State Route 16 (US 41-A)
Bedford, Coffee, and Franklin CountiesTimeline
Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur for the improvements of the three sections of State Route 16 (US 41-A).
SR 16 from SR 64 to SR 276 | |
This section has been divided into two segments in an effort to obtain funding for construction. |
|
ROW Acquisition/Relocation |
Completed February 2011 |
SR 64 to Jenkins Road | |
Construction Contract Awarded | October 2018 |
Construction Estimated Completion Date | Fall 2021 |
Jenkins Road to SR 276 | |
Construction Contract Awarded | October 2017 |
Construction Estimated Completion Date | Summer 2020 |
SR 16 from SR 276 to west of Magnolia Lane | |
This section has been divided into two segments in an effort to obtain funding for construction. | |
ROW Acquisition/Relocation |
Completed January 2010 |
SR 276 to Rippy Ridge Road | |
Construction Contract Awarded | December 2013 |
Construction Completion Date | August 2017 |
Rippy Ridge Road to west of Magnolia Lane | |
Construction Contract Awarded | April 2010 |
Construction Completion Date | April 2013 |
SR 16 from west of Moore-Coffee County line to North Washington Street | |
Construction Completion Date | March 2017 |
*All forecasted dates are subject to change.