Roadway Activity Report for the Lower East and Upper Cumberland (June 19-25, 2025)

Friday, June 20, 2025 | 01:52pm

                                                                                                      DISTRICT 27

CLAY COUNTY SR-52 [18.7-20.56] from South of Boyd Street to Near SR-53 resurfacing: The contractor has completed resurfacing. Intermittent lane closures will be used along with flaggers to control traffic through the work zone as the contractor completes the remaining incidental work. Motorists are encouraged to use caution and watch for construction equipment and personnel. [Rogers Group, Inc./Livingston/CNZ023]

CLAY, CUMBERLAND, DEKALB, PICKETT, PUTNAM, AND WHITE COUNTY The ADA curb ramp upgrades on various State Routes: The contractor will be removing and replacing curb ramps in Pickett County on SR-325 from LM 4.23 (near Hillcrest Drive) to LM 8.08 (near E. Main Street). During this work, sidewalk closures will be in place and lane closures will be used to facilitate the work. Flaggers will be present to control the flow of traffic through the work zone. Motorists are encouraged to use caution through the work zone and should be prepared to stop.
 [MarCor Construction, Inc./Cookeville/CNY252]

CUMBERLAND COUNTY I-40 Utility Work both directions from MM 304.4 to MM 311: Officer assisted rolling roadblock on I-40 beginning eastbound in Putnam County LM 299.6 (near Exit 300 Monterey/Livingston) and westbound in Cumberland County at LM 310.2 (near Exit 311 Plateau Road). Message boards, signage, trucks, and law enforcement vehicles will be preset along I-40 and ramps. Motorists should be prepared to stop and expect delays. 06/22/25 from 6 am to 8 am. [PIN 105727.01 - Utilities Office]

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Hubert Conley Road at the intersection of SR-28 has been closed for construction activities. The contractor has closed North Grace Hill Drive at the existing intersection of SR-28 (US-127) for construction activities. Motorists should utilize South Grace Hill Drive as the detour with appropriate signs. Traffic has been moved to temporary alignment on Plateau Road and permanent alignment on Potato Farm Road. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change. [Jones Bros. Contractors, LLC/Crossville/CNV009]

CUMBERLAND COUNTY SR-1 (US-70) construction of bridge over the Obed River (LM 12.7): Construction activities continue on SR-1 (US-70) over the Obed River bridge. SR-1 has been reopened. Construction crews will be working outside of the roadway to install utilities. Traffic should be cautious of construction equipment near the shoulders. Contractor may need to flag traffic to move equipment or vehicles across the road.
 [Whaley Construction, LLC/Crossville/CNX110]

CUMBERLAND COUNTY SR-1 [8.86-13.27] from Pomona Road to SR-24 resurfacing: The contractor has started resurfacing operations on SR-1 from near Pomona Road to SR-24 intersection. The contractor will utilize temporary lane closures and flaggers throughout the project. Signs will accompany any closures. Motorists should use caution when traveling through the work zone. [Rogers Group, Inc./Crossville/CNZ067]

CUMBERLAND COUNTY SR-28 (Main Street, US-127) downtown pedestrian improvement project between Lantana Road (Highway 70 East) and Neecham Street: Construction activities are ongoing along SR-28 (Main Street). The contractor is working on removing and replacing the concrete sidewalk and curb ramps from Lantana Road to West 2nd Street. The contractor will be pouring concrete beginning from Lantana Road to West 2nd Street. During this time, the contractor will utilize flaggers, and the road will be reduced to one lane for a period of time. Once operations are completed for the day, traffic will be reopened to two lanes. The shoulder parking along this area has been closed. Signs and flaggers may be utilized during these lane closures and/or lane shifts. Motorists should use caution when traveling through the work zone. [Adams Contracting, LLC/Crossville/LP24_1]

CUMBERLAND COUNTY SR-28 (US-127) [5.11-8.9] from north of Hillendale Road to south of Sawmill Road resurfacing: The contractor continues resurfacing operations on SR-28. Lane closures will be utilized during operations. Flaggers and signs will be displayed prior to the work zone. Motorists should use caution when traveling in the area.
 [Rogers Group, Inc./Crossville/CNZ030]

CUMBERLAND COUNTY SR-298 [8.35-9.02] from north of Catoosa Canyon Dr to south of Obed Pines Rd construction of a small drainage structure: The contractor continues construction activities on Genesis Road (SR-298). Both lanes of Genesis Road (SR-298) at LM 8.35 to LM 9.02 have been closed and will be closed for the duration of the project with a posted detour route along SR-28 (US-127) and SR-62. The contractor will be working to replace a culvert underneath Genesis Road and installing retaining walls. RESTRICTIONS: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02. [J. Hill Excavating, LLC/Crossville/CNZ103]

CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Construction activities are in progress. Contractor anticipates opening the roadway to all lanes of traffic. Motorists should be cautious of the change in traffic. Activities may require temporary lane closures and/or traffic stoppages on Interstate Drive (SR-462), as well as short term closures of city streets. Flagging operations will accompany these closures with appropriate signs. Traffic has been shifted to the center lanes along Interstate Drive (SR-462). Motorists traveling west on Interstate Drive should be mindful of the "Right Turn Only" lane at the intersection of Stout Drive. Motorists should use caution when traveling through the work zone. [Rogers Group, Inc./Crossville/CNV010]

CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor will continue work along the new alignment of SR 28. Flaggers are being intermittently used to control traffic through parts of the workzone. Motorists are encouraged to use caution and watch for construction equipment and personnel adjacent to the roadway. [Jones Bros. Contractors, LLC/Cookeville/CNV300]

DEKALB COUNTY SR-26 (SPARTA HWY.) Utility Work both directions from LM 26 to LM 29.75: Flagger assisted lane closures on SR-26 (Sparta Hwy) from the White County line to Billings Road / Johnson Chapel Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 05/28/25 thru 08/30/25 from 8 am - 3 pm. [2024-410]

DEKALB COUNTY SR-26 (W. BROAD ST.) Utility Work both directions from LM 16 to LM 18: Shoulder and lane closures on SR-26 (W. Broad Street) between Dry Creek Road and Wal-Mart entrance. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, personnel/flaggers, and barrels/cones will be present, 06/19/25 thru 06/30/25 from 8 am - 3 pm. [2023-710]

DEKALB COUNTY SR-264 (TEMPERANCE HALL RD.) TDOT Maintenance northbound from LM 0.0 to LM 1.0: SR264 will be reduced to one lane from 6/19/25 thru 6/25/25 to repair a slide area near the 0.54MM. Traffic signals will be in place. Motorists are encouraged to slow down and use caution when in the area.

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading and construction activities throughout the project. Temporary lane closures and periodic traffic stoppages will be necessary for construction activities and motorists should be prepared to stop while traveling through the work zone. Motorists are encouraged to obey posted speed limit and to watch for construction equipment and personnel adjacent to the roadway. The West end of Old Liberty Road will be closed to through traffic due to construction activities. Motorists and EMS will need to use the East entrance of Old Liberty Road to gain access and follow detour signs.
 [Twin K Construction/Cookeville/CNV012]

OVERTON COUNTY SR-52 resurfacing from east of SR-294 (LM 12.2) to near Dogwalk Road (LM 18.3): The contractor has completed resurfacing. Intermittent lane closures will be used along with flaggers to control traffic through the work zone as the contractor completes the remaining incidental work. Motorists are encouraged to use caution and watch for construction equipment and personnel. [Rogers Group, Inc./Livingston/CNZ039]

OVERTON COUNTY SR-52 [10.96-11.28] from Near Henson St. to Robert St. Resurfacing: The contractor has completed resurfacing. Intermittent lane closures will be used along with flaggers to control traffic through the work zone as the contractor completes the remaining incidental work. Motorists are encouraged to use caution and watch for construction equipment and personnel.
 [Rogers Group, Inc./Livingston/CNZ039]

OVERTON COUNTY SR-85 [11.17-11.91] from SR-111 to SR-52 resurfacing: The contractor has completed resurfacing. Intermittent lane closures will be used along with flaggers to control traffic through the work zone as the contractor completes the remaining incidental work. Motorists are encouraged to use caution and watch for construction equipment and personnel. [Rogers Group, Inc./Livingston/CNZ039]

PICKETT COUNTY SR-111 (HWY. ONE ELEVEN) TDOT Bridge Inspection southbound at LM 3.21: On Wednesday, June 25th, TDOT consultants will perform an evaluation of the L. B. Hassler Memorial Bridge over the Obed River in Pickett County. This work will require closure of the south-bound shoulder on the bridge from 8:30 AM until 3:30 PM.

PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. West Davis Road and Henley Drive remain closed at the intersection of SR-136 with detour signs to utilize Bunker Hill Road. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel. [Rogers Group, Inc./Cookeville/CNV284]

PUTNAM COUNTY SR-136 (S. JEFFERSON AVE.) Utility Work southbound from LM 2.55 to LM 2.75: Southbound lane closures on SR-136 (S Jefferson Ave) between Spring Street Town Square to I-40. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/14/24 through 07/30/25 from 9 am - 2 pm. [2024-640]

PUTNAM COUNTY SR-164 (HANGING LIMB RD.) Utility Work both directions from LM 1 to LM 4: Temporary stop light assisted lane closures on SR-164 (Hanging Limb Road) at the intersection with Lake Hills Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, personnel, and barrels/cones will be present, 06/23/25 thru 06/30/25. The temporary stop light will be active 24/7, with work being performed from 7:30 am - 5 pm. [2025-334]

PUTNAM COUNTY SR-84 (CALFKILLER HWY.) TDOT Maintenance northbound from LM 3.0 to LM 4.0: SR84 will be closed Monday- Saturday 7:00AM-5:00PM from 6/19/25 thru 7/19/25 to repair a slide area near the 3.2MM. All other times the roadway will be reduced to one lane with signals. Motorists are encouraged to slow down and use caution when in the area. RESTRICTIONS: Horizontal clearance will be restricted to 10FT. NO TRACTOR TRAILERS.

PUTNAM COUNTY SR-84 (CALFKILLER HWY.) Utility Work both directions from LM 1 to LM 8: Flagger assisted lane closures on SR-84 (Calfkiller Hwy) from the White County line to Hidden Acres Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/24/25 thru 07/30/25 from 8 am - 3 pm. [2023-577]

PUTNAM COUNTY SR-24 [23.27-29.89] from Hitchcock Drive to Mill Creek Road Resurfacing: The contractor will be continuing milling and paving operations. During this work, lane closures will be utilized with one lane shut down. Flaggers will be present to control the flow of traffic through the work zone. Motorists are encouraged to use caution as they approach the work zone, and they should be prepared to stop. [Rogers Group, Inc./Cookeville/CNZ041]

WHITE COUNTY SR-26 (SMITHVILLE HWY.) Utility Work both directions from LM 0 to LM 1: Flagger assisted lane closures on SR-26 (Sparta Hwy) from the DeKalb County line to Jay Hutchings Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 05/28/25 thru 08/30/25 from 8 am - 3 pm. [2024-410]

 

                                                                                                        DISTRICT 28

BLEDSOE COUNTY SR-30 and SR-443, the grading, drainage, stream relocation, widening, and resurfacing on Summer City Road: The contractor will be performing grade work and widening on Summer City Road in Bledsoe County. This work will narrow the lanes at LM 2.0 and LM 4.3 and will leave both lanes open to traffic. Please slow down and use caution when driving through the work zone. [Rogers Group, Inc./Dunlap/CNY153]

COFFEE COUNTY I-24 (MM 117) construction of an overpass carrying Wattendorf Memorial Highway/AEDC Road, including grading, drainage, retaining walls, and paving: Drivers can expect short term flagging operations for trucks entering and exiting the work zone on Wattendorf Highway. Please use caution when traveling through the work zone.
 [Jones Bros. Contractors, LLC/Tullahoma/CNZ029]

COFFEE COUNTY I-24 resurfacing from east of SR-2 (US-41) (LM 8.9) to near SR-55 (LM 14.8), including bridge expansion joint repairs and thin epoxy overlay: Beginning 06/22/2025, there will be nightly alternating lane closures on I-24 from 7PM-6AM for resurfacing operations. One lane in each direction will be maintained at all times.
 [Rogers Group, Inc./Tullahoma/CNY262]

COFFEE COUNTY I-24 (MM 105) construction of an overpass carrying SR-2 (US-41): Phase 2 of I-24 bridge replacement at Exit 105 will continue this week. SR-2 will be reduced to one lane utilizing traffic signal system. The temporary traffic signal will remain in effect until 10/16/25.
 [Bell and Associates Construction, LP/Tullahoma/CNX309]

COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 1 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. Contractor may use temporary lane shifts to complete utility work. Phase 1 traffic shift has reduced lanes from 3 to 2 from Cedar Lane to near Grau Lane in order to continue bridge replacement and storm drainage work.
 [Dement Construction Company, LLC/Tullahoma/CNX912]

COFFEE COUNTY SR-55 repair of the bridge over the Little Duck River (LM 14.0): Lanes are reduced to one lane in each direction across the SR-55 bridge over the Little Duck River for bridge repair work. This lane reduction will be in place until work is complete in Fall 2025.
 [Mid-State Construction Company, Inc./Tullahoma/CNX412]

COFFEE COUNTY SR-55 [13.79-15.32] from US-41 to north of Interstate Drive resurfacing: There will be no lane closures during Bonnaroo. Lane closures for final pavement markings will resume Tuesday 6/17 and will continue nightly until complete from 7PM to 6AM. One lane in each direction will be maintained at all times. [Volunteer Paving, LLC/Tullahoma/CNY267]

FRANKLIN COUNTY SR-130 (OLD TULLAHOMA RD.) Utility Work both directions from LM 3 to LM 5: Flagger assisted lane closures on SR-130 (Old Tullahoma Road) at the intersection with Hurricane Road / Blue Creek Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/16/25 thru 06/30/25 from 9 am - 2 pm. [2025-180]

FRANKLIN COUNTY Old Decherd Road over Wagner Creek (LM 0.3) construction of a bridge: Old Decherd Road is closed at Wagner Creek for bridge replacement. A signed detour is in place. The road closure will be in place for the duration of the project through June 30th, 2025. RESTRICTIONS: Old Decherd Road at Wagner Creek is closed.
 [Dement Construction Company, LLC/Tullahoma/CNY068]

MARION COUNTY SR-2 (US-HWY. 41) Utility Work both directions from LM 32 to LM 34: Flagger assisted lane closures on SR-2 (US Hwy 41) in front of Kelly's Ferry Church of God west of Raccoon Mountain Drive. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/18/25 thru 06/30/25 from 9 am - 2 pm. [2025-053]

MARION COUNTY SR-156 repair of bridge over Tennessee River, LM 15.2: The contractor will be performing painting operations and structural repairs on the SR-156 bridge over the Tennessee River in South Pittsburg. This work will require a traffic shift leaving both lanes open to traffic. Please use caution when driving through the work zone.
 [Olympus Painting Contractors Inc./Dunlap/CNY063]

SEQUATCHIE COUNTY SR-8 (RANKIN AVE.) Utility Work both directions from LM 13 to LM 15: Flagger assisted lane closures on SR-8 (Rankin Avenue) between Hwy 28 / Main Street S and Wilhoit Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 05/15/25 thru 06/25/25 from 9 am - 2 pm. [2025-317]

WARREN COUNTY SR-1 (US-70S) bridge repair over SR-55 (LM 10.5): The contractor will maintain the closure of one lane on SR-1 on both the EB and WB sides on the bridges with drums. Under the bridge on SR-55 Bypass the portable barrier rail will remain in place long term, closing the outside shoulders under the bridge. Temporary lane and shoulder closures on and surrounding over and under bridge will also be utilized as needed with proper signing. RESTRICTIONS: Maximum width 15 feet both directions. [Mid-State Construction Company, Inc./McMinnville/CNY196]

 

                                                                                                      DISTRICT 29

BRADLEY COUNTY I-75 at Paul Huff Parkway Interchange modifications: During this reporting period, the contractor will continue work on permanent signs. Intermittent flagging operations and temporary lane closures may be necessary. Motorists are advised to reduce speed and use caution in the work zone. [Summers-Taylor, Inc./Cleveland/CNX362]

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will continue grading work and install driveways, sidewalk, and curb. Intermittent flagging operations will take place throughout the project during various work activities. The contractor is also scheduled to begin asphalt paving beginning 06/23/25 between the hours of 8 PM and 6 AM. This work is expected to continue for several days and will require temporary shifting of traffic. The speed limit in the work zone has been reduced to 35 mph. Motorists are advised to use caution in the work zone and watch for flaggers assisting with traffic control. [Summers-Taylor, Inc./Cleveland/CNV130]

BRADLEY COUNTY SR-2 [0-6.2] from Hamilton County Line to Boss Road micro surfacing: The contractor will continue micro surfacing operations on SR2 from the Hamilton County line (LM 0) to Boss Road (LM 6.2). The contractor will flag two (2) mile sections and a pacing vehicle will guide traffic through the work zone during micro surfacing operations. Flagging will begin 8AM each day. Traffic delays are expected during this work.
 [Asphalt Paving Systems, Inc./Chattanooga West/CNZ022]

BRADLEY COUNTY SR-306 [0-5.55] from SR60 to SR308 resurfacing: During this reporting period the contractor will complete final pavement markings. Motorists should be aware of workers and construction equipment present during this time. Intermittent flagging of traffic will be necessary while work is occurring. [Asphalt Paving Systems, Inc./Cleveland/CNZ021]

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly Lane closures will occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. These closures may temporarily reduce traffic to a single lane. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. (Note: Currently on Wednesday (6/18) and Thursday night (6/19) the contractor is scheduled to have lane closures on I-24 West from 9 PM to 6 AM. During these closures, paving, striping and other needed work will take place between South Moore Road and Germantown Road along with work on North Terrance in this area. A new entrance ramp to I-24 West from North Terrance between South Moore Road and Belvoir Avenue will be opened to traffic. Also, during these nightly closures (6/18 and 6/19) the I-24 West entrance ramp from Germantown Road will be temporarily closed (9 PM to 6 AM) for reconfiguration and restriping of lanes, along with tree trimming and other work. Advanced warnings and detours will be posted. From Friday night (6/20) at 9 PM through Monday morning (6/23) at 6 AM the contractor will temporarily reduce the 3 lanes of traffic on I-24 West to 2 lanes and detour them from the interstate to a temporary alignment on North Terrace and back onto the interstate using the Germantown Road entrance ramp. This temporary traffic change will allow the contractor to have safe access to areas necessary for the final tie-in of I-24 West to the bridge over Germantown Road. Germantown Road and portions of North Terrace will be closed for this weekend, and detours will be posted. A designated truck detour route using South Moore Road will be posted. Law enforcement officers will be present throughout the period when detours and closures are in effect. During installation and removal of this temporary weekend detour, the contractor may reduce interstate traffic to a single lane for a short time very late at night or very early in the morning. Traffic will be returned to the interstate and 3 lanes open by 6 AM Monday (6/23) morning. All work is weather sensitive, and should it be canceled, it will be rescheduled to the next available days. From Monday (6/23) through Wednesday (6/25) the contractor will continue to have nightly closures (9 PM to 6 AM) on I-24 East in preparation for a similar weekend traffic shift planned for the future.) It may be necessary to do short duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrail, attenuators, etc. Portions of the left lane on North and South Terrace between Germantown Road and Spring Creek Road will remain closed for the installation of drainage structures, sanitary sewers, retaining and noise wall construction. All work is weather permitting. The entrance and exit ramps to I-24 between Belvoir Avenue and Moore Road are currently closed. (Note: See above for new information on the entrance ramp from North Terrace to I-24 West) RESTRICTIONS: I-24 Ramps between Belvoir Ave. and S. Moore Road are closed.
 [Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]

HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work both directions from LM 14 to LM 15: NIGHTTIME Flagger assisted lane closures on SR-2 (Brainerd Road) between Spring Creek Road and Howell Avenue. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 03/03/25 through 06/25/25 from 9 pm - 5 am. [2025-016]

HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 18 to LM 21: Flagger assisted lane closures on SR-2 (Lee Hwy) between Robin Drive and Courage Way. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/23/25 thru 06/24/25 from 9 am - 2 pm. [2025-092]

HAMILTON COUNTY SR-27 (ROSSVILLE BLVD.) Utility Work both directions from LM 5 to LM 8: Flagger assisted lane closures on SR-27 (Rossville Blvd) at the intersection with E. 32nd Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/23/25 thru 06/25/25 from 9 am - 2 pm. [2025-321]

HAMILTON COUNTY SR-319 (HIXSON PK.) Utility Work both directions from LM 16 to LM 19: Flagger assisted lane closures on SR-319 (Hixson Pike) between Yaphank Road and Frankie Lane. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/23/25 thru 06/27/25 from 9 am - 2 pm. [2025-374]

HAMILTON COUNTY SR-320 (E. BRAINERD RD.) Utility Work both directions from LM 1 to LM 4: Shoulder and lane closures on SR-320 (E. Brainerd Road) between Kenmoor Drive and Meadowlark Lane. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/23/25 thru 06/30/25 from 9 am - 2 pm. [2025-390]

HAMILTON COUNTY SR-320 (E. BRAINERD RD.) Utility Work both directions from LM 6 to LM 9: Flagger assisted lane closures on SR-320 (E. Brainerd Road) between James Allen Trail and Generations Way. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/19/25 thru 06/23/25 from 9 am - 2 pm. [2025-445]

HAMILTON COUNTY I-124 (US-27) from I-24 Interchange to South of the Tennessee River Bridge: Daily lane closures are possible between 9 AM and 3:30 PM as the contractor work along the ramps and 4th Street. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control. [Stansell Electric Company, Inc./Chattanooga East/CNY900]

HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps and Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman’s Jewelers and Texas Roadhouse. The contractor has implemented a traffic shift on Hamilton Place Blvd. shifting NB and SB traffic to the east side of the existing roadway from near the I-75 SB on-ramp to near Bams Drive for the installation of storm drainage. The contractor will maintain 1 lane of traffic in each direction throughout this area. On the nights of 05/24/25 and 05/25/25 the contractor will install a single right lane closure on I-75 SB from MM 7.2 to MM 6.0 for the installation of concrete barrier rail on the right shoulder. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel. [Summers-Taylor, Inc./Chattanooga West/CNX358]

HAMILTON COUNTY SR-2 [11.33-11.92] from Dodds Ave to Seminole Drive tunnel rehabilitation: TRAFFIC SHIFT - Starting 06/04/25, both directions of traffic will be reduced to one lane and both flows of traffic will share the existing east bound tunnel. The west bound traffic will shift across the existing medians to be able to travel through the east bound tunnel. There will be a raised curb and reflective delineators that will divide traffic within the tunnel.
 [Stansell Electric Company, Inc./Chattanooga East/CNY192]

HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, for bridge and grading work. The flagging operations will be performed on 06/19/25, 06/20/25, 06/23/25, 06/24/25, and 06/25/25 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for bridge work, delivery of materials and equipment. On 06/25/25, a traffic shift will be implemented onto new alignment from the intersection of Apison Pike/Collegedale Pkwy to Apison Pike/University Drive.
 [Wright Brothers Construction Company, Inc./Chattanooga East/CNT336]

MCMINN COUNTY SR-30 (DECATUR PK.) Utility Work both directions from LM 8 to LM 11: Flagger assisted lane closures on SR-30 (Decatur Pike) between Westside Street / Mission Street and Hughes Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/25/25 from 9 am - 1 pm, with a rain date of 07/02/25. [2025-368]

MCMINN COUNTY SR-30 (TENNESSEE AVE.) Utility Work both directions from LM 19 to LM 21: Flagger assisted lane closures on SR-30 from Cooper Street to Sable Road to 6th Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/06/25 thru 07/31/25 from 9 am - 2 pm. [2025-228]

MCMINN COUNTY SR-30 (US-411) Utility Work both directions from LM 20 to LM 21: Flagger assisted lane closures on SR-30 (US-411) between 7th Street and 3rd Street / Mecca Pike. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/05/25 thru 06/30/25 from 9 am - 2 pm. [2025-316]

MCMINN COUNTY SR-39 (W. ATHENS ST.) Utility Work both directions from LM 12 to LM 16: Flagger assisted lane closures on SR-39 (W. Athens Street) between Casey Gap Zion Hill Road and Sunny Side Avenue. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/24/25 from 9 am - 1 pm, with a rain date of 07/01/25. [2025-354]

MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the Northbound and Southbound traffic will be reduced to one lane and controlled by traffic signals. County road 567 will be closed to traffic (LOCAL TRAFFIC ONLY) and detoured to SR039. This closure is necessary to perform the bridge replacement. The lane restriction will remain in place until the bridge replacement is completed.
 [Whaley Construction, LLC/Chattanooga East/CNX069]

MCMINN COUNTY SR-39 from west of Cook Drive to SR-30 and from SR-310 to the Monroe County Line: During this reporting period, the contractor will continue resurfacing work. Motorists should be aware of workers in the area performing this work. Intermittent lane closures and flagging operations around the work area will be necessary. A temporary lane closure will be necessary on the outside lane of SR-30 at the intersections with SR-39 while work is performed in this area. Work is scheduled to occur between 9 PM and 6 AM.
 [Rogers Group, Inc./Cleveland/CNZ038]

POLK COUNTY SR-68 construction of bridge over Brush Creek (LM 16.4): During this update period, the contractor will continue phase 2 grading and begin asphalt paving. A temporary traffic signal system is active on SR-68 near LM 16.4. The northbound lane of SR-68 will be closed in the area controlled by the temporary traffic signal system. Motorists are advised to reduce speed and use caution in the work zone. Motorists should be aware that temporary stopping and shifting of traffic may be necessary during paving operation. [Wright Brothers Construction Company, Inc./Cleveland/CNX347]

POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period the contractor will continue installing EPSC measures and begin grading work. Motorists should be aware of workers in the area performing this work. Intermittent flagging operations around the work area may be necessary. [Wright Brothers Construction Company, Inc./Cleveland/CNZ042]

RHEA COUNTY SR-29 (US-HWY. 27) Utility Work both directions from LM 25 to LM 33: Flagger assisted lane closures on SR-29 (US-Hwy 27) from Dewey Sheppard Lane to Whites Creek Road / Jenkins Waldo Lane. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/23/25 thru 07/02/25 from 9 am - 2 pm. [2025-282 & 2025-329]

RHEA COUNTY SR-68 (WATTS BAR HWY.) Utility Work both directions from LM 7 to LM 12: Flagger assisted lane closures on SR-68 (Watts Bar Hwy) between SR-27 / Rhea County Hwy and Walker Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/16/25 thru 06/27/25 from 9 am - 2 pm. [2025-328 & 2025-331]

RHEA COUNTY SR-29 [14.66-19.879] from Boofer Lane to Metzger LN Resurfacing: Paving operations are planned to begin 06/23/25. The contractor will utilize temporary lane closures from 7AM to 6PM during paving operations. Motorists should use caution while traveling on this route and pay attention to all construction signage. [Rogers Group, Inc./Chattanooga West/CNY118]

RHEA COUNTY SR-30 repair of bridge over Tennessee River: The repair of the bridge on S.R. 30 over the Tennessee River (L.M. 17.28): The bridge has been reduced to one lane of traffic under the control of a traffic signal. The contractor will be making repairs under the Tennessee River Bridge. Watercraft users should use caution when accessing the TWRA boating ramp under the bridge in Rhea County. The contractor will have equipment and materials in the area of the access road for the boating ramp. [Mid-State Construction Company, Inc./Chattanooga East/CNY201]

 

                                                                                                       REGION WIDE

REGION 2 The on-call concrete pavement repair at various locations on various Interstate and State Routes: The contractor will be repairing concrete pavement on ramps at I-24 exit 97. The ramps being repaired at exit 97 are the I-24 WB off ramp, the EB off ramp, and the EB on ramp. This work will require the narrowing of each ramp with a minimum open lane width of 10 feet. Please use caution when driving through the work zones.
 [Bluegrass Contracting Corporation/Dunlap/CNY295]

REGION 2 Dynamic Message Sign (DMS) Life Cycle Replacement: Shoulder Closures will be in place on Bradley I-75 NB between MM 25 and MM 35, on McMinn I-75 SB between MM 44 and MM 36, and Marion County I-24 WB at MM 156. Trucks will be entering and exiting the work zone during daytime hours. RESTRICTIONS: BRADLEY I-75 NB BETWEEN MM 25 and MM 35 AND MCMINN I-75 SB BETWEEN MM 44 and MM 36 both the inside and outside shoulders will be closed with concrete barrier rail installed. Total width will be 24 feet wide. Wide loads may need to utilize both lanes of traffic through this area.
 [Davis H. Elliot Construction Company, Inc./Chattanooga East/CNX413]

REGION 2 Installation of new and upgraded curb ramps and other miscellaneous pedestrian safety improvements: The ADA curb ramp upgrades on various State Routes: Construction activities are ongoing along Market Street, Alton Parkway, and Rossville Blvd in Chattanooga. The contractor is working on removing and replacing the concrete sidewalk and curb ramps. The sidewalk will be closed in this area to all users. Lane closures may be required at times for construction activities. Signs and flaggers may be utilized during these lane closures. Motorists should use caution when traveling through the work zone. [Southern Constructors, Inc./Chattanooga East/CNY253]

REGION 2 The drain cleaning on various Interstate and State Routes: Drain cleaning operations are planned on various routes throughout Region 2. This is a mobile operation along the shoulders with impacts to adjacent traffic lanes. Temporary lane closures maybe utilized to complete this work. These operations will occur at night Sunday through Thursday between 8 PM and 6 AM. [Sweeping Corporation of America, Inc./Chattanooga West/CNY226]

REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed. [Cumberland Guardrail, Inc./McMinnville/CNY105]

REGION 2 The sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes.
 [Sweeping Corporation of America, Inc./Chattanooga West/CNY210]

REGION 2 Thermoplastic retracing on various interstate and state routes: The contractor will be on site in Dekalb County along SR-26 from LM 15.920 - 28.240 and in Warren County along SR-55 from LM 0.00 - 4.77 and along SR-1 from LM 10.50 - 13.50 and LM 14.00 - 14.761. During this work, the contractor will utilize a mobile operation with mobile message boards and an attenuator truck. Motorists are encouraged to slow down as they approach the work and should be aware of the potential of stopped or slowing traffic. [Reynolds Sealing and Striping, Inc./Cookeville/CNZ054]

REGION 2 Various Interstate and SRs - Cable Barrier Repair: The contractor will have short term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed.
 [LU, Inc./McMinnville/CNY183]

REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic. Flaggers will assist with traffic control as needed. [Lumin8 Transportation Technologies, LLC/Chattanooga East/CNX270]

 

                                                                                                    RESTRICTIONS

CUMBERLAND COUNTY - CNZ103: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02.

PUTNAM COUNTY: Horizontal clearance will be restricted to 10FT. NO TRACTOR TRAILERS.

FRANKLIN COUNTY - CNY068: Old Decherd Road at Wagner Creek is closed.

WARREN COUNTY - CNY196: Maximum width 15 feet both directions.

HAMILTON COUNTY - DB2101: I-24 Ramps between Belvoir Ave. and S. Moore Road are closed.

REGION 2 - CNX413: BRADLEY I-75 NB BETWEEN MM 25 and MM 35 AND MCMINN I-75 SB BETWEEN MM 44 and MM 36 both the inside and outside shoulders will be closed with concrete barrier rail installed. Total width will be 24 feet wide. Wide loads may need to utilize both lanes of traffic through this area.

                                                                                                                ###