State Route 16 (US 41-A)

Bedford, Coffee, and Franklin Counties

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur for the improvements of the three sections of State Route 16 (US 41-A).

SR 16 from SR 64 to SR 276
This section has been divided into two segments in an effort to obtain funding for construction.
ROW Acquisition/Relocation
Completed February 2011
SR 64 to Jenkins Road  
Construction Contract Awarded October 2018
Construction Completion Date Fall 2020
Jenkins Road to SR 276  
Construction Contract Awarded October 2017
Construction Completion Date Summer 2020
SR 16 from SR 276 to west of Magnolia Lane
This section has been divided into two segments in an effort to obtain funding for construction.
ROW Acquisition/Relocation
Completed January 2010
SR 276 to Rippy Ridge Road  
Construction Contract Awarded December 2013
Construction Completion Date August 2017
Rippy Ridge Road to west of Magnolia Lane  
Construction Contract Awarded April 2010
Construction Completion Date April 2013
SR 16 from west of Moore-Coffee County line to North Washington Street
Construction Completion Date March 2017

*All forecasted dates are subject to change.