State Route 6 (Franklin Road)

Williamson County

Timeline

All dates are tentative and subject to change. The approved completion date was in Summer 2022. However, multiple utility conflicts led to significant delays of the project's completion. The project is expected to be substantially completed with traffic in its final configuration by Thanksgiving. Final paving and striping operations were expected to be completed by the end of the year. Remaining striping and punch list items will likely be completed by the Spring of 2023 to mark the final completion of the project.

Preliminary Work August 2017 – October 2017
  • Traffic Control
  • Erosion Control
  • Clearing
 
Phase I October 2017 - Spring 2021
  • Utility work/relocation
  • Excavation/Grading
  • Construction of five retaining walls
  • Box culvert Installations
  • Base stone
  • Curb
  • Asphalt paving
  • Sidewalk
  • Swap traffic
 
Phase II Spring 2021  - Fall 2022
  • Excavation/Grading
  • Box Culvert Installations
  • Construction of one retaining wall
  • Base stone
  • Curb
  • Asphalt Paving
  • Sidewalk
  • Final Paving
  • Pavement Markings, Signs
 

The adjusted estimated completion date for this project is Early Spring 2023