Skip to Main Content

State Route 65 (US 431)

Robertson County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW) and Construction. Proposed improvements to State Route 65 (US 431), between Old Highway 431 and SR 11 (US 41), consist of two roadway projects. The following is a reflection of various aspects of the phases as they have occurred or will occur on the improvements of the two sections.

Walling Road to SR 11 (US 41)    
Construction Contract Awarded September 2015  
Estimated Construction Completion Date August 2018  
Old Highway 431 to Walling Road    
ROW Appraisals/Acquisitions Completed October 2015  
Construction Contract Awarded January 2018  
Estimated Completion Date
August 2020  

*All forecasted dates are subject to change.

NOTE: The section of SR 65 from Old Highway 431, north of the Davidson County line, to Walling Road has been divided into two segments in an effort to sustain funding for construction.