Roadway Activity Report for the Lower East and Upper Cumberland (November 06-12, 2025)
BLEDSOE COUNTY SR-30 and SR-443, the grading, drainage, stream relocation, widening, and resurfacing on Summer City Road: The contractor will be performing grade work and widening on Summer City Road in Bledsoe County. This work will narrow the lanes at LM 2.0 and LM 4.3 and will leave both lanes open to traffic. Please slow down and use caution when driving through the work zone. [Rogers Group, Inc./Dunlap/CNY153]
BRADLEY COUNTY SR-40 [5.1-9.7] from Lyles Rd. to Bradley-Polk County Line resurfacing: During this reporting period, the contractor will continue resurfacing work on SR-40. Temporary lane closures will be necessary during daytime hours on weekdays while work is performed. Motorists should use caution when traveling through the work zone and be aware of equipment in the area. [APAC - Atlantic, Inc./Cleveland/CNZ020]
BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will perform punch list work on SR-60 in Bradley County. Intermittent lane closures may be necessary while work occurs.
[Summers-Taylor, Inc./Cleveland/CNV130]
BRADLEY COUNTY SR-74 [11.445-11.83] from Whaley Road to SR-60 APD-40 drainage improvements: During this reporting period, the contractor will continue grading work on SR-74. Intermittent flagging operations and shoulder closures will be necessary periodically. Motorists should use caution and reduce speed when traveling through the work zone.
[APAC - Atlantic, Inc./Cleveland/CNZ243]
CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY. The installation of Weigh-in-Motion technology at 28 sites on various Interstate and State Routes: No Region 2 Lane Closures this week on CNX913. [Davis H. Elliot Construction Company, Inc./Maint - R2/CNX913]
CANNON COUNTY SR-281 [0-4.51] from SR-53 to Todd Rd resurfacing: The contractor will have lane closures during daylight hours as needed from 5 AM to 9 PM for punch list and project wrap-up operations as needed. Flaggers will be present during the lane closure operations, and at least one lane will remain open at all times. [Rogers Group, Inc./McMinnville/CNZ066]
COFFEE COUNTY I-24 (MM 117) construction of an overpass carrying Wattendorf Memorial Highway/AEDC Road, including grading, drainage, retaining walls, and paving: Drivers can expect short-term flagging operations for trucks entering and exiting the work zone on Wattendorf Highway. Please use caution when traveling through the work zone.
[Jones Bros. Contractors, LLC/Tullahoma/CNZ029]
COFFEE COUNTY I-24 TDOT Bridge Maintenance westbound at MM 100.2: Bridge Repair operations will be conducted on 11/05/2025 from 8 PM to 2 AM and on 11/06/2025 from 8 PM to 2 AM with a lane closure. A rolling roadblock will be used to set up and take down the traffic control. THP will be used as motorists travel throughout the area.
COFFEE COUNTY SR-2 (US-41) TDOT Contractor both directions from LM 14.18 to LM 14.4: There will be a mobile traffic control operation as the TDOT contractor will be taking survey grades in the Sanitary and Storm Drains in this area. This will occur on Thursday and Friday, and possibly Monday and Tuesday the following week, from 9 AM - 3 PM.
COFFEE COUNTY SR-55 (MCMINNVILLE HWY.) TDOT Contractor both directions from LM 14.6 to LM 15.00: There will be a mobile traffic control operation as the TDOT contractor will be taking survey grades in the Sanitary and Storm Drains in this area. This will occur on Thursday and Friday and possibly Monday and Tuesday the following week, from 9 AM - 3 PM.
COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 1 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. The contractor may use temporary lane shifts to complete storm structure installations. Phase 1 traffic shift has reduced lanes from 3 to 2 from Cedar Lane to near Grau Lane in order to continue bridge replacement and storm drainage work.
[Dement Construction Company, LLC/Tullahoma/CNX912]
COFFEE COUNTY SR-55 repair of the bridge over the Little Duck River (LM 14.0): Lanes are reduced to one lane in each direction across the SR-55 bridge over the Little Duck River for bridge repair work. This lane reduction will be in place until work is complete in Fall 2025. [Mid-State Construction Company, Inc./Tullahoma/CNX412]
CUMBERLAND COUNTY SR-24 [15.056-15.56] from Crossville city limits to Seventh-Day Adventist Church and School bridge replacement: The contractor will be installing signs and beginning general clearing of the project outside of the roadway. Activities may require temporary lane closures and/or traffic stoppages on SR-24 to move equipment.
[Mid-State Construction Company, Inc./Crossville/CNZ206]
CUMBERLAND COUNTY SR-28 (US-127 S.) Utility Work both directions from LM 0.44 to LM 5.94: Northbound and Southbound Lane closures on SR-28 (HWY 127 S.) between Lowes Gap Rd. and Willard Brown Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 10/30/25 through 02/25/2026 from 9 am - 2 pm. [2025-659]
CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. The contractor has scheduled paving operations beginning on the north end of the project on the proposed alignment. The contractor has closed North Grace Hill Drive at the existing intersection of SR-28 (US-127) for construction activities. Motorists should utilize South Grace Hill Drive as the detour with appropriate signs. Traffic has been moved to temporary alignment on Plateau Road and permanent alignment on Potato Farm Road. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change. [Jones Bros. Contractors, LLC/Crossville/CNV009]
CUMBERLAND COUNTY SR-298 [8.35-9.02] from north of Catoosa Canyon Dr to south of Obed Pines Rd construction of a small drainage structure: The contractor continues construction activities on Genesis Road (SR-298). Both lanes of Genesis Road (SR-298) at LM 8.35 to LM 9.02 have been closed and will be closed for the duration of the project with a posted detour route along SR-28 (US-127) and SR-62. The contractor will be working to replace a culvert underneath Genesis Road and install retaining walls. RESTRICTIONS: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02. [J. Hill Excavating, LLC/Crossville/CNZ103]
CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Construction may take place as the contractor finishes remaining small items. Activities may require temporary lane closures and/or traffic stoppages on Interstate Drive (SR-462), as well as short-term closures of city streets. Flagging operations will accompany these closures with appropriate signs. Motorists should use caution when traveling through the work zone.
[Rogers Group, Inc./Crossville/CNV010]
CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor has shifted traffic to phase 2 on the newly constructed portions of SR-28 LM 0.90 to 1.98 in Fentress County. Work will proceed on the existing alignment of SR-28. Flaggers are being used intermittently as needed to control traffic through the work zone. Motorists are encouraged to use caution, be aware of new traffic signs and pavement markings, and watch for construction equipment and personnel throughout the project. [Jones Bros. Contractors, LLC/Cookeville/CNV300]
DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading and construction activities throughout the project. Temporary lane closures and periodic traffic stoppages will be necessary for construction activities and motorists should be prepared to stop while traveling through the work zone. Motorists are encouraged to obey the posted speed limit and to watch for construction equipment and personnel adjacent to the roadway. The West end of Old Liberty Road will be closed to through traffic due to construction activities. Motorists and EMS will need to use the East entrance of Old Liberty Road to gain access and follow detour signs.
[Twin K Construction/Cookeville/CNV012]
DEKALB COUNTY SR-26 [10.88-13.25] from Near East Main Street to Trapp Lane resurfacing: The contractor will be onsite intermittently to complete remaining contract work and complete any punch list work. Daily lane closures may be utilized to facilitate this work, and motorists should follow all signage and expect delays. [Tinsley Asphalt, LLC /Cookeville/CNZ136]
DEKALB COUNTY SR-96 (DALE RIDGE RD.) TDOT Maintenance in both directions from LM 12.5 to LM 12.9: SR96 will be closed both directions on 11/5/25 and 11/6/25 from 8 AM - 4 PM due to construction. Message boards will be in place. Motorists are encouraged to use caution when in the area.
FENTRESS COUNTY SR-62 [5.79-5.81] from west of SR-28 (US-127) to SR-28 (US-127) storm drain installation: The contractor will be closing a lane on SR-62 from LM 5.79 to LM 5.81 just west of SR-28 (US-127) to install a storm drain. The closure will occur daily from 6 AM to 5 PM beginning 11/10/25 to 11/14/25. Flaggers will be used to control traffic. Motorists are advised to pay attention to signs and flaggers, using caution as they travel through the work zone.
[Jones Bros. Contractors, LLC/Livingston/CNV300]
GRUNDY COUNTY SR-50 (--) Utility Work both directions from LM 0.08 to LM 0.16: Flagging assisted lane closures on Hwy 50 (SR 50) between Coffee County Rd. and I-24 Exit 127. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 11/11/25, with a rain date of 11/12/25 from 9 am - 2 pm/ [2025-647]
HAMILTON COUNTY I-124 (US-27) from I-24 Interchange to South of the Tennessee River Bridge: Daily lane closures are possible between 9 AM and 3:30 PM as the contractor works along the ramps and 4th Street. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control
[Stansell Electric Company, Inc./Chattanooga East/CNY900]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly Lane closures will occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. These closures may temporarily reduce traffic to a single lane. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. (Note: Nighttime Lane closures (9 PM to 6 AM) of I-24 West and East should be expected between Germantown Road and Spring Creek Road on Thursday (11/6) and from Sunday (11/9) to Thursday (11/13) next week for paving as well as painting and texture coating of retaining and noise walls. At times, traffic may be temporarily reduced to a single lane while this work is taking place. As paving of traffic lanes and the painting of walls progresses, it will be necessary to temporarily close entrance and exit ramps along I-24 for crews to safely perform their work. Message boards and detours will be posted to guide traffic to the next available ramp. Currently, the entrance ramp from South Terrace onto I-24 East (between South Moore Road and McBrien Road) is scheduled to be closed the nights of Thursday (11/6), and Sunday (11/9) through Tuesday (11/11) for painting and texture coating the various walls along the ramp. Most of the remaining work items on this project are temperature and weather-sensitive. If any of them are canceled due to inclement conditions, they will be rescheduled to take place on the next available day when adequate conditions exist.) It may also be necessary to do short-duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrails, attenuators, etc. Portions of the left lane on North and South Terrace between Germantown Road and Spring Creek Road will remain closed for the installation of drainage structures, sanitary sewers, retaining and noise wall construction.
[Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]
HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps and Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman’s Jewelers and Texas Roadhouse. The contractor has implemented a traffic shift on Hamilton Place Blvd. shifting NB and SB traffic to the east side of the existing roadway from near the I-75 SB on-ramp to near Bams Drive for the installation of storm drainage. The contractor will maintain 1 lane of traffic in each direction throughout this area. On the nights of 11/10/25 through 11/13/25, the contractor will close the I-75 SB Entrance Ramp from Shallowford Road from 10 PM until 6 AM for bridge beam erection. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel.
[Summers-Taylor, Inc./Chattanooga West/CNX358]
HAMILTON COUNTY I-75 [4.2-4.5] from Exit 4A to SR-153 to Exit 3 to East Brainerd Road box culvert rehabilitation: The right shoulder of SB I-75 is closed with concrete barrier rail in place. Drivers should watch for construction vehicles entering and exiting the interstate. [Wright Brothers Construction Company, Inc./Chattanooga East/CNZ186]
HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work both directions from LM 12.93 to LM 13.03: Flagging assisted lane closures on Brainerd Rd. Between Germantown Rd. and Belvoir Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 11/06/25 through 12/12/25 from 9 am - 2 pm/ [2025-687]
HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 0.0 to LM .74: Flagging assisted lane closures on Lee Hwy (OE479) from near the entryway for McKay's to the end of Lee Hwy at General Shale Brick & Building Materials. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 09/08/25 through 11/10/25 from 7 am - 5 pm/ [2024-297]
HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 18.80 to LM 18.86: Flagger assisted lane closures on SR-2 (Lee Hwy) between McCutcheon Rd and Elm Dr. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 10/2/25 thru 11/10/25 from 9 am - 2 pm. [2024-338]
HAMILTON COUNTY SR-312 (MAHAN GAP RD.) Utility Work both directions at LM 14.68: Flagger assisted lane closures on SR-312 (Mahan Gap Rd.) at the intersection of Mahan Gap Rd. and Bill Ln. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 11/12/25 from 9 am - 2 pm with a rain date of 11/14/2025 from 9 AM to 2 PM [2025-671]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317 during daytime hours. [Wright Brothers Construction Company, Inc./Chattanooga East/CNT336]
HAMILTON COUNTY SR-317 (APISON PK.) Utility Work both directions from LM 9.90 to LM 10.15: Daytime and Nighttime closure. Flagger assisted lane closures on SR-317 (Apison Pike) between Cash Ln. and Merc Ln. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, Daytime 11/6/25 thru 11/7/25 from 9 am - 2 pm. Nighttime 11/7/2025 through 11/9/2025 10 PM to 6 AM [2025-661]
HAMILTON COUNTY SR-8 [10.14-11.96] from Frazier Ave to Signal Mountain Blvd resurfacing: Contractor will be finishing roadway striping at night. Traffic may be detoured around intersections to complete work. [APAC - Atlantic, Inc./Chattanooga East/CNZ138]
JACKSON COUNTY SR-135 [15.74-20.76] from SR-56 to Clay County Line resurfacing: The contractor will be on site intermittently to work on punch list items. During this work temporary lane closures may be used with flaggers present. Signs warning of the closures will be in place. Motorists should use caution as they approach the work zone and should prepare to stop and follow the directions of the flagger. [Rogers Group, Inc./Cookeville/CNZ139]
MARION COUNTY I-24 [156.4-160.2] from 156.4 to 160.2 resurfacing: The contractor will be performing resurfacing operations on I-24 EB and WB in Marion County from MM 156.4 East of SR-28 to MM 160.2 West of the Tennessee River. This work will require single lane closures leaving one lane open in each direction each night worked. Resurfacing operations will be Sunday through Thursday from 6 PM CT - 5 AM CT. Please use caution when driving through the work zones.
[Talley Construction Company, Inc./Dunlap/CNZ108]
MARION COUNTY SR-108 [2.8-3.24] slide mitigation: The contractor will be performing slide mitigation operations, including grading, drainage and paving on SR-108 in Marion County at LM 2.8. The roadway will be reduced to one lane controlled by temporary traffic signals. The project completion date is 08/31/2027. Please use caution when driving through the work zone.
[Wright Brothers Construction Company, Inc./Dunlap/CNZ226]
MARION COUNTY SR-2 [17.2-17.3] from 17.2 to 17.3 construction: The contractor will be performing grading and drainage operations on SR-2 in Marion County near LM 17.25. This work will require a lane shift for the EB traffic; the WB traffic will be unaffected. Please slow down and use caution when driving through the work zone. [Talley Construction Company, Inc./Dunlap/CNZ244]
MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the contractor will be flagging the roadway to perform work. This flagging operation will only occur during daytime hours.
[Whaley Construction, LLC/Chattanooga East/CNX069]
MCMINN COUNTY SR-39 from west of Cook Drive to SR-30 and from SR-310 to the Monroe County Line: During this reporting period, the contractor will complete punch-list work on SR-39. Motorists should be aware of workers in the area performing this work. Intermittent lane closures and flagging operations around the work area will be necessary.
[Rogers Group, Inc./Cleveland/CNZ038]
POLK COUNTY SR-68 construction of bridge over Brush Creek (LM 16.4): During this update period, the contractor will continue punch list work on SR-68 in Polk County. Intermittent lane closures may be necessary to complete this work.
[Wright Brothers Construction Company, Inc./Cleveland/CNX347]
POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period the contractor will continue construction on the SR-68 North bridge. All SR-68 traffic is using the existing SR-68 South bridge while construction occurs on the new SR-68 North bridge. All SR-40/SR-68 interchange traffic will utilize the SR-68 South interchange ramps. A temporary 3-way stop has been implemented at the intersection of the SR-40 interchange ramp and SR-68. Motorists are encouraged to slow down when entering the construction zone and look out for new stop signs on SR-68 near the SR-40/SR-68 interchange.
[Wright Brothers Construction Company, Inc./Cleveland/CNZ042]
PUTNAM COUNTY I-40 Utility Work both directions from MM 298.0 to MM 301.6: Law Enforcement assisted rolling roadblock between Jackson Lee Rd Overpass, Eastbound and Exit 301 (Monterey Livingston) westbound. Message boards, signage and law enforcement vehicles will be present. Motorists should be aware of personnel and equipment, reduce speed, and be prepared to stop. 11/9/25 between 6:00 am and 9:00 am. With a rain date of 11/16/2025 between 6 AM and 9 AM (2024-874 & 2024-869]
PUTNAM COUNTY SR-111 (STATE HWY. 111) TDOT Maintenance southbound at LM 3.53: SR111 southbound will continue to be reduced to one lane for the construction of a new turning lane. Expect the roadway to be reduced to one lane weekdays between the hours of 8 AM-3 PM until the project is completed. Motorists are encouraged to follow signage and use caution when in the area.
PUTNAM COUNTY SR-136 (S. JEFFERSON AVE.) Utility Work both directions from LM 2.55 to LM 2.75: Northbound and southbound lane closures on SR-136 (S Jefferson Ave) between Spring Street Town Square to I-40. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/14/24 through 11/15/25 from 9 am - 2 pm. [2024-640]
PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Bunker Hill Rd is closed at the intersection of SR-136 with detour signs to utilize Henley Dr. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel and equipment adjacent to the roadway. [Rogers Group, Inc./Cookeville/CNV284]
PUTNAM COUNTY SR-24 (CROSSVILLE HWY.) Utility Work both directions from LM 35.55 to LM 38.09: Eastbound and Westbound Lane closures on SR-24 (Crossville Hwy.) between E. Wilder Ave. and Walker Farm Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/06/25 through 05/06/2026 from 9 am - 2 pm. [2025-521]
PUTNAM COUNTY SR-84 (CALFKILLER HWY.) Utility Work both directions from LM 1.0 to LM 8.0: Flagger assisted lane closures on SR-84 (Calfkiller Hwy) from the White County line to Hidden Acres Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/24/25 thru 11/30/25 from 8 am - 3 pm. [2023-577]
REGION 2 Dynamic Message Sign (DMS) Life Cycle Replacement: No lane closures this week.
[Davis H. Elliot Construction Company, Inc./Chattanooga East/CNX413]
REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short-term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic.
[Lumin8 Transportation Technologies, LLC/Chattanooga East/CNX270]
REGION 2 Snow-plowable marker re-lensing: The contractor will start snow-plowable lens replacement on 09/15/2025 on the following routes: Picket County SR-28 from LM 1.590 - 7.140, SR-52 from LM 0.000 - 2.260, SR-111 from LM 0.000 - 12.055, SR-154 from LM 0.000 - 5.726, SR-295 from LM 0.000 - 5.030, and SR-325 from LM 0.000 - 12.625, and Fentress County SR-28 from LM 0.000 - 33.580, SR-52 from LM 4.420 - 13.600, SR-52 from LM 17.620 - 27.930, SR-62 from LM 0.000 - 12.710, SR-85 from LM 0.000 - 11.010, SR-154 from LM 0.000 - 13.480, SR-296 from LM 0.000 - 3.030, SR-297 from LM 0.000 - 8.790, and SR-325 from LM 0.000 - 2.540. The contractor is expected to perform this work in the evening (8 PM - 6 AM) and will be utilizing a mobile operation. Motorists should use caution and expect delays when contract crews are present. [W.L. Markers Inc./Cookeville/CNZ053]
REGION 2 The crack sealing at various locations on various State Routes: The contractor will have lane closures between 5 AM and 9 PM for crack sealing operations. Work will continue 7 days per week unless the contractor stops for weather or other logistical purposes. Locations: Cumberland County SR-28 LM 14.96 to 8.25, Overton County SR-111 LM 3.29 to 10.69, Clay County SR-82 LM 20.58 to 26.60, Putnam County SR-111 LM 0.00 to 2.03
[Reynolds Sealing and Striping, Inc./McMinnville/CNZ143]
REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short-term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed.
[Reynolds Fence and Guardrail, Inc./McMinnville/CNZ112]
REGION 2 Thermoplastic retracing on various interstate and state routes: The contractor will be on site in Rhea County on SR-30 at SR-303, Clay County SR-51 at SR-52, SR-58 LM 17.430 - 17.830, Hamilton County SR-17 at LM 8.73, Hamilton County SR-317 at LM 0.517, Hamilton County SR-317 at SR-153 Interchange, Hamilton County SR-317 at LM 0.971, Hamilton County SR-317 at LM 1.308, Hamilton County SR-317 at LM 1.573 - 1.794, Rhea County SR-30 from SR-29 to Cottonport Road. During this work, the contractor will utilize a mobile operation with mobile message boards and an attenuator truck. Motorists are encouraged to slow down as they approach the work and should be aware of the potential of stopped or slowing traffic.
[Reynolds Sealing and Striping, Inc./Cookeville/CNZ054]
REGION 2 Various Interstate and SRs - Cable Barrier Repair: The contractor will have short-term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed.
[LU, Inc./McMinnville/CNY183]
WHITE COUNTY SR-111 (SPENCER HWY.) TDOT Maintenance southbound at LM 7.3: SR111 will be reduced to one lane starting 10/30/25 at 8:00 AM for the widening and resurfacing of a turning lane. Expect the roadway to be reduced to one lane weekdays between the hours of 8:00-3:00 PM until the project is completed. Motorists are encouraged to follow signage and use caution when in the area.
RESTRICTIONS
CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY - CNX913
CUMBERLAND COUNTY - CNZ103: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02.
###