Constructability Reviews

photo of constructed retaining wallThe Tennessee Department of Transportation is responsible for an integrated transportation system that provides the opportunity for economic prosperity and a high quality of life for Tennessee’s citizens.  In order for the Department to build fiscally responsible projects and maintain this infrastructure, development of transportation projects requires the combined effort of many resources, functional areas, and partnerships.  As part of the Department’s Strategic Planning, Business Process Re-engineering was initiated to develop and adjust procedures, as needed, to ensure that a quality product is provided.  One such initiative was the development of the Constructability Review.

Recognizing the challenges associated with highway construction, the goal of the Constructability Review is to utilize the expertise of both the Department and outside resources, including the Road Building Industry. This allows the designer to tap into the vast wealth of knowledge and experience available from the construction industry and others alike. A Constructability Review is intended to improve project quality, minimize potential change orders during construction, and provide a buildable and biddable construction bid package.

For questions concerning Constructability Reviews, please contact Jamie Waller by email at Jamie.Waller@tn.gov or by phone at (615) 741-0784.

As a contractor, how can I participate?

  • Participation in a review is voluntary, non-compensable, and will not prevent you from submitting a bid for the project.  Anything you choose to share will remain in confidence.  Any Contractor that is prequalified with TDOT's Construction Division may request participation by completing and submitting a Letter of Interest to Jamie Waller at Jamie.Waller@tn.gov.

How are projects recommended for a Constructability Review?

  • TDOT staff will conduct site reviews during the preliminary engineering and design phase of all projects.  The determination for the need for a Constructability Review will be made at the site review.

Previous Constructability Reviews

Constructability Review Tentative Date Region County Route PIN Type of Work Meeting Summary
6/14/2016 -6/15/2016 3 Davidson I-24 113437.00 Bridge Rehabilitation Davidson I-24 Summary
7/5/2016 - 7/6/2016 1 Knox SR-62 101204.00 Reconstruction Knox SR-62 Summary
7/11/2016 - 7/12/2016 3 Marshall SR-50 101887.00 Reconstruction Marshall SR-50 Summary
7/19/2016 - 7/21/2016 2 Cumberland SR-101 100268.00 Reconstruction Cumberland SR-101 Summary
8/24/2016 - 8/25/2016 4 Henry SR-54 101886.01 Widen Henry SR-54 Summary
11/14/2016 - 11/17/2016 3 Williamson SR-6 105717.00 Reconstruction Williamson SR-6 Summary
1/25/2017-1/26/2017 3 Williamson & Maury SR-247 103169.00 Widen Maury SR-247 Summary
9/11/17-9/12/17 3 Shelby SR-57 101645.00 Bridge Replacement Shelby SR-57 Summary

Upcoming Constructability Reviews

Constructability Review Tentative Date Region County Route PIN Type of Work  
Fall 2017 3 Rutherford SR-99 104004.01 Widen  
Fall 2017 3 Williamson SR-397 101454.01 New Construction  
Winter 2017 3 Davidson SR-112 103764.00 Widen  
Winter 2017 3 Davidson I-24   Modify Interchange  
Winter 2017 1 Blount SR-115 101651.01 Widen  
Spring 2018 1 Knox SR-115 100241.02 Widen  
Spring 2018 2 Hamilton I-24 112833.00 Modify Interchange

Documents


Frequent Topics

  • Project Phasing & Timing
  • Retaining Wall constructability
  • Utility Relocation & Coordination with other work
  • Railroad Challenges
  • Crane Placement

Common Review Questions

  • Describe each phase of work.
  • What is an appropriate project duration?
  • What are the greatest challenges of the project?
  • Do you have any ideas for implementing innovation to expedite overall job completion?
  • How/where do you plan to place you cranes?