga West/CNZ022]
BRADLEY COUNTY SR-306 [0-5.55] from SR60 to SR308 resurfacing: During this reporting period the contractor will complete punch list work. Motorists should be aware of workers and construction equipment present during this time. Intermittent flagging of traffic may be necessary while work is occurring. [Asphalt Paving Systems, Inc./Cleveland/CNZ021]
HAMILTON COUNTY I-24 TDOT Maintenance westbound from MM 179 to MM 178: During this report period, crews will be performing concrete repairs on I-24 Westbound between the mile markers 179 and 178 from 9pm on 07/09/2025 to 6am 07/10/2025. Lane 2 will be closed during this period, including the William Street Westbound On ramp to I-24 Westbound. Traffic is advised to take alternat routes if possible.
HAMILTON COUNTY I-24 TDOT Maintenance westbound from MM 183.5 to MM 181.5: During this report period, crews will be performing concrete repairs on I-24 Westbound between the mile markers 183.5 and 181.5 from 9pm on 07/08/2025 to 6am 07/09/2025. Lanes 1 & 2 will be closed during this period. Traffic is advised to take alternate routes if possible.
HAMILTON COUNTY I-75 TDOT Maintenance northbound from MM 11.0 to MM 12.6: During this report period, crews will be performing concrete repairs on I-75 Northbound between the mile markers 11.0 and 12.6 from 9pm on 07/07/2025 to 6am 07/08/2025. Lanes 1 & 2 will be closed during this period. Traffic is advised to take alternate routes if possible.
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly Lane closures will occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. These closures may temporarily reduce traffic to a single lane. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. On Monday night (7/7 9PM to 6AM) I-24 West will have a single right lane closure at the Germantown Road on ramp to I-24 West. This closure is needed to add temporary barrier rail for scheduled noise wall work on the ramp. The I-24 West on ramp at Germantown Road will be closed (starting 7/8 12AM) for noise wall installation work that will continue for the next several weeks (6 to 8 weeks). Detours will be in place for the ramp closure. Also, OH sign work has been pushed from this week to next week 7/8 to 7/11 (and extending into next report). This work will require lane closures on I-24EB/WB and I-75NB/SB (9PM to 6AM) for OH sign work reducing traffic down to one lane (Work will start at I-24 East to I-75 North and then progress to I-75 South to I-24 West). It may be necessary to do short duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrail, attenuators, etc. Portions of the left lane on North and South Terrace between Germantown Road and Spring Creek Road will remain closed for the installation of drainage structures, sanitary sewers, retaining and noise wall construction. The entrance and exit ramps to I-24 between Belvoir Avenue and Moore Road are currently closed (Note: A new entrance ramp from North Terrace to I-24 West is now open in this area. See above for information on the exit ramp from I-24 East to South Terrace). RESTRICTIONS: I-24 Ramps between Belvoir Ave. and S. Moore Road are closed. [Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]
HAMILTON COUNTY SR-2 (DODDS AVE.) TDOT Bridge Inspection both directions at LM 11.34: An inspection of the McCallie Avenue bridge over Dodds Avenue will result in lane closures on Dodds Avenue from 8 AM until 3 PM on Monday July 7, 2025. Motorists are advised to use caution, obey temporary traffic control, and be alert to changes in the traffic pattern as it changes throughout the day as the inspection progresses.
HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 0 to LM 0.74: Flagging operations on Lee Hwy (0E479) from near the entryway for McKay's to the end of Lee Hwy at General Shale Brick & Building Materials. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 07/08/25 through 07/11/2025 from 9 am - 2 pm. [2024-297]
HAMILTON COUNTY SR-27 (ROSSVILLE BLVD.) Utility Work both directions from LM 5 to LM 8: Flagger assisted lane closures on SR-27 (Rossville Blvd) at the intersection with E. 32nd Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 07/07/25 thru 07/11/25 from 9 am to 2 pm. [2025-321]
HAMILTON COUNTY SR-8 (RINGGOLD RD.) Utility Work both directions from LM 3 to LM 4: Flagger assisted lane closures on SR-8 (Ringgold Road) from Kingwood Drive / Wimberly Lane to McBrien Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 07/07/25 from 9 am - 2 pm, with a rain date of 07/08/25. [2025-359]
HAMILTON COUNTY SR-8 (SIGNAL MOUNTAIN BLVD.) Utility Work both directions from LM 13 to LM 18: Flagger assisted lane closures on SR-8 (Signal Mountain Blvd) from the intersection with SR-27 (Suck Creek Road) to Maryland Avenue. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 07/08/25 thru 08/04/25 from 9 am - 2 pm. [2025-042, 2025-361, 2025-362, 2025-363, 2025-364]
HAMILTON COUNTY I-124 (US-27) from I-24 Interchange to South of the Tennessee River Bridge: Daily lane closures are possible between 9 AM and 3:30 PM as the contractor work along the ramps and 4th Street. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control
[Stansell Electric Company, Inc./Chattanooga East/CNY900]
HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps and Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman’s Jewelers and Texas Roadhouse. The contractor has implemented a traffic shift on Hamilton Place Blvd. shifting NB and SB traffic to the east side of the existing roadway from near the I-75 SB on-ramp to near Bams Drive for the installation of storm drainage. The contractor will maintain 1 lane of traffic in each direction throughout this area. On the night of 07/08/25 the contractor will close 2 right lanes on I-75 NB from MM 4.0 to MM 5.0 for bridge construction activities. This closure will shift to 2 left lanes as the night progresses. On the night of 07/09/25 the contractor will close 2 right lanes on I-75 SB from MM 6.2 to MM 4.8 for bridge construction activities. This closure will shift to 2 left lanes as the night progresses. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel.
[Summers-Taylor, Inc./Chattanooga West/CNX358]
HAMILTON COUNTY SR-2 [11.33-11.92] from Dodds Ave to Seminole Drive tunnel rehabilitation: TRAFFIC SHIFT - Starting 06/04/25, both directions of traffic will be reduced to one lane and both flows of traffic will share the existing east bound tunnel. The west bound traffic will shift across the existing medians to be able to travel through the east bound tunnel. There will be a raised curb and reflective delineators that will divide traffic within the tunnel.
[Stansell Electric Company, Inc./Chattanooga East/CNY192]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, for bridge and grading work. The flagging operations will be performed on 07/03/25, 07/07/25, 07/08/25, and 07/09/25 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for bridge work, delivery of materials and equipment.
[Wright Brothers Construction Company, Inc./Chattanooga East/CNT336]
MCMINN COUNTY SR-30 (TENNESSEE AVE.) Utility Work both directions from LM 19 to LM 21: Flagger assisted lane closures on SR-30 from Cooper Street to Sable Road to 6th Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/06/25 thru 07/31/25 from 9 am - 2 pm. [2025-228]
MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the Northbound and Southbound traffic will be reduced to one lane and controlled by traffic signals. County road 567 will be closed to traffic (LOCAL TRAFFIC ONLY) and detoured to SR039. This closure is necessary to perform the bridge replacement. The lane restriction will remain in place until the bridge replacement is completed.
[Whaley Construction, LLC/Chattanooga East/CNX069]
MCMINN COUNTY SR-39 from west of Cook Drive to SR-30 and from SR-310 to the Monroe County Line: During this reporting period, the contractor will begin final pavement marking work on SR-39 near the Monroe County Line and SR-39 through downtown Athens. Motorists should be aware of workers in the area performing this work. Intermittent lane closures and flagging operations around the work area will be necessary. Work on the downtown section may occur between 9 PM and 6 AM.
[Rogers Group, Inc./Cleveland/CNZ038]
POLK COUNTY SR-123 [0-1.25] from North of SR68 to North Carolina State Line resurfacing: During this reporting period the contractor is scheduled to begin resurfacing work on SR-123. Temporary lane closures will be necessary to perform this work. Motorists are advised to slow down and watch for flaggers who will assist with directing traffic.
[APAC - Atlantic, Inc./Cleveland/CNZ040]
POLK COUNTY SR-40 [23.59-26] from Carrianne Hills Rd to East of Main Street resurfacing: During this reporting period the contractor is scheduled to begin resurfacing work on SR-40. Temporary lane closures will be necessary to perform this work. Motorists are advised to slow down and watch for flaggers who will assist with directing traffic.
[APAC - Atlantic, Inc./Cleveland/CNZ040]
POLK COUNTY SR-68 construction of bridge over Brush Creek (LM 16.4): During this update period, the contractor will continue final grading, asphalt paving, and guardrail installation. A temporary traffic signal system is active on SR-68 near LM 16.4. The Northbound lane of SR-68 will be closed in the area controlled by the temporary traffic signal system. Motorists are advised to reduce speed and use caution in the work zone. Motorists should be aware that temporary stopping and shifting of traffic may be necessary during paving operation.
[Wright Brothers Construction Company, Inc./Cleveland/CNX347]
POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period the contractor will continue installing EPSC measures and performing grading work. Motorists should be aware of workers in the area performing this work. Intermittent flagging operations around the work area may be necessary. Additional traffic control devices will be installed soon.
[Wright Brothers Construction Company, Inc./Cleveland/CNZ042 ]
RHEA COUNTY SR-302 (NEW LAKE RD.) Utility Work both directions from LM 9 to LM 12: Flagger assisted lane closures on SR-302 (New Lake Road) from SR-68 (Watts Bar Hwy) to Hinch Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/30/25 thru 07/11/25 from 9 am - 2 pm. [2025-382]
RHEA COUNTY SR-68 (WASSOM MEMORIAL HWY.) Utility Work both directions from LM 5 to LM 8: Flagger assisted lane closures on SR-68 (Wasson Memorial Hwy) from SR-68 (Rhea County Hwy) to Firetower Road / Beauty Peak Lane. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 07/07/25 thru 07/18/25 from 9 am - 2 pm. [2025-402]
RHEA COUNTY SR-29 [14.66-19.879] from Boofer Lane to Metzger LN Resurfacing: Paving operations are planned to begin 06/30/25. The contractor will utilize temporary lane closures from 7AM to 6PM during paving operations. Motorists should use caution while traveling on this route and pay attention to all construction signage.
[Rogers Group, Inc./Chattanooga West/CNY118]
RHEA COUNTY SR-30 repair of bridge over Tennessee River: The contractor will be making repairs under the Tennessee River Bridge. Watercraft users should use caution when accessing the TWRA boating ramp under the bridge in Rhea County. The contractor will have equipment and materials in the area of the access road for the boating ramp.
[Mid-State Construction Company, Inc./Chattanooga East/CNY201]
REGION WIDE
REGION 2 The on-call concrete pavement repair at various locations on various Interstate and State Routes: The contractor will be repairing concrete pavement on ramps at I-24 exit 97. The ramps being repaired at exit 97 are the I-24 WB off ramp, the EB off ramp, and the EB on ramp. This work will require the narrowing of each ramp with a minimum open lane width of 10 feet. Please use caution when driving through the work zones.
[Bluegrass Contracting Corporation/Dunlap/CNY295]
REGION 2 Dynamic Message Sign (DMS) Life Cycle Replacement: Lane Closures will be needed on Bradley I-75 NB between MM 25 and MM 35 and on McMinn I-75 SB between MM 44 and MM 36 the nights of 07/09/25 and 07/10/25 between he hours of 8PM and 6AM. Shoulder Closures will be in place on Bradley I-75 NB between MM 25 and MM 35, on McMinn I-75 SB between MM 44 and MM 36, and Marion County I-24 WB at MM 156. Trucks will be entering and exiting the work zone during daytime hours. RESTRICTIONS: BRADLEY I-75 NB BETWEEN MM 25 and MM 35 AND MCMINN I-75 SB BETWEEN MM 44 and MM 36 both the inside and outside shoulders will be closed with concrete barrier rail installed. Total width will be 24 feet wide. Wide loads may need to utilize both lanes of traffic through this area.
[Davis H. Elliot Construction Company, Inc./Chattanooga East/CNX413]
REGION 2 Installation of new and upgraded curb ramps and other miscellaneous pedestrian safety improvements: The ADA curb ramp upgrades on various State Routes: Construction activities are ongoing along Market Street, Alton Parkway, and Rossville Blvd in Chattanooga. The contractor is working on removing and replacing the concrete sidewalk and curb ramps. The sidewalk will be closed in this area to all users. Lane closures may be required at times for construction activities. Signs and flaggers may be utilized during these lane closures. Motorists should use caution when traveling through the work zone.
[Southern Constructors, Inc./Chattanooga East/CNY253]
REGION 2 The drain cleaning on various Interstate and State Routes: Drain cleaning operations are planned on various routes throughout Region 2. This is a mobile operation along the shoulders with impacts to adjacent traffic lanes. Temporary lane closures maybe utilized to complete this work. These operations will occur at night Sunday through Thursday between 8 PM and 6 AM.
[Sweeping Corporation of America, Inc./Chattanooga West/CNY226]
REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed.
[Cumberland Guardrail, Inc./McMinnville/CNY105]
REGION 2 The sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes.
[Sweeping Corporation of America, Inc./Chattanooga West/CNY210]
REGION 2 Various Interstate and SRs - Cable Barrier Repair: The contractor will have short term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed.
[LU, Inc./McMinnville/CNY183]
REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic. Flaggers will assist with traffic control as needed.
[Lumin8 Transportation Technologies, LLC/Chattanooga East/CNX270]
RESTRICTIONS
CUMBERLAND COUNTY - CNZ103: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02.
PUTNAM COUNTY - Horizontal clearance will be restricted to 10FT. NO TRACTOR TRAILERS.
FRANKLIN COUNTY - CNY068: Old Decherd Road at Wagner Creek is closed.
HAMILTON COUNTY - DB2101: I-24 Ramps between Belvoir Ave. and S. Moore Road are closed.
REGION 2 - CNX413: BRADLEY I-75 NB BETWEEN MM 25 and MM 35 AND MCMINN I-75 SB BETWEEN MM 44 and MM 36 both the inside and outside shoulders will be closed with concrete barrier rail installed. Total width will be 24 feet wide. Wide loads may need to utilize both lanes of traffic through this area.
###