Roadway Activity Report – Region 2 (Parts of East and Middle Tennessee) for September 12 - 18, 2024

Thursday, September 12, 2024 | 12:20pm

           
 DISTRICT 27

CUMBERLAND COUNTY I-40 Utility Work both directions from MM 304.4 to MM 327: THP assisted rolling roadblock begging eastbound at MM 304 near SR-24 crossover and westbound at MM 327 (I-40 Rest Area). Motorists should reduce speed and be prepared to stop. Message boards, signage and law enforcement vehicles will be present, 09/15/24 from 6 am to 11 am, with a rain date of 09/22/24. [2024-180 and 2024-317]

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Paving operations are ongoing throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. The contractor has closed North Grace Hill Drive at the existing intersection of SR-28 (US-127) for construction activities. Motorists should utilize South Grace Hill Drive as the detour with appropriate signs. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution while traveling through the work zone. [Jones Bros. Contractors, LLC/Crossville/CNV009]

CUMBERLAND COUNTY SR-1 (US-HWY. 70 W.) Utility Work both directions from LM 0.04 to LM 2.71: Lane closures both eastbound and westbound on SR-1(US-70W) between Glade Creek Rd and Old Ridge Rd. Motorists should reduce speed and be prepared to stop. Trucks with strobe lights, signage, and barrels/cones will be present, 8 am to 3:30 pm, 08/29/24 through 09/30/24. [2024-533]

CUMBERLAND COUNTY SR-1 (US-HWY. 70 W.) Utility Work both directions from LM 24 to LM 26: Flagging operations on SR-1 (Rockwood-Crossville Hwy) from East of Cox Valley / I-40 overpass to East of Mackie Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 09/05/24 through 09/30/24 from 8 am - 3 pm. [2024-421]

CUMBERLAND COUNTY SR-101 (PEAVINE RD.) Utility Work both directions from LM 16 to LM 23: Flagging operations on SR-101 (Peavine Road) from North of I-40 to Dartmoor-Snead Drive. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 09/05/24 through 09/30/24 from 8 am - 3 pm. [2024-318]

CUMBERLAND COUNTY SR-24 (US-70 N.) Utility Work both directions from LM 11.36 to LM 13.09: Lane closures both eastbound and westbound on SR-24 (US-70N) between Farris Rd and East of Bell Rd. Motorists should reduce speed and be prepared to stop. Trucks with strobe lights, signage, and barrels/cones will be present, 8 am to 3:30 pm, 08/29/24 through 09/30/24. [2024-535]

CUMBERLAND COUNTY SR-24 (US-70 N.) Utility Work both directions from LM 3.75 to LM 5.80: Lane closures both eastbound and westbound on SR-24 (US-70N) between Randolph and Falls Rd. Motorists should reduce speed and be prepared to stop. Trucks with strobe lights, signage, and barrels/cones will be present, 8 am to 3:30 pm, 08/29/24 through 09/30/24. [2024-532]

CUMBERLAND COUNTY SR-24 (US-70 N.) Utility Work both directions from LM 6.09 to LM 8: Lane closures both east and westbound on SR-24 (US-70N) between Randolph and Miller Ct. Motorists should reduce speed and be prepared to stop. Trucks with strobe lights, flaggers, signage, and barrels/cones will be present, 8 am to 3:30 pm, 08/29/24 through 09/30/24. [2024-531]

CUMBERLAND COUNTY SR-68 Utility Work both directions from LM 4.81 to LM 12.44: Intermittent stoppages as well as shoulder and lane closures on SR-68 from Cox Valley Road to Old Grandview Hwy. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 08/29/24 through 09/30/24 from 9 am - 2 pm. [2024-152]

CUMBERLAND COUNTY SR-68 Utility Work both directions from LM 9.5 to LM 11.7: Flagging operations on SR-68 from West of Alps Road to Coal Creek Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 09/12/24 through 10/11/24 from 8 am - 4 pm. [2024-551]

CUMBERLAND COUNTY SR-1 (US-70) construction of bridge over the Obed River (LM 12.7): Bridge replacement activities continue SR-1 (US-70) over the Obed River bridge. SR-1 (US-70) is to be closed at the bridge for the duration of the project until the work is completed. A detour with signs has been displayed to utilize Northside Drive (SR-462) to travel around the closure. Additionally, the left turn from Sparta Drive onto Miller Avenue (SR-392) has been closed for the duration of the project. Motorists should be aware of the road closure and utilize the detour route as necessary. RESTRICTIONS: Bridge on SR-1 (US-70) over the Obed River is being replaced. The road is closed at LM 12.72. [Whaley Construction, LLC/Crossville/CNX110]

CUMBERLAND COUNTY SR-1 resurfacing from LM 16.29 to LM 28: The contractor will be on site intermittently to perform punch list work. During this work, lane closures may be utilized, and flaggers will be present to control the flow of traffic through the work zone. Motorists should use caution as they approach the work zone. [Asphalt Paving Systems, Inc./Cookeville/CNY902]

CUMBERLAND COUNTY SR-101 resurfacing from south of SR-282 (Dunbar Lane, LM 12.4) to SR-1 (US-70, LM 15.9): Contractor working on final resurfacing activities. Shoulder and/or lane closures will be necessary to complete the work. Appropriate signs will be utilized to direct traffic. Motorists should use caution while driving through the work zone. [Rogers Group, Inc./Crossville/CNY010]

CUMBERLAND COUNTY SR-28 (Main Street, US-127) downtown pedestrian improvement project between Lantana Road (Highway 70 East) and Neecham Street: Construction activities are ongoing along SR-28 (Main Street). The contractor is working on removing and replacing the concrete sidewalk and curb ramps North from Lantana Road to near West 2nd Street. The shoulder parking along this area has been closed. Lane closures may be required at times for construction activities. Signs and flaggers may be utilized during these lane closures and/or lane shifts. Motorists should use caution when traveling through the work zone.
[Adams Contracting, LLC/Crossville/LP24_1]

CUMBERLAND COUNTY SR-28 (US-127) grading, drainage, signals and paving from SR-68 to south of the bridge over Byrd's Creek (LM 9.7 to LM 10.6): Construction activities are in progress along SR-28 and SR-68. Construction equipment and vehicles will be entering and exiting the work zone frequently. The signals at the intersection of SR-28 and SR-68 are operational. Motorists should be mindful of the change as they travel along SR-28 and SR-68. Flaggers may be utilized at times. Motorists should use caution when traveling through the area and be aware of the traffic pattern shifts. [Cleary Construction, Inc./Crossville/CNW231]

CUMBERLAND COUNTY SR-298 resurfacing from near Jackie Drive (LM 2.7) to east of Lake Francis Road (LM 6.8): Contractor working on final resurfacing activities. Temporary lane closures may be necessary for work activities. Motorists should be cautious of flagging operations. Flaggers and advanced warning signs will be displayed to alert motorists of the traffic conditions.
[Rogers Group, Inc./Crossville/CNY103]

CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Construction and paving activities are in progress. The contractor will be closing the right lane of Northbound SR-28 near Interstate Drive (SR-462) from 7 AM to 4 PM to work on the shoulder. The right lane will be reopened at the end of each work shift. Activities will require temporary lane closures and/or traffic stoppages on Interstate Drive (SR-462), as well as short term closures of city streets. Flagging operations will accompany these closures with appropriate signs. The right shoulder of SR-28 Northbound near the intersection of Interstate Drive has been closed. Motorists traveling west on Interstate Drive should be mindful of the "Right Turn Only" lane at the intersection of Stout Drive. Motorists should use caution when traveling through the work zone.
[Rogers Group, Inc./Crossville/CNV010]

CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor will continue work along the new alignment of SR 28. In addition, the contractor will be performing utility work adjacent to the existing alignment of SR 28. Flaggers are being intermittently used to control traffic through parts of the work zone. Motorists are encouraged to use caution and watch for construction equipment and personnel adjacent to the roadway. [Jones Bros. Contractors, LLC/Cookeville/CNV300]

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading and construction activities throughout the project. Temporary lane closures and periodic traffic stoppages will be necessary for construction activities and motorists should be prepared to stop while traveling through the work zone. Motorists are encouraged to obey posted speed limit and to watch for construction equipment and personnel adjacent to the roadway. The West end of Old Liberty Road will be closed to through traffic due to construction activities. Motorists and EMS will need to use the East entrance of Old Liberty Road to gain access and follow detour signs.
[Twin K Construction/Cookeville/CNV012]

FENTRESS COUNTY SR-52 (E. CENTRAL AVE.) TDOT Maintenance both directions at LM 13.2: TDOT maintenance crews will be repairing drainage structure on SR-52 at the 13.2 mm between Stewart St. and E Mark Twain Ave. This will cause shoulder closure in this area. Work will take place during the hours of 7am and 3pm Monday through Fridays. Motorists are advised to use caution in this area.

JACKSON COUNTY SR-135 rockfall mitigation north of Daniel Hill Lane (LM 7.1): The contractor has begun clearing and rockfall mitigation work. SR-135 is closed from LM 6.31 – 7.76. Message boards and detour routes are in place. Motorists are encouraged to use caution and follow detour signage. RESTRICTIONS: Closed with detour in place. [Tim's Tree Service, Inc./Livingston/CNX406]

JACKSON COUNTY SR-53 resurfacing from near SR-262 (LM 13.5) to SR-56 (LM 15.7) and on SR-56 from north of Old Creek Road (LM 10.1) to the Cumberland River Bridge (LM 11.1): The contractor has completed paving on SR-53 (LM 13 to LM 16) and SR-56 (LM 10 to LM 12) and associated bridge repair work. Flaggers will be used intermittently to control traffic through the work-zone as the contractor completes incidental work. Motorists are encouraged to use caution and watch for construction equipment and personnel on the roadway.
[Rogers Group, Inc./Livingston/CNY120]

JACKSON COUNTY SR-85 bridge repair over Indian Creek (LM 4.77): The contractor continues bridge repair work. The road is reduced to one 11’ lane from LM 4.5 – 5.0 using temporary traffic signals to control traffic through the work zone. A wide load detour is in place for vehicles that require larger clearance. Motorists are encouraged to use caution and watch for construction equipment and personnel throughout the work zone. RESTRICTIONS: The road is reduced to one 11’ lane from LM 4.5 – 5.0 using temporary traffic signals to control traffic through the work zone. [Thomson and Thomson, Inc./Livingston/CNX111]

PICKETT COUNTY SR-111 resurfacing from Pendergrass Road (LM 5.4) to near Beason Road (LM 8.5): The contractor plans to start paving operations on SR-111 the week of 9/16/24. Flaggers will be used to control traffic through the work-zone. Motorists are encouraged to use caution and watch for construction equipment and personnel on the roadway.
[Rogers Group, Inc./Livingston/CNY149]

PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Pigeon Roost Creek Road and Messenger Road are closed at the intersection of SR-136 with detour signs to utilize Bunker Hill Road. In addition, the turning lane serving Prescott South Middle School has been taken out of service and northbound Jefferson Avenue will be restricted to one lane. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel. [Rogers Group, Inc./Cookeville/CNV284]

PUTNAM COUNTY I-40 from east of SR-56 (MM 274) to east of SR-56 (MM 281): The contractor has completed paving operations, but they will continue to be on site performing final work, including installation of permanent roadway markings from Sunday through Thursday nights. During this work, one lane may be closed in each direction or mobile traffic control operations may be used. Motorists are encouraged to use caution and to be prepared to stop as they approach the work zone. [Vulcan Construction Materials, LLC/Cookeville/CNX410]

PUTNAM COUNTY SR-135 construction of a concrete slab bridge on SR-135 at LM 13.6: SR-135 is closed from LM 13.53 – 13.59 for bridge construction. Message boards and detour routes are in place. Motorists are encouraged to use caution and follow detour signage. RESTRICTIONS: Closed with detour in place. [J. Hill Excavating, LLC/Livingston/CNY903]

PUTNAM COUNTY SR-24 (US-70N) bridge repair over Falling Water River (LM 24.4): The contractor will continue performing bridge repair work on SR 24 at LM 24.42. Motorists should be prepared to stop at the temporary traffic signal and should be aware of construction equipment and personnel adjacent to the roadway. One lane of SR 24 will remain open through the duration of this project; however, motorists should use caution as they travel through the work zone.
[Mid-State Construction Company, Inc./Cookeville/CNY066]

PUTNAM COUNTY SR-24 resurfacing from West of SR-56 (MM 11) to near Miller Road (15.7): The contractor will be on site intermittently to work on punch list items. During this work, one lane may be closed, and flaggers will be present to control the flow of traffic through the work zone. Motorists are encouraged to use caution as they approach the work zone.
[Rogers Group, Inc./Cookeville/CNY100]

WHITE COUNTY SR-111 resurfacing from Van Buren County Line (LM 0) to near Shady Oak Rd (LM 4.2): The contractor will be on site intermittently to perform punch list work. During this work, lane closures may be used to control the flow of traffic through the work zone. Motorists are encouraged to use caution through the work zone. [Asphalt Paving Systems, Inc./Cookeville/CNY902]

DISTRICT 28

BLEDSOE COUNTY SR-28 (US-HWY. 127) TDOT Maintenance northbound from LM 15.2 to LM 15.4: Road is shut down to one lane, Traffic is using the second lane to travel.

BLEDSOE COUNTY SR-285 resurfacing from the Van Buren County Line (0.0) to SR-101 (3.2): The contractor will be working on SR-285 from the Van Buren County Line (LM 0.00) to SR-101 (LM 3.15) to resurface and install safety devices. This work will require single lane closures controlled by flaggers. Please use caution when driving through the work zone.
[Rogers Group, Inc./Dunlap/CNY122]

BLEDSOE COUNTY SR-30 and SR-443, the grading, drainage, stream relocation, widening, and resurfacing on Summer City Road: The contractor will be performing grade work and widening on Summer City Road in Bledsoe County. This work will narrow the lanes at LM 2.0 and LM 4.3 and will leave both lanes open to traffic. Please slow down and use caution when driving through the work zone. [Rogers Group, Inc./Dunlap/CNY153]

BLEDSOE COUNTY SR-301 resurfacing from SR-285 (0) to south of CC Road (0.9): The contractor will be resurfacing SR-301 from SR-285 (LM 0.00) to South of the CC Road (LM 0.90). This work will require single lane closures controlled by flaggers. Please use caution when driving through the work zone. [Rogers Group, Inc./Dunlap/CNY122]

COFFEE COUNTY SR-55 (MCMINNVILLE HWY.) Utility Work both directions at LM 16.02: Flagging operation on SR-55 (McMinnville Hwy) between Interstate Drive and Ridgewood Drive. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 09/11/24 through 09/13/24 from 8 am - 10 am. [2024-530]

COFFEE COUNTY I-24 (MM 105) construction of an overpass carrying SR-2 (US-41): Phase 1 of I-24 bridge replacement at Exit 105 will continue this week. SR-2 will be reduced to one lane utilizing traffic signal system. The temporary traffic signal will remain in effect until 10/16/25. There will be rolling roadblocks on I-24 in both directions to run new utility lines across the interstate and to remove old lines. Rolling roadblocks are scheduled for 9/12 between 9AM and 12PM.
[Bell and Associates Construction, LP/Tullahoma/CNX309]

COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 1 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. Contractor may use temporary lane shifts to complete utility work. Phase 1 traffic shift has reduced lanes from 3 to 2 across the bridge over Rock Creek in order to start bridge replacement work. [Dement Construction Company, LLC/Tullahoma/CNX912]

COFFEE COUNTY SR-55 repair of the bridge over the Little Duck River (LM 14.0): Lanes are reduced to one lane in each direction across the SR-55 bridge over the Little Duck River for bridge repair work. This lane reduction will be in place until work is complete on 7/31/25.
[Mid-State Construction Company, Inc./Tullahoma/CNX412]

FRANKLIN COUNTY Old Decherd Road over Wagner Creek (LM 0.3) construction of a bridge: Old Decherd Road is closed at Wagner Creek for bridge replacement. A signed detour is in place. The road closure will be in place for the duration of the project through June 30th, 2025. RESTRICTIONS: Old Decherd Road at Wagner Creek is closed. [Dement Construction Company, LLC/Tullahoma/CNY068]

FRANKLIN COUNTY SR-127 from north of Farm Lane (LM 5.2) to the Coffee County line (LM 9.9): There will be flagging operations for resurfacing activities from 7AM to 7PM daily.
[Tinsley Asphalt, LLC /Tullahoma/CNY124]

MARION COUNTY I-24 TDOT Contractor eastbound from MM 160.1 to MM 160.7: An in-depth inspection of the Holman J. Walker Bridge, the Interstate 24 bridge over the Tennessee River, will require lane closures daily from September 16th through September 20th. One lane will be closed on the bridge from 8 AM until 3 PM until the inspection is complete. The eastbound right-hand lane and shoulder will be closed on Monday, September 16th and Tuesday, September 17th from 8AM until 3PM. Inspection crews are expected to complete work in the eastbound lane on Wednesday, September 18th and begin working in the westbound right-hand lane in the afternoon. The westbound right-hand lane and shoulder are scheduled to be closed from 8AM until 3PM on Thursday the 19th and Friday, September 20th. Motorists are advised to merge left as soon as possible when approaching the work zone.

MARION COUNTY I-24 from east of Big Fiery Gizzard Creek (MM 146) to near SR-27 (US-72, MM 152): The contractor will be working on I-24 EB and WB from MM 146 to MM 152 to perform resurfacing operations. Work will be performed Sunday night through Friday night from 7 PM – 6 AM each night. This work will require single lane closures in each direction leaving one lane open to traffic each way. THP and truck mounted attenuators will be on site during the work.
[Rogers Group, Inc./Dunlap/CNX403]

MARION COUNTY SR-108 resurfacing from SR-28 (LM 0) to Grundy County Line (LM 11): The contractor will be resurfacing SR-108 from SR-28 (LM 0.00) to the Grundy County Line (LM 11.01). This work will require single lane closures controlled by flaggers. Please use caution when driving through the work zone. [Asphalt Paving Systems, Inc./Dunlap/CNY056]

VAN BUREN COUNTY SR-285 (MOONEYHAM-LONEWOOD RD.) Utility Work northbound from LM 9.1 to LM 16.18: Flagging operations on SR-285 (Mooneyham-Lonewood Road) between Haston Road and Salzer Mountain Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 07/08/24 through 10/31/24 from 9 am - 2 pm. [2024-309]

VANBUREN COUNTY SR-30 Miscellaneous Safety Improvements: The contractor will have intermittent lane and shoulder closures for sign installations, guardrail work, and pavement markings. Motorists should expect delays. Flagging operations will be in place.
[Superior Traffic Control, LLC/Inc./McMinnville/CNY093]

VANBUREN COUNTY SR-53 Miscellaneous Safety Improvements: The contractor will have intermittent lane and shoulder closures for sign installations, guardrail work, and pavement markings. Motorists should expect delays.
[Superior Traffic Control, LLC/Inc./McMinnville/CNY093]

WARREN COUNTY SR-1 (US-70S) resurfacing from east of SR-288 (LM 18.5) to west of SR-136 (LM 23.1): The contractor will have lane closures and shoulder closures from 6 AM to 8 PM daily for paving operations. [Tinsley Asphalt, LLC /McMinnville/CNY121]

WARREN COUNTY SR-108 resurfacing from the Grundy County line (LM 0.0) to south of SR-287 (LM 2.8): The contractor will have intermittent lane closures for wrap up operations from 6 AM until 7 PM. Motorists should expect delays. Flagging operations will be in place.
[Tinsley Asphalt, LLC /McMinnville/CNY101]

DISTRICT 29

BRADLEY COUNTY I-75 at Paul Huff Parkway Interchange modifications: During this reporting period, the contractor will be working on boring underground conduits for the new traffic signals. Intermittent flagging operations and temporary lane closures may be necessary. Motorists are advised to reduce speed & use caution in the work zone. [Summers-Taylor, Inc./Cleveland/CNX362]

BRADLEY COUNTY I-75 resurfacing from south of MM 18.6 (LM 3) to north of Exit 20 (LM 5.4): During this reporting period, the contractor will be working on permanent pavement markings. Nightly lane closures will occur as needed between the hours of 7:00 PM until 6:00 AM. Intermittent closures of Exit 20 will be required periodically for the duration of the project. Motorists are advised to reduce speed and use caution in the work zone. THP will be on site during work activities.
[Talley Construction Company, Inc./Cleveland/CNX405]

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will continue grading work and install new storm drainage. Intermittent flagging operations will take place throughout the project during various work activities. The speed limit in the work zone has been reduced to 35 mph. Motorists are advised to use caution in the work zone and watch for flaggers assisting with traffic control.
[Summers-Taylor, Inc./Cleveland/CNV130]

BRADLEY COUNTY SR-312 (HARRISON PK.) Utility Work both directions from LM 7.67 to LM 7.55: Flagger assisted westbound lane closure between Conner Rd and 700’ west of Westside Dr NW. Motorists should reduce speed and be prepared to stop. Flaggers, trucks, signage, and barrels/cones will be present, 09/05/24 to 10/24/24 between from 9 am - 2 pm. [2024-164]

BRADLEY COUNTY SR-312 (HARRISON PK.) Utility Work both directions from LM 7.67 to LM 7.55: Flagger assisted westbound lane closure between Conner Rd and 700’ west of Westside Dr NW. Motorists should reduce speed and be prepared to stop. Flaggers, trucks, signage, and barrels/cones will be present, 09/16/24 to 10/24/24 between from 9 am - 2 pm. [2024-164]

BRADLEY COUNTY SR-317 (WEATHERLY SWITCH RD.) Utility Work both directions from LM 7.67 to LM 7.55: Flagger assisted westbound lane closure between Conner Rd and 700’ west of Westside Dr NW. Motorists should reduce speed and be prepared to stop. Flaggers, trucks, signage, and barrels/cones will be present, 09/05/24 to 10/24/24 between from 9 am - 2 pm. [2024-164]

BRADLEY COUNTY SR-311 resurfacing from SR-60 (LM 5) to SR-74 (LM 6.1): During this reporting period, the contractor will begin resurfacing work in the area. Intermittent flagging operations may be necessary around the work area. Motorists are advised to reduce speed and use caution in the work zone. [Wright Brothers Construction Company, Inc./Cleveland/CNX132]

BRADLEY COUNTY SR-40 (US-64) resurfacing from SR-2 (US-11, US-64, LM 0.0) to near McKamy Street (LM 1.2): During this reporting period, the contractor is scheduled to begin resurfacing work on SR-40. The contractor is closing SR-40 Westbound right lane from Bates Street to Edwards Street for the construction of a concrete island. This temporary closure will remain in place until the resurfacing is completed on SR-40 and permanent marking is in place for the new alignment.
[Wright Brothers Construction Company, Inc./Cleveland/CNX132]

BRADLEY COUNTY SR-74 resurfacing from SR-311 (LM 12.7) to SR-40 (US-64, LM 13.9): During this reporting period, the contractor will begin resurfacing work in the area. Intermittent flagging operations may be necessary around the work area. Motorists are advised to reduce speed and use caution in the work zone. [Wright Brothers Construction Company, Inc./Cleveland/CNX132]

BRADLEY COUNTY SR-74 tom north of Inman Street (13.9) to north of SR-60 (15.5): During this reporting period, the contractor will continue resurfacing work on SR-74. Nightly closures will occur as needed between the hours of 8:00 PM until 6:00 AM. Motorists are advised to reduce speed and use caution in the work zone. [Talley Construction Company, Inc./Cleveland/CNY095]

BRADLEY, HAMILTON, MEIGS, RHEA, AND POLK COUNTY Curb ramp upgrades in District 29: During this reporting period, the contractor will be completing punch list work in Sale Creek and on SR74. Intermittent lane closures may be necessary during this work. Motorists are advised to reduce speed and use caution in the work zone. [Southern Constructors, Inc./Cleveland/CNX361]

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly Lane closures will occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. (Note: The contractor is scheduled to temporarily close the South Terrace entrance ramp to I-24 East on Sunday (9/15) night from 10 PM to 5 AM. Detours will be posted. This closure is necessary to shift traffic to the new ramp. Also, in late September the contractor will again be making major traffic shifts on I-24 East and West between Belvoir Avenue and Sprig Creek Road to continue the next phase of construction in these areas.) It may also be necessary to do short duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or to repair guardrail, attenuators, etc. The left lane on North and South Terrace between Belvoir Avenue and Spring Creek Road will be closed for installation of drainage structures, retaining and noise wall construction. During this reporting period, the contractor will have the right lane closed on North Terrace from Belvoir Avenue to Germantown Road to install a bore for the City of Chattanooga Sewer Line. Intermittent daytime non-rush hour lane closures may also be necessary throughout the period on South Terrace and North Terrace to work on utilities, street lighting, and various other construction items. All work is weather permitting. Moore Road and McBrien Road bridges over I 24 are closed as well as the entrance and exit ramps to I-24 between Belvoir Avenue and Moore Road. A continuous flow detour using Belvoir Avenue and Spring Creek Road is in place for local traffic. RESTRICTIONS: Moore Road and McBrien Road over I-24 closed. I-24 Ramps between Belvoir and Moore Road closed. [Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]

HAMILTON COUNTY SR-2 (E. 23RD ST.) Utility Work westbound from LM 9.69 to LM 9.94: NIGHTTIME (8 pm - 5:30 am) shoulder and lane closure on SR-2 (E. 23rd Street) between 4th Avenue and Dodds Avenue. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 01/23/24 through 09/18/24. [2023-192/197]

HAMILTON COUNTY SR-319 (DUPONT PKWY.) Utility Work northbound from LM 2.19 to LM 2.47: Utility construction on Dupont Parkway will require a northbound shoulder and single lane closure on the C. B. Robinson bridge over Tennessee River. Traffic will be shifted to a temporary traffic pattern while construction is ongoing. Motorists should use caution when traveling through the area and be aware of the traffic pattern shifts. Work will begin 09/11/24 thru 09/30/24 from 9 am to 4 pm. [2024-414]

HAMILTON COUNTY SR-320 (E. BRAINERD RD.) Utility Work westbound at LM 3.66: Single westbound lane closure on SR-320 (E. Brainerd Rd) beginning near Graysville Rd and Stanley Drive. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 9 am to 2 pm, 08/22/24 through 10/4/24. [2024-528]

HAMILTON COUNTY SR-8 (MARKET ST.) TDOT Contractor both directions at LM 9.68: The Tennessee Department of Transportation will conduct quarterly testing, inspection and maintenance on the Chief John Ross Bridge, also known as Market Street Bridge, over the Tennessee River in downtown Chattanooga on Sunday, September 15, 2024, from 8 AM until 12 PM. The bridge will be closed to all vehicle and pedestrian traffic during this time. This work is weather dependent. In the event of inclement weather, the operation will be rescheduled to take place at a later date.

HAMILTON COUNTY SR-8 (RINGGOLD RD.) Utility Work westbound from LM 1.27 to LM 1.3: Shoulder and lane closures on SR-8 (Ringgold Road) between Slater Road and N./S. Smith Street. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present 08/21/24 through 09/20/24 from 9 am - 2 pm. [2024-343]

HAMILTON COUNTY SR-8 (W. MAIN ST.) Utility Work both directions from LM 8.09 to LM 8.32: Nighttime road closure and detour on W. Main St between Market St and Broad St. Signage for detour route and barricades will be present. Detour will reroute traffic to 20th St beginning 09/04/24 to 10/02/24 from 10 pm to 4 am. [2024-527]

HAMILTON COUNTY I-124 (US-27) from I-24 Interchange to South of the Tennessee River Bridge: Daily lane closures are possible between 9 AM and 3:30 PM as the contractor work along the ramps and 4th Street. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control [Stansell Electric Company, Inc./Chattanooga East/CNY900]

HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel. This reporting period, the contractor plans to temporary close the I-75 northbound entrance ramp from Shallowford Road to install a traffic shift. Nightly lane closures will be implemented on I-75 northbound and southbound between MM 5 and MM 7 to perform traffic shift northbound and additional left shoulder closure southbound.
[Summers-Taylor, Inc./Chattanooga West/CNX358]

HAMILTON COUNTY Resurfacing on SR-29 (US-27) from south of Old Dayton Pike (LM 25.7) to north of Coulterville Road (LM 28.3): The contractor will be performing resurfacing operations. This work will require daily lane closures from 7 AM to 5 PM in either direction.
[Wright Brothers Construction Company, Inc./Chattanooga West/CNY098]

HAMILTON COUNTY SR-2 (US-11, US-64) McCallie Tunnel cleaning: The contractor will be cleaning this tunnel on Wednesday from 8 PM - 6 AM. There will be one lane closed in each direction for this work. [Diamond Specialized, Inc./Chattanooga West/CNY133]

HAMILTON COUNTY SR-29 (US-27) resurfacing from Morrison Springs Road (LM 6.1) to SR-153 (LM 11.6): Work is complete. Waiting on contractor to remove signs.
[Wright Brothers Construction Company, Inc./Chattanooga West/CNX238]

HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, for utility and grading work. The flagging operations will be performed on 09/12/24, 09/13/24, 09/16/24, 09/17/24, and 09/18/24 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment. On 09/14/24, the contractor will be closing one lane of McKee Business Entrance No. 1 to tie into the new alignment. [Wright Brothers Construction Company, Inc./Chattanooga East/CNT336]

HAMILTON COUNTY SR-319 (Hixon Pike) miscellaneous safety improvements from Boy Scout Road (LM 8.5) to Thrasher Pike (LM 9.5): The contractor will be retrofitting curb ramps throughout the project limits. Daily right lane closures between 8 AM and 5 PM will be utilized to accomplish this work. Motorists should use caution as workers will be present.
[J. M. Hanner Construction Co., Inc./Chattanooga West/CNY109]

HAMILTON COUNTY SR-58 resurfacing from SR-153 (LM 4.6) to near Eller Road (LM 6.5): Resurfacing operations are ongoing. Nightly lane closures are planned from 7 PM to 6 AM. Motorists should use caution in this area.
[Wright Brothers Construction Company, Inc./Chattanooga West/CNY057]

HAMILTON COUNTY SR-8 (US-127) construction near Palisades Road (LM 15.2) to near Sunset Drive (LM 15.4): The contractor completed the slope remediation work. Minor road repairs are required, and signs will remain until this work is completed.
[Wright Brothers Construction Company, Inc./Chattanooga West/CNW001]

HAMILTON COUNTY SR-8 (US-127) Stringers Ridge Tunnel cleaning: On Wednesday of this reporting period from 8 PM - 6 AM, the tunnel will be closed for cleaning. There will be signs directing traffic to go for the detour around the closure.
[Diamond Specialized, Inc./Chattanooga West/CNY133]

MCMINN COUNTY SR-2 (US-HWY. 11) Utility Work both directions from LM 16 to LM 19.5: Flagging operations on SR-2 (US-Hwy 11) from Clubhouse Drive and W. Farrell Street. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 09/09/24 through 09/27/24 from 9 am - 2 pm. [2024-374]

MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the Northbound and Southbound traffic will be reduced to one lane and controlled by traffic signals. County road 567 will be closed to traffic (LOCAL TRAFFIC ONLY) and detoured to SR039. This closure is necessary to perform the bridge replacement. The lane restriction will remain in place until the bridge replacement is completed.
[Whaley Construction, LLC/Chattanooga East/CNX069]

MEIGS COUNTY SR-60 construction of a small drainage structure (L.M. 1.6): A long-term single lane closure is in place as crews work to replace a drainage culvert. A temporary traffic signal has been implemented to flag traffic while the work is being performed. Traffic should use caution approaching the work area. [Wright Brothers Construction Company, Inc./Chattanooga West/CNX408]

MEIGS COUNTY W. Memorial Drive, Bridge over Decatur Branch, LM 0.37 in Decatur: During this reporting period, the bridge over Decatur Branch on W Memorial Dr. will be closed to all traffic. This closure is necessary to perform the Box Bridge Replacement. Detour routes are posted with signs. This closure will remain in place until the Box Bridge Replacement and associated work is completed. RESTRICTIONS: Box bridge on W Memorial Drive over Decatur Branch is closed for replacement. [Southern Constructors, Inc./Chattanooga East/CNY099]

POLK COUNTY SR-68 construction of bridge over Brush Creek (LM 16.4): During this update period, the contractor will continue grading operation on East side of SR-68. A temporary traffic signal system is active on SR-68 near LM 16.4. The northbound lane of SR-68 will be closed in the area controlled by the temporary traffic signal system. Motorists are advised to reduce speed and use caution in the work zone. [Wright Brothers Construction Company, Inc./Cleveland/CNX347]

RHEA COUNTY SR-29 (US-27) resurfacing from north of Payne Lane (LM 11) to near Bradley Street (L.M. 14.6): The contractor has finished the resurfacing work and has some minor cleanup. Intermittent temporary lane closures are possible to complete the work.
[Rogers Group, Inc./Chattanooga West/CNX219]


REGION WIDE

REGION 2 The crack sealing at various locations on various State Routes: There will be mobile closure operations for crack sealing work across the region. During this period, work is expected to take place in Polk, Bradley, Meigs, and Hamilton counties.
[Reynolds Sealing and Striping, Inc./Tullahoma/CNY123]

REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short term shoulder and/or lane closures to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will always remain open to traffic on the interstate, and flaggers will be present on state routes during any work that is performed. [Cumberland Guardrail, Inc./McMinnville/CNY105]

REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic. Flaggers will assist with traffic control as needed. [Lumin8 Transportation Technologies, LLC/Chattanooga East/CNX270]

REGION 2 The installation of longitudinal cable barrier on various Interstate Routes: The contractor will have nightly and daytime shoulder closures on interstates throughout Region 2 in order to perform cable rail removal and installation. For the foreseeable future, the majority of work will take place in Marion County from MM 162 to the Hamilton Co. line and from the Georgia Line to MM 173 in Hamilton Co. Both travel lanes will always remain open to traffic on the interstate during any daytime work that is performed. Work is scheduled for both day and night beginning 09/15/24 and continuing through 09/20/24. Nighttime single lane closures will be in place nightly beginning Sunday from 8 PM to 6 AM. Daytime shoulder closures will continue during weekdays between 6 AM and 8 PM. [R.D. Construction, LLC/McMinnville/CNW374]

REGION 2 The on-call concrete pavement repair at various locations on various Interstate and State Routes: Vulcan Materials Co. will be repairing concrete pavement in Bradley County in Cleveland at the cloverleaf ramps on SR-40 and SR-60. Various ramps will have repairs done and during the repairs half the ramp widths will be closed leaving a minimum of 10-foot lanes open to traffic. Please use caution when driving through the work zones.
[Vulcan Construction Materials, LLC/Dunlap/CNW379]

REGION 2 The random on-call cable barrier repair on various Interstate and State Routes: The contractor may have short term shoulder closures to perform cable rail repair. Both travel lanes will always remain open to traffic on the interstate during any daytime work that is performed. Nighttime closures will be needed occasionally and will be worked nightly Sunday though Thursday from 7 PM to 6 AM as needed. [Tennessee Guardrail, Inc./McMinnville/CNX312]

RESTRICTIONS

CUMBERLAND COUNTY - CNX110: Bridge on SR-1 (US-70) over the Obed River is being replaced. The road is closed at LM 12.72.

JACKSON COUNTY - CNX406: Closed with detour in place.

JACKSON COUNTY - CNX111: The road is reduced to one 11’ lane from LM 4.5 – 5.0 using temporary traffic signals to control traffic through the work zone.

PUTNAM COUNTY - CNY903: Closed with detour in place.

FRANKLIN COUNTY - CNY068: Old Decherd Road at Wagner Creek is closed.

HAMILTON COUNTY - DB2101: Moore Road and McBrien Road over I-24 closed. I-24 Ramps between Belvoir and Moore Road closed.

MEIGS COUNTY - CNY099: Box bridge on W Memorial Drive over Decatur Branch is closed for replacement.

###