CHEATHAM & ROBERTSON COUNTY I-24
The resurfacing on I-24 from the Robertson County line, crossing through Robertson County to the Davidson County line.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures in both directions for installation of thermoplastic, pavement markings, and rumble strips. There will be temporary ramp closures at Exit 31 (MM 25 – 31.6).
DAVIDSON COUNTY I-24
The resurfacing on I-24 from Haywood Lane to the Rutherford County line.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane and ramp closures in both directions for striping and rumble strip operations.
• 11/14, 8 p.m. – 11/15, 12 p.m., There will be lane and shoulder closures from the Mill Creek bridge to Bell Road bridge in both directions for epoxy overlay operations.
• 11/15, 8 p.m. – 11/16, 12 p.m., There will be a lane and shoulder closure on I-24 EB from the Mill Creek Bridge to the Bell Road Bridge for epoxy overlay operations.
• 11/16 - 11/19, 8 p.m. - 5 a.m., There will be lane and shoulder closures on I-24 in both directions from the Mill Creek Bridge to the Bell Road Bridge for epoxy overlay operations.
Barrier wall repair.
• Nightly, 8 p.m. – 5 a.m., There will be a single lane closure in both directions for barrier wall repair.
RUTHERFORD COUNTY I-24.
Ramp improvements at U.S. 231 (SR 10, South Church Street) (Exit 81) in Murfreesboro, including grading, drainage, signals, lighting, and paving.
• Nightly, 8 p.m. – 5 a.m., There will be WB alternating lane closures for milling, paving, and striping. Alternating lane closure on Exit 81 for the removal of existing high mast light standards.
• 11/13, 8 p.m. – 5 a.m., WB Exit 81 will have a temporary ramp closure, EB left lane closure, a WB double right lane closure with one planned rolling roadblock for installation of overhead sign structure (MM 81).
The interchange improvement on I-24 at Medical Center Parkway, including grading, drainage, paving, retaining wall, ITS, signals, and lighting.
• Nightly, 8 p.m. – 5 a.m., There will be temporary lane closures in both directions on the off-ramps from I-24 to Medical Center Parkway and on Medical Center Parkway/Fortress Boulevard for construction activities (MM 76).
Pavement Repair.
• Nightly, 8 p.m. – 5 a.m., There will be a closure of lane 2 and shoulder at MM 86.4 on I-24 WB. There will be a secondary closure of lane 2 and shoulder on I-24 EB at MM 82.4 and the EB on-ramp (MM 81.24).
• Nightly, 8 p.m. – 5 a.m., There will be a closure of lane 4 and the shoulder on I-24 EB (MM 65.3-65.5). There will be a secondary closure on I-24 EB of lane 4, shoulder, and the 66 on-ramp (MM 67-68).
• Nightly, 8 p.m. – 5 a.m., There will be a closure of lane 3, lane 4, shoulder, and on-ramp on I-24 EB (MM 63-64).
• Nightly, 8 p.m. – 5 a.m., There will be a closure of the shoulder, lane 1, and lane 2 on I-24 WB (MM 70.2). There will then be a secondary closure of lane 3, lane 4, and the Exit 70 on-ramp on I-24 WB.
DAVIDSON COUNTY I-40
The repair of the bridge on I-40 over the Harpeth River including grading, drainage, and paving.
• Nightly, 8 p.m. – 5 a.m., There will be temporary, alternating lane closures in both directions for bridge repair work (MM 194 – 196).
The resurfacing on I-40 from 46th Avenue to near Jefferson Street including bridge expansion, joint repair, and thin epoxy overlay.
• Nightly, 8 p.m. – 5 a.m. (excluding Saturday), There will be alternating lane closures on I-40 in both directions for bridge work, shoulder stone, and pavement markings. There will be temporary ramp closures to and from I-440 and SR 155 as needed.
The grading, drainage, construction of bridges, retaining walls and paving on SR 255 over I-40 at the Donelson Pike interchange.
• 11/13, 8 p.m. – 4 a.m., There will be a double right lane closure EB and a single right lane closure WB for sign removal. Temporary ramp closures for a short period (MM 214-218).
Bridge inspection.
• 11/17 – 11/19, 9 a.m. – 3 p.m., There will be a WB lane closure on Exit 204A to Briley Parkway NB for routine bridge inspection. One lane will remain open (MM 204).
• 11/15, 6 a.m. – 12 p.m., All westbound lanes of traffic be closed; traffic will be diverted to the I-440 EB Exit 206 for one hour for bridge inspection (MM 206).
The cleaning of median inlets.
• Nightly, 8 p.m. – 5 a.m., There will be an inside single lane closure in both directions for median inlet cleaning. Traffic control will be provided (MM 204-213).
DICKSON COUNTY I-40
Tier 2 patching.
• Nightly, 8 p.m. – 5 a.m., There will be a closure of lane 3 and the shoulder on I-40 EB, and the I-840 on-ramp to I-40 EB. There is a second location that will require a closure of lane 2, lane 3, shoulder, and the I-840 EB off-ramp (MM 175-177).
Aerial crossing.
• 11/16, 6 a.m. – 9 a.m., There will be a rolling roadblock in both directions for aerial crossing (MM 164-165.6).
HUMPHREYS COUNTY I-40
Bridge repair.
• 11/13, 7 p.m. – 5 a.m., There will be a temporary lane closure on I-40 EB for pavement marking operations.
SMITH COUNTY I-40
Sinkhole injection.
• Nightly, 8 p.m. – 5a.m., There will be a closure of lane 2 and the shoulder (MM 262-263).
WILSON COUNTY I-40
The resurfacing on I-40 from the Davidson County line to west of Golden Bear Parkway.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures in both directions for milling, paving, and overhead sign repairs. Exit 226 EB and WB will be closed as needed (222 – 228).
• 11/13, 8 a.m. – 4 p.m., There will be a closure of the back parking lot at the MM 227.8 WB truck stop for milling and paving operations.
Overhead sign installation
• Nightly, 8 p.m. – 5 a.m., There will be a double inside lane and shoulder closure for the installation of an overhead sign.
DAVIDSON COUNTY I-65
The resurfacing on I-65 from I-40 to near the Cumberland River bridge including thin epoxy overlay.
• Nightly, 8 p.m. – 5 a.m. (excluding weekends), There will be alternating lane closures in both directions for wall texture coating and pavement markings.
Streetlight conversion.
Nightly, 8 p.m. – 5 a.m., There will be a right lane and shoulder closure in both directions.
Barrier wall repair.
• Nightly, 8 p.m. – 5 a.m., There will be inside lane and shoulder closure for barrier wall repair (MM 90.2)
DAVIDSON AND SUMNER COUNTIES I-65
I-65 widening and improvements from near Rivergate Parkway to near US 31W (SR 41).
• Daily, 9 a.m. – 3 p.m., There will be alternating lane closures on SR 174 (Long Hollow Pike) and US-31W for bridge work (MM 95 – 99). One lane will remain open in both directions.
• Nightly, 8 p.m. – 5 a.m., There will be lane closures on I-65 in both directions for construction activities (MM 95 – 99). One lane in each direction will remain open. There will also be intermittent ramp closures at SR 174 (Long Hollow Pike) and US-31W (SR 41) as needed.
• Nightly, 8 p.m. – 5 a.m., Cedar Street will be closed for bridge construction activities. Detour will be in place.
• 11/16 – 11/19, 8 p.m. – 5 a.m., There will be alternating lane closures and full road closures on I-65 and US 31W in both directions to set steel beams for bridge. Detours will be utilized (MM 95-99).
ROBERTSON COUNTY I-65
Interchange lighting on I-65 at SR-109 (Exit 121) in Portland.
• 11/13 - 11/14, 8 p.m. – 5 a.m., There will be an inside lane and shoulder closure in both directions for bridge mounted light installation. Two lanes will remain open in both directions. Additional lane closures for NB and SB off-ramps, one lane will remain open for these ramps (MM 120-121).
DAVIDSON COUNTY I-440
Bridge Inspection.
• 11/15, 6 a.m. – 12 p.m., Lane 2 will be closed on the I-440 EB ramp for bridge inspection work (MM 0-0.1).
• 11/15, 6 a.m. – 12 p.m., All lanes will be closed temporarily on I-440 WB ramp toward I-40 WB. Traffic will be diverted to I-40 EB for one hour (MM 0.2).
BEDFORD COUNTY SR 10
Intersection improvements on SR 10 (US 231) at SR 82 (Sawney Webb Memorial Hwy).
• Daily, continuous, There will be a closure of the inside lane, inside turn lane, and inside acceleration lanes for grading operations. Two NB through lanes and 1 SB through lane of traffic will be maintained for duration of construction phase.
DAVIDSON COUNTY SR 1
Safety improvements at Hamilton Church Road.
• Daily, 9 a.m. – 3 p.m., There will be lane closures on Hamilton Church Road in both directions for construction activities. One lane will remain open at all times.
Streetlight conversion.
• Daily, 9 a.m. – 3 p.m., There will be a right lane and shoulder closure for streetlight conversion (LM 20 – 30).
Sign installation.
• LOOK AHEAD: 11/21, 9 a.m. – 3 p.m., There will be a right lane closure for the installation of a sign on a building ( LM 17).
DAVIDSON COUNTY SR 6
The resurfacing on SR 6 (Rosa L. Parks/James Robertson Parkway) from Broadway to the bridge over Ellington Parkway.
• Nightly, 8 p.m. – 5 a.m. (excluding weekends), There will be alternating lane closures in both directions for paving and special marking operations.
DAVIDSON COUNTY SR 11
The widening of US 31A (SR 11, Nolensville Pike) from North of the Mill Creek bridge to SR 254 (Old Hickory Boulevard) including bridges, retaining walls, signals, and lighting.
• Daily, 9 a.m. – 3 p.m., There will be temporary road closures on SR 11 and associated side roads for utility relocation, grading, and drainage (LM 1.7 – 4.2).
• Continuous, There will be a continuous closure of Brooklawn Drive until the end of November for utility relocation, grading, and drainage work. A detour will be in place.
Utility relocation.
• Daily, 9 a.m. – 3 p.m., There will be lane closures in both directions for relocation of existing facilities prior to a TDOT project (LM 23.36 – 24.47). The center turn lane, and one lane of traffic will be closed.
• Nightly, 8 p.m. – 5 a.m., There will be lane closures in both directions for relocation of existing facilities prior to a TDOT project (LM 23.36 – 24.47). The center turn lane, and two lanes of traffic will be closed.
Pole Replacement.
• Daily, 9 a.m. – 3 p.m., There will be lane closures near Nolensville Rd. at Ocala Dr.
• Daily, 9 a.m. – 3 p.m., There will be lane closure to along SR 11 (Nolensville Pike) to replace poles.
• Daily, 9 a.m. – 3 p.m., There will be lane closure to along SR 11 (Dickerson Pike) to replace poles.
DAVIDSON COUNTY SR 12
Fiber installation.
• Daily, 9 a.m. – 3 p.m., There will be lane closures along SR 12 Rosa L Parks for installation of fiber between Harrison Street and 10th Circle N.
Line replacement.
• Daily, 9 a.m. – 3 p.m., There will be lane closures along SR 12 Rosa L Parks while opening the primary line at the intersection with Garfield Street.
DAVIDSON COUNTY SR 41
Pedestrian Hybrid Beacon Installation.
• Daily, 9 a.m. – 3 p.m., The far-right lanes in both directions will be closed by NDOT for the installation of new PHB.
DAVIDSON COUNTY SR 45
The improvement of the intersection on SR 45 (Old Hickory Boulevard) and Myatt Drive.
• Daily, 9 a.m. – 3 p.m. (excluding weekends), There will be intermittent single lane closures in both directions along SR 45 for signal installation work.
Streetlight conversion.
• Daily, 9 a.m. – 3 p.m., There will be a right lane and shoulder closure for streetlight conversion (LM 4.7-5.7).
DAVIDSON COUNTY SR 65
Water/Fire hydrant installation.
• Daily, 9 a.m. – 3 p.m., There will be NB/SB lane closures along SR 65 to install new water main and service from the intersection of Whites Creek Pike and W Trinity Lane to the intersection of Whites Creek Pike and Knight Drive.
DAVIDSON COUNTY SR 106
Film shoot.
• 11/17, 8 p.m. – 3 a.m., There will be an EB south curb outer lane closure of SR 6 between Overhill Drive and Warfield Drive for truck and bus loading for filming.
DAVIDSON COUNTY SR 155
The resurfacing on SR 155 from south of the NERR underpass to north of McGavock Pike.
• Nightly, 8 p.m. – 5 a.m. (excluding Saturday), There will be alternating lane closures on Briley Pkwy in both directions for paving, marking and shoulder stone. Temporary ramp closures as needed.
• Daily, 9 a.m. – 3 p.m. (excluding Saturday), There will be shoulder and partial ramp closures in both directions at Opry Mills, McGavock Pike, and Two Rivers for pavement marking. No traffic will ever be shut down.
ITS Maintenance.
• 11/13, 8 p.m. – 5 a.m., There will be a single right lane closure for HAR flashing beacon removal (LM 27.50).
Bridge inspection.
• 11/19 – 11/21, 9 a.m. – 3 p.m., There will be a SB lane closure at Exit 27 for routine bridge inspection. One lane will remain open.
• 11/19 – 11/21, 9 a.m. – 3 p.m., There will be a lane closure on the SR 155 NB ramp to I-40 EB for bridge inspection. One lane will remain open.
DAVIDSON COUNTY SR 254
The resurfacing on SR 254 (Old Hickory Boulevard) from Cloverland Drive to Blue Hole Road.
• Nightly, 8 p.m. – 5 a.m. (excluding weekends), There will be lane closures on Old Hickory Boulevard in both directions for pavement marking operations and concrete work.
DAVIDSON COUNTY SR 255
New turn lane: grading, paving, and striping.
• Daily, 9 a.m. – 3 p.m., There will be a right lane and shoulder closure for the construction of a new turn lane.
DAVIDSON & SUMNER COUNTY SR 386
Electric line installation.
• Daily, 9 a.m. – 3 p.m., There will be lane closures on Vietnam Veterans Boulevard at Liberty Ln. to install overhead lines.
DICKSON COUNTY SR 46
The construction of a box beam bridge on SR 46 over Yellow Creek.
• Continuous, The bridge will be reduced to one lane to demo the existing structure and reconstruct the new bridge. Traffic will be controlled by temporary signals (LM 19.06).
MAURY COUNTY SR 50
The resurfacing on SR 50 from SR 99 to near Nicholas Long Drive.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures on SR 50 in both directions for pavement markings.
RUTHERFORD COUNTY SR 1
The grading, drainage, signals, and paving on US 41 from near Jefferson Pike to near SR 266 (Sam Ridley Parkway).
• Nightly, 8 p.m. – 5 a.m., There will be lane closures in both directions for construction activities.
The resurfacing of US 41 (SR 1) from north of Florence Road to SR 268.
• Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures in both directions on US 41 (US 70, SR 1) north of Florence Road to SR 268 for final striping and guardrail. At least one lane will remain open in each direction.
RUTHERFORD COUNTY SR 99
The grading, drainage, and construction of retaining walls, signals, and paving on SR 99 from Veterans Parkway to Cason Lane.
• Daily, 9 a.m. – 3 p.m., There will be temporary lane closures in both directions for construction activities.
RUTHERFORD SR 266
The grading, drainage, signals, and paving on SR 266 (Sam Ridley Parkway) at the intersection of Motlow College Blvd.
• Continuous, There will be lane closures in both directions for construction activities, new turn lanes, and roadway widening.
The installation of turn lanes and short-range detection equipment at the intersection of Sam Ridley Parkway and Old Nashville Highway.
• Daily, 9 a.m. – 3 p.m., There will be temporary lane closures in both directions for construction activities.
SMITH COUNTY SR 80
Cross drain replacement.
• 11/13, 8 a.m. – 2:30 p.m., There will be a 2-lane closure in both directions near Hacket Hollow Road for cross drain replacement (LM 2.8 – 3.2).
SMITH COUNTY SR 141
Roadway repair.
• Continuous, There is a full road closure of SR 141 in both directions (LM 14.68 – 14.77) until on or before 12/31/2025 due to emergency bank stabilization. A detour is in place (westbound to SR 53, eastbound to SR 96).
SUMNER COUNTY SR 6
The grading, drainage, construction of a concrete box bridge, paving, and signals on Walton Ferry Road/Old Shackle Island Road from Nokes Drive to Volunteer Drive in Hendersonville.
• Nightly, 8 p.m. – 5 a.m., There will be temporary lane closures on SR 6 in both directions for underground utility work (LM 2.95 – 3.10).
• Daily, 8 a.m. – 6 p.m., There will be a road closure on Cages Road for utility crossings at the Walton Ferry Road intersection. A detour plan will be in place to divert traffic onto Sanders Ferry Road and Imperial Blvd.
The grading, drainage, signals, and paving for Project Woolhawk including SR 6 and SR 25.
Milling and paving.
• Daily, 9 a.m. – 3 p.m., There will be intermittent EB lane closures and flagging operations for milling, paving, striping, and signal operations.
• Daily, 9 a.m. 3 p.m., There will be alternating lane closures in both directions for milling and paving at Maple Row Blvd and Mayfair Blvd.
SUMNER COUNTY SR 386
The resurfacing on SR 386 from near Forest Retreat Road to near Saundersville Road.
• Nightly, 8 p.m. – 5 a.m., There will be lane closures on Vietnam Veterans Boulevard (SR 386) including Exits 6, 7, and 8 in both directions for final punch list items.
WILLIAMSON COUNTY SR 31
Turn lane installation.
• Daily, 8 a.m. – 5 p.m., One SB lane will be closed for the milling, grading, and paving for the installation of a turn lane. One lane will always remain open.
WILLIAMSON COUNTY SR 96
Aerial cable replacement.
• Daily, 9 a.m. – 3 p.m., There will be lane closure for replacement of overhead cable at 575 Murfreesboro Road to Murfreesboro Road at Jordan Road and Highway 96 at the intersection of Eddy Lane in Franklin (LM 3.21 – 12).
WILLIAMSON COUNTY SR 100
The construction of pedestrian facilities on SR 100 from Fairview Community Center to Bowie Lake Road.
• Daily, 9 a.m. – 3 p.m., There will be intermittent lane closures in both directions for utility relocation and grading work.
WILLIAMSON COUNTY SR 106
ITS Infrastructure Expansion.
• Daily, 9 a.m. – 3 p.m. (excluding weekends), There will be a right-turn lane closure on Lewisburg Pk. with Donelson Creek for installation work.
WILLIAMSON COUNTY SR 431
Asphalt widening.
• Daily, 9 a.m. – 3 p.m., There will be alternating lane closures in both directions for the widening of SR-431 (LM 4.9 – 5.3).
WILSON COUNTY SR 24
The grading, drainage, signals, and paving on SR 24 (US-70) from Terrace Hill Road to Adeles Garden Road.
• Daily, 8 a.m. – 2 p.m., There will be temporary lane closures and flagging operations on SR 24 for utility relocations and grading operations (LM 5.9 – 6.49).
• Continuous, There will be a westbound shoulder closure and lane shift with barrier wall along SR 24 at Terrace Hill Road for grading operations (LM 5.9 – 6.49).
WILSON COUNTY SR 141
The grading, drainage, and construction of concrete box bridges and paving on SR 141 (Hartsville Pike) from north of Lovers Lane to SR 26 (US-70).
• Daily, 9 a.m. – 3 p.m., There will be temporary lane closures on SR 141 in both directions for utility relocation, grading, and paving operations (LM 8.7 – 10.5).
WILSON COUNTY SR 171
Intelligent Transportation System and signal improvements from Division Street to Central Pike.
• Daily, 9 a.m. – 3 p.m., There will be temporary lane closures and flagging operations in both directions for underground survey work and conduit installation (LM 3.56 – 7.22).
Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity. Information in this report is provided to the Department of Transportation by the contractors. Most work is weather dependent and subject to change due to inclement weather. From your desktop or mobile device, get the latest construction activity and live streaming SmartWay traffic cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any landline or cellular phone for travel information or follow us on Twitter at www.twitter.com/TN511 for statewide travel. As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for your destination. Drivers should never tweet, text or talk on a cell phone while behind the wheel.