State Route 374
Montgomery CountyTimeline
Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW) and Construction. The proposed extension of State Route 374, including widening of SR 149, west of Clarksville, is currently in the Planning and Environmental phase. Below is a reflection of each project phase as they have occurred or will occur for the proposed project.
Environmental Assessment (EA) Approved | January 2019 |
Public Hearing | March 2019 |
Finding of No Significant Impact (FONSI) Approved | July 2020 |
Final NEPA Document Approved | Summer 2020 |
Due to the significant cost estimate to appraise and acquire Right of Way within the project limits, the proposed improvements will be separated into two smaller sections or phases. The anticipated timeline for each segment is as follows.
US 79 / SR 76 / Dover Road to Dotsonville Road |
|
ROW Appraisal/Acquisition | Funded in FY 2022 |
Dotsonville Road to SR 149 | |
ROW Appraisal/Acquisition | Pending Funding |
*All forecasted dates are subject to change.