Residential Building Permit Fees

NOTE: For construction costs above the maximum listed in the table below there is an additional fee of $50.00 for each additional $50,000 or fraction thereof.

Cost of Construction* Fee Additional Fee for
Plumbing and HVAC
Inspection**
Additional Fee if
Slab Other than
Monolith Pour***
$0 to $5,000 $100 $100 $100
$5,001 to $100,000 $350 $100 $100
$100,001 to $150,000 $400 $100 $100
$151,001 to $200,000 $450 $100 $100
$200,001 to $250,000 $500 $100 $100
$250,001 to $300,000 $550 $100 $100
$300,001 to $350,000 $600 $100 $100
$350,001 to $400,000 $650 $100 $100
$400,001 to $450,000 $700 $100 $100
$450,001 to $500,000 $750 $100 $100
$500,001 to $550,000 $800 $100 $100
$550,001 to $600,000 $850 $100 $100
$600,001 to $650,000 $900 $100 $100
$650,001 to $700,000 $950 $100 $100
$700,001 to $750,000 $1,000 $100 $100
$750,001 to $800,000 $1,050 $100 $100
$800,001 to $850,000 $1,100 $100 $100
$850,001 to $900,000 $1,150 $100 $100
$900,001 to $950,000 $1,200 $100 $100
$950,001 to $1,000,000 $1,250 $100 $100
$1,000,001 to $1,050,000 $1,300 $100 $100
$1,050,001 to $1,100,000 $1,350 $100 $100
$1,100,001 to $1,150,000 $1,400 $100 $100
$1,150,001 to $1,200,000 $1,450 $100 $100
$1,200,001 to $1,250,000 $1,500 $100 $100
$1,250,001 to $1,300,000 $1,550 $100 $100
$1,300,001 to $1,350,000 $1,600 $100 $100
$1,350,001 to $1,400,000 $1,650 $100 $100
$1,400,001 to $1,450,000 $1,700 $100 $100
$1,450,001 to $1,500,000 $1,750 $100 $100

* The cost of construction cannot be less than $60.57 per heated square foot of construction

** An HVAC and Plumbing Inspection is required for all new construction

*** Slab other than Monolith Pour Inspection is required when slab and footing are cast separately