State Route 96

Williamson and Rutherford Counties

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. Due to the size of the State Route 96 project, the planned improvements have been separated into four smaller sections or phases. The following is a reflection of various aspects of these phases as they have occurred or will occur along the corridor.

Section Phase Dates
from east of Arno Road to SR 252 (Wilson Pike) Construction Estimated Completion: June 2024
from SR 252 (Wilson Pike) to I-840 Engineering Underway  
from I-840 to Coleman Hill Road Engineering Underway  
from Coleman Hill Road to Veterans Parkway Engineering Underway  

*All forecasted dates are subject to change.