Weekly Construction Report for Parts of East and Middle Tennessee for July 17 - July 23, 2014

Thursday, July 17, 2014 | 08:57am

BRADLEY COUNTY, I-75 construction of a concrete Bulb-Tee Beam Bridge, including grading, drainage and paving at the Exit 20 interchange (U.S. 64 Bypass East, U.S. 74 East, SR-311, APD-40) (LM 4.86) in Cleveland:  Work continues on this project.  On Wednesday, July 23, 2014, traffic will be moved onto the first phase of the new bridge over I-75.  Traffic has been shifted to the new temporary alignment at I-75 the southbound exit ramp.  Additionally, the contractor will be working on clearing and drainage and doing bridge work during this report period.  Any work requiring interstate lane closures is limited to Sunday through Thursday nights between 7PM - 6AM.  Signs will be posted and flaggers will assist with traffic control if needed.  THP will assist with traffic control as necessary during interstate lane closures.  Estimated project completion date is November 2015.

BRADLEY COUNTY, Benton Pike, Durkee Road, and Michigan Avenue, grading, drainage, and paving on a State Industrial Access route serving the Whirlpool Corporation:  The contractor continues work on this project at the Whirlpool Corporation plant.  Intermediate paving will be taking place along Benton Pike and Durkee Road.  Flaggers will assist with traffic control as needed.  Estimated project completion date is October 2014. 

CANNON / WARREN COUNTY, U.S. 70S (SR-1) grading, drainage, and construction of a concrete I beam bridge from near SR-281 in Cannon County to near SR-287 in Warren County:  The majority of the work has been completed on this project.  However, all motorists should continue to use caution and be alert to construction equipment and vehicles within the work zone.  Estimated project completion date is July 2014. 

CANNON / WARREN COUNTY, U.S. 70S (SR-1) paving from near SR-281 in Cannon County to Spring Valley Road in McMinnville, Warren County:  Work continues on this project.  Paving operations will be ongoing for the next several months (including weekends).  Stop signs and advanced warning signs have been added on all side roads and county roads while milling and paving operations continue on the mainline.  Message boards have been placed on both ends of the project to alert motorists of extensive truck traffic.  All motorists should use extreme caution and be alert to construction equipment and vehicles on the project.  Flaggers may be present on side roads.  No interruption of traffic is expected.  Estimated project completion date is September 2014. 

COFFEE COUNTY, I-24 grading, drainage and paving at the eastbound and westbound weigh stations from MM 117-115.5:  The contractor will have shoulder closures on I-24 East and West to perform work at the weigh stations.  No interstate lane closures are scheduled during this report period.  Lane closures on I-24 will only be allowed nightly from 6PM – 6AM.  THP will assist with traffic control as necessary during interstate lane closures and one lane will remain open at all times.  Estimated project completion date is November 2014. 

COFFEE COUNTY, SR-55 repair of bridge over SW Atlantic St., CSX Railroad, and SE Atlantic St. (LM 2.64):  Work is set to begin on this project during this report period.  On Monday, July 21, the contractor will begin installation of temporary striping followed by installation of barrier rail on Wednesday evening, July 23, 2014.  Once barrier rail is successfully installed, SR-55 at this location will be reduced to one lane in each direction until completion of the project.  Estimated project completion is December 2014. 

COFFEE and FRANKLIN COUNTIES - miscellaneous safety improvements on various state and local routes:  During this report period, the contractor will have lane closures on SR-15 in both directions from LM 23.70 to 28.30 to install guardrail.  At least one travel lane will remain open to traffic at all times.  Flaggers will assist with traffic if necessary.  Estimated completion date is July 2014. 

CUMBERLAND COUNTY, SR-462 new construction from U.S. 70 (SR-1) to U.S. 70N (SR-1), including grading, drainage and paving:  Construction work on this project is complete and final inspection has been performed.  The contractor will be addressing punchlist items during this report period.   Erosion control activities are in progress prior to issuance of a Notice of Termination.  Estimated project completion date is July 2014. 

CUMBERLAND COUNTY, U.S. 127 (SR-28) bridge repair over Obed River (LM 17.50):  Construction signs, portable barrier rail, arrowboards and barrels have been installed to reduce traffic from two lanes to one lane on both the northbound and southbound bridges.  Traffic on each bridge has been switched to the opposite lane to allow construction activities to continue.  Estimated project completion date is November 2014. 

CUMBERLAND COUNTY, SR 298 (Genesis Road) Resurfacing from west of Roy McCoy Road (LM 12.38) to the Morgan County line (LM 18.31):  Construction work on this project includes installation of construction signs, cold planning and asphalt paving.  Lane closures will be required with flaggers to control traffic.  Estimated project completion date is July 2014. 

DeKALB COUNTY, SR-26 (U.S. 70) construction of a welded steel plate girder bridge and three retaining walls over the Caney Fork River and Sligo Road (LM 24.58):  This bridge replacement project is underway.  During construction, the current bridge over the river will remain open to traffic until the new structure is constructed and able to carry traffic.  The contractor may have short lane closures to perform various operations on an as-needed basis.  Flaggers will be on site to assist with traffic control.  Estimated project completion date is June 2016. 

DeKALB, PUTNAM, WARREN COUNTIES, Miscellaneous safety improvements on Austin Bottom Road/Cookeville Boatdock Road/Baxter Road from Austin Lake Road/Sunny Point Road in DeKalb County to I-40 in Putnam County; miscellaneous safety improvements at the intersection of Old Smithville Road and Pike Hill Road (LM 0.36):  The contractor may have short lane closures to perform various operations on an as-needed basis.  Flaggers and THP will be on site to help with traffic control as necessary.  Estimated project completion date is July 2014. 

HAMILTON COUNTY, U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  The contractor will close Whitehall Road from Nye Drive to the Pinnacle Apartments rear entrance starting Monday, July 7 and ending on Friday, July 18.  Additionally, the contractor will close the Dayton Blvd. entrance ramp to U.S. 27 South on the evenings of Monday – Wednesday, July 21-23 to drill for high mast lighting.  On the evenings of Thursday, July 17 and Monday, July 21, 2014 the contractor will close East Elmwood Dr. between Whitehall Rd. and East Frontage Rd. and the right lane on U.S. 27 North from Manufacturers Rd. to the Signal Mtn. Blvd. exit to pour the bridge deck over East Elmwood Dr.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015. 

HAMILTON COUNTY, SR-58 resurfacing from Lakewood Acres Road (LM. 9.20) to Greenwood Road (LM 14.68):  During this report period, the contractor will be working on punchlist items.  Estimated completion date is July 2014. 

HAMILTON COUNTY, construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of working on road and drainage, along with environmental measures.  Traffic will not be impacted at this time so no lane closures are needed.  Estimated project completion date is September 2014. 

JACKSON COUNTY, SR-262 bridge repair over Cumberland River (LM 7.56):  Work continues on this project.  Temporary traffic signals have been removed, and the bridge is open to two lanes of traffic.  The contractor will be doing some minor work to complete the project in the next few weeks.  There may be shoulder closures as the result of this work.  Flaggers will assist with traffic control as necessary.  Estimated project completion date is July 2014. 

JACKSON COUNTY, SR-85 construction of small drainage structure at LM 11.27:  Work continues on this project.  SR-85 is closed at this site, and a detour is in place.  Flaggers will assist with traffic control as necessary.  Estimated project completion date is August 2014. 

JACKSON COUNTY, SR-53 resurfacing (thin-mix overlay) from SR-56 (LM 14.22) to the bridge over Roaring River (LM 15.72); SR-56 resurfacing (thin-mix overlay) from north of Old Creek Road (LM 10.02) to SR-53 (LM 10.94)  bridge repair over Cumberland River (LM 7.56):  Work continues on this project.  Milling and paving operations are underway.  Flaggers will assist with traffic control as necessary.  Estimated project completion date is July 2014. 

MARION and HAMILTON COUNTIES, I-24 resurfacing project from the end of Tennessee River Bridge at Nickajack Lake in Marion County near mile marker 161 extending through Hamilton County to the Georgia State Line near mile marker 167, including bridge deck repair:  Work continues on this project.  During this report period, the contractor will be performing nighttime paving operations on both sides of the interstate throughout the project area.  Paving operations requiring interstate lane closures are limited to Sunday through Thursday nights between 9PM – 6AM EDT.  THP will assist with traffic control as necessary during interstate lane closures.  Estimated project completion date is September 2014. 

MARION COUNTY, U.S. 41 (U.S. 64, U.S. 72, SR-2) replacement of the truss bridge over the Tennessee River at Nickajack Lake (LM 21.14) with a multi-span steel plate girder bridge:  The truss bridge is now closed to all through traffic until the new adjacent bridge currently under construction is completed.  A detour route that adds an additional 1.5 miles to the current route is posted.  Estimated date to have the bridge open to traffic is late summer 2014, with the final completion of the project by the end of the year. 

McMINN COUNTY, SR-30 widening project, including grading, drainage, paving, construction of a concrete box beam bridge and retaining wall from County Road 609 to the 4-lane section in Etowah:  Work continues on this project.  Traffic has been shifted onto the new traffic lanes from County Road 623 to west of County Road 561.  With this latest traffic shift, all traffic is now traveling on the newly-constructed traffic lanes from County Road 609 to the four lanes west of County Road 561.  Drivers are urged to use caution and pay attention to construction signs in this area.  Flaggers will assist with traffic control as needed.  Estimated project completion is November 2014. 

McMINN COUNTY, U.S. 411 (SR-30) resurfacing from east of Clearmont Drive (LM 19.19) to 9th Street (LM 21.04):  There will be intermediate lane closures in both directions as the contractor begins milling and paving the roadway.  Flaggers will assist with traffic control as needed.  Estimated project completion is July 2014.

McMINN and RHEA COUNTIES, SR-30 resurfacing (microsurfacing) from Duckett Hollow Rd. (LM 1.75) to west of Milton Rd. (LM 6.36); U.S. 27 (SR-29) resurfacing (microsurfacing) from south of Boofer Lane (LM 14.60) to Old SR-29 (LM 19.80):  Work will begin on this project during this report period.  Bridge repair work is scheduled to start on the bridge over Clear Creek in Rhea County on July 21, 2014 prior to the beginning of resurfacing work, which will require a lane closure on the bridge.  During this project, there will be intermediate lane closures in both directions as the contractor begins milling and paving the roadway.  Flaggers will assist with traffic control as needed.  Estimated project completion is September 2014.

MEIGS COUNTY, SR-30 relocation beginning east of the Tennessee River to west of SR-58:  Work on this project is substantially complete.  There will be few, if any, traffic disruptions from here on out until punchlist work is complete.  Flaggers will assist with traffic control as needed.  Estimated project completion is July 2014. 

POLK COUNTY, U.S. 64 (SR-40) resurfacing from east of Main St. (LM 26) to the North Carolina State Line (LM 30.02):  Work continues on this project.  During this work, there will be intermittent lane closures in both directions on U.S. 64.  Flaggers will assist with traffic control as needed.  Drivers are urged to use caution and pay attention to construction signs in this area.  Estimated project completion is July 2014.

PUTNAM COUNTY, I-40 resurfacing project from east of SR-56 (Exit 280) to near east of SR-136 (MM 287, LM 19.65), including bridge expansion joint repair:  Work continues on this project.  This is a nighttime paving operation and work will occur on both sides of the interstate.  Milling and/or paving operations requiring lane closures will be limited to Sunday through Thursday nights between 8PM – 6AM.  The only exception to this time restriction will be for bridge expansion joint repairs, which are not scheduled at this time.  One lane will remain open to traffic at all times during paving operations.  THP will assist with traffic control as necessary during interstate lane closures.  Estimated project completion is July 2014. 

PUTNAM and WHITE COUNTIES, resurfacing of SR-135 from Falling Water River Bridge (LM 0.08) to south of Winston Dr. (LM 7.74); resurfacing of SR-136 from U.S. 70 (SR-26/LM 11.43) to the bridge over SR-111 (LM 19.85); resurfacing of SR-135 from SR-136 (LM 5.81) to the Falling Water River Bridge (LM 19.85):  The contractor may have short lane closures to perform various operations on an as needed basis.  Flaggers will be on site to help with traffic control.  Estimated project completion is September 2014. 

VAN BUREN COUNTY, SR-111 grading, drainage, and paving from south of Manus Road to south of SR-285 near Double Bridge Road:  Work continues on this project.  Utilities are currently being installed while work is progressing on pipe replacements and extensions at various locations.  Grading and blasting operations are underway.  Motorists should expect delays..  Flaggers will be present during progression of work.  Motorists should use caution and be alert to construction equipment and vehicles within the work zone. The speed limit has been reduced to 45 MPH and is being enforced.  Estimated project completion date is November 2015. 

WHITE COUNTY, SR-111 resurfacing from north of SR-135 (LM 13.52) to north of SR-136 (LM 17.43):  The contractor may have short term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as necessary.  Project completion date is August 2014. 

###