NOTE: For construction costs above the maximum listed in the table below there is an additional fee of $50.00 for each additional $50,000 or fraction thereof.
Cost of Construction* | Fee | Additional Fee for Plumbing and HVAC Inspection** |
Additional Fee if Slab Other than Monolith Pour*** |
---|---|---|---|
$0 to $5,000 | $100 | $100 | $100 |
$5,001 to $100,000 | $350 | $100 | $100 |
$100,001 to $150,000 | $400 | $100 | $100 |
$151,001 to $200,000 | $450 | $100 | $100 |
$200,001 to $250,000 | $500 | $100 | $100 |
$250,001 to $300,000 | $550 | $100 | $100 |
$300,001 to $350,000 | $600 | $100 | $100 |
$350,001 to $400,000 | $650 | $100 | $100 |
$400,001 to $450,000 | $700 | $100 | $100 |
$450,001 to $500,000 | $750 | $100 | $100 |
$500,001 to $550,000 | $800 | $100 | $100 |
$550,001 to $600,000 | $850 | $100 | $100 |
$600,001 to $650,000 | $900 | $100 | $100 |
$650,001 to $700,000 | $950 | $100 | $100 |
$700,001 to $750,000 | $1,000 | $100 | $100 |
$750,001 to $800,000 | $1,050 | $100 | $100 |
$800,001 to $850,000 | $1,100 | $100 | $100 |
$850,001 to $900,000 | $1,150 | $100 | $100 |
$900,001 to $950,000 | $1,200 | $100 | $100 |
$950,001 to $1,000,000 | $1,250 | $100 | $100 |
$1,000,001 to $1,050,000 | $1,300 | $100 | $100 |
$1,050,001 to $1,100,000 | $1,350 | $100 | $100 |
$1,100,001 to $1,150,000 | $1,400 | $100 | $100 |
$1,150,001 to $1,200,000 | $1,450 | $100 | $100 |
$1,200,001 to $1,250,000 | $1,500 | $100 | $100 |
$1,250,001 to $1,300,000 | $1,550 | $100 | $100 |
$1,300,001 to $1,350,000 | $1,600 | $100 | $100 |
$1,350,001 to $1,400,000 | $1,650 | $100 | $100 |
$1,400,001 to $1,450,000 | $1,700 | $100 | $100 |
$1,450,001 to $1,500,000 | $1,750 | $100 | $100 |
* The cost of construction cannot be less than $60.57 per heated square foot of construction
** An HVAC and Plumbing Inspection is required for all new construction
*** Slab other than Monolith Pour Inspection is required when slab and footing are cast separately