State Route 6 (Franklin Road)

Williamson County

Timeline

All dates are tentative and subject to change. The approved completion date is in Summer 2022. Phase 2 of the project is underway. Work on retaining walls and box culverts will begin in early fall 2021 after a traffic shift onto new asphalt on a section near Holly Tree Gap Road. Utility relocations are in progress along with storm drainage installation and grade work. The remainder of the paving is scheduled for early summer 2022.

 

 

Preliminary Work August 2017 – October 2017
  • Traffic Control
  • Erosion Control
  • Clearing
 
Phase I October 2017 - Spring 2021
  • Utility work/relocation
  • Excavation/Grading
  • Construction of five retaining walls
  • Box culvert Installations
  • Base stone
  • Curb
  • Asphalt paving
  • Sidewalk
  • Swap traffic
 
Phase II Spring 2021  - Summer 2022
  • Excavation/Grading
  • Box Culvert Installations
  • Construction of one retaining wall
  • Base stone
  • Curb
  • Asphalt Paving
  • Sidewalk
  • Final Paving
  • Pavement Markings, Signs
 

The estimated completion date for this project is Summer 2022.