West Tennessee Construction September 10 - September 16, 2009

Friday, September 11, 2009 | 02:56am
September 10 - September 16, 2009
 
CARROLL COUNTY, SR-76: Widening from Sydnor & Winston Roads to McKenzie. Watch for construction equipment entering and leaving roadway.  Speed Limit 45MPH. Traffic has been shifted to the new roadway.
 
CARROLL COUNTY, SR-22:(Recovery Act Project) bridge replacement, (Lexington Street) south of court square to SR-22 BYP CLOSED. Detour route posted.
 
DYER COUNTY, I-155 Bridge Repair: bridge repairs, over Mississippi River.  Northbound and Southbound shoulders are closed.
 
DYER COUNTY, SR-210:bridge repairs, over branch LM-0.30. Roadway is closed to traffic. Detour route posted.
 
FAYETTE COUNTY, Bridge Repair (5) on I-40
      Friday, September 11 through Monday September 14, westbound from 8PM-6AM. The contractorwill have lane closures in order to perform partial and full depth deck repair. One lane will be maintained in both directions at all times.
 
GIBSON COUNTY, SR-425: grade, drain and paving operations beginning west of Gann Road to Salem Street.
 
GIBSON COUNTY, SR-43:, grade, drain, installation of signals and paving operations at Old Medina Road. Speed Limit 45MPH.
 
HARDEMAN and McNAIRY COUNTIES, SR-15: construction of 4-lane highway from McClintock Rd to SR-225
 
HARDEMAN and McNairy COUNTIES, SR-125: bridge repairs, over branch LM-19.00. Roadway reduced to one lane with temporary signal. Use caution.
 
HARDIN COUNTY, SR-15: construction of 4-lane highway from near Savannah to Firetower Road. Watch for construction equipment entering and leaving roadway.
 
HENDERSON COUNTY, SR-20: construction of 4-lane highway from Madison County line to west of Crucifer Road. Watch for construction equipment entering and leaving roadway.
 
HENRY COUNTY, SR-69A: bridge repairs, over the Big Sandy River LM-0.13, roadway reduced to one (10’ 6”) lane with temporary signal
 
LAUDERDALE COUNTY, US-51 (SR-3) @ Tipton County line LM-0.00 to State Highway Garage: (Recovery Act Project)
      Thursday September 10 through Wednesday September 16, northbound & southbound from 7AM-7PM. The contractorwill have lane closures in order to perform paving operations and shoulder work. One lane will be maintained in both directions at all times.
 
MADISON COUNTY, Interstate 40 Resurfacing:  
      Thursday September 10 through Wednesday, September 16 eastbound and westbound from 7PM-5AM. The contractor willhavelane closures in order to perform shoulder work,joint work,pavement repairs,placement of reflective markers, and painted pavement markings. One lane will be maintained in both directions at all times.
 
McNAIRY COUNTY, US 64 (SR 15) Resurfacing from SR 5 to Mulberry St.:(Recovery ActProject)
      Thursday September 10 through Wednesday September 16: No Closures Scheduled.
 
OBION COUNTY, SR-22: bridge repairs, over North Reelfoot Creek LM-15.63 roadway will be reduced to one (10’) lane and maintained with temporary signal. Indian Creek LM-23.35 roadway will be reduced to one lane with temporary signal. 
 
OBION COUNTY, SR-5: bridge replacement, over Cane Creek LM-22.37 and over North Fork Hoosier Creek LM-18.22.  Roadway reduced to one (12’) lane northbound with temporary signal.
 
REGION 4, On-Call Guardrail Repair
HAYWOOD COUNTY
      Monday, September 14, 8PM-10PM, nightly: I-40 Eastbound east of Exit 56, one lane closed, one lane open.
      Monday, September 14, 10PM-12AM, nightly: I-40 Westbound “Off”ramp @ Exit 56/Brownsville, CLOSED.
      Monday, September 14 through Tuesday, September 15, 10PM-2AM, nightly: I-40 Westbound Off”ramp @ Exit 56/Brownsville and one lane closed,one lane open.
      Tuesday, September 15, 2AM-6AM, nightly: I-40 Eastbound near MM 49 between Exit 42/SR-222and Exit 56/Brownsville, one lane closed, one lane open.
      Wednesday, September 16, 2AM-6AM, nightly: I-40 Eastbound near MM 49 between Exit 42/SR-222and Exit 56/Brownsville, one lane closed, one lane open.
SHELBY COUNTY
      Tuesday, September 15 through Wenesday, September 16, 10PM-2AM, nightly: I-40 Eastbound near Exit 3/Watkins, one lane closed, two lanes open.
      Tuesday, September 15, 8PM-10PM, nightly: I-240 Southbound “On” ramp from Exit 28/S. Parkway EB, CLOSED.
 
SHELBY COUNTY, Seismic Retrofit on the bridge on I-40 over the Mississippi River 
      Thursday, September 10 6AM-7PM.  There will be one lane closed each direction (two lanes open).
      Thursday, September 10 7PM-6AM.  The traffic will be shifted into its final position for this closure with two lanes open both westbound and eastbound.  These closures will continue over the next few months, for bridge repair.
      Monday, September 14 6AM. There will be one lane closed Westbound (two lanes open), one lane closed (two lanes open) Eastbound. The two lanes that are closed are side by side. Ramp “NO” will remain open. These closures will continue over the next few months, for bridge repair.
      Friday, September 18 7PM. There will be one lane closed Westbound (two lanes open), two lanes closed Eastbound (one lane open). These closures will continue over the next few months, for bridge repair.
      Friday, September 18 through Monday, September 21 7PM-6AM. Ramp “NO” will be closed.
      Monday, September 21 6AM. There will be one lane closed Westbound (two lanes open), two lanes open Eastbound. Ramp “NO” open. These closures will continue over the next few months, for bridge repair.
 
SHELBY COUNTY, I-240, I-55 & I-40 ITS cable/radar/electrical installation
      Thursday September 10 through Wednesday September 16. No scheduled closures.
 
SHELBY COUNTY, SR-3 (US-51/Thomas Street) at Wolf River: bridge construction. Roadway reduced from 4 lanes to one (11’) lane in each direction.
 
SHELBY COUNTY, I-55 at Mallory Avenue: Widening of exist bridges, 3 lanes reduced to 2 each direction. Southbound will be shifted to the newly widening roadway. Traffic switched to new roadway. There will no longer be access to Mallory (Exit 9) from Northbound I-55. Use Third St (Exit 7) detour to Mallory. Riverside Drive from Mallory Avenue to Devant Street is closed indefinitely.  This existing section of roadway will be new location of the northbound I-55 entrance ramp. Use the newly constructed Riverport Road extension as an alternate route.
      Thursday September 10 through Thursday, September 16 northbound from 9AM-3PM. The contractor will haveintermittent lane closures to drive sheet piling along the interstate at Bridge 1 (MM 9). The contractor will be excavating the bridge abutments this week and needs to drive the sheet piling to safe up the interstate. One lane will be maintained in both directions at all times.
 
SHELBY COUNTY, I-55:resurfacing at Mississippi State Line to Nonconnah Creek.
      Thursday September 10 through Wednesday September 16. No scheduled closures.
 
TIPTON COUNTY, SR-14 (Austin Peay Highway):(Recovery ActProject)grade, drain and paving operations, beginning north of SR-206 and extending to 1.2 miles east of SR-384.
 
TIPTON COUNTY, SR-59:(Recovery ActProject) bridge replacement, over drainage ditch of Little Beaver Creek LM-24.54.
 
 
 
TDOT is now on Twitter.  For up to the minute traffic information in West Tennessee, including Memphis and Jackson, follow us on Twitter at http//www.twitter.com/Memphis511. For statewide travel information follow
 
All scheduled work is subject to change due to adverse weather conditions or other conditions beyond the control of the contractor.