State Route 149 / State Route 13

Montgomery County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction.  

Engineering Summer 2009  
Design Public Meeting June 29, 2010  
NEPA Document Approved 2011  
Right-of-Way Process (18-24 months) Summer 2012  
Construction   Started March 2018
 

Construction Schedule

All scheduled work is tentative and subject to change.

Preliminary Work  - March 2018 to Summer 2018

  • Clearing
  • Construct Access Road to Bridge

 

Phase I  -  March 2018 to Summer 2019

  • Traffic Control
  • Erosion Control
  • Phase I Bridge Construction
  • Phase I Roadway
  • Road and Drainage
  • Excavation
  • Paving and Striping
  • Traffic to Phase I of New Bridge

 

Phase II and III  - Summer 2019 to May 2021

  • Traffic Control 
  • Erosion Control
  • Demo Old Bridge (Fall 2019)
  • Excavation
  • Phase II Bridge Construction  (Fall 2019-Fall 2020)
  • Phase II Roadway  (Summer 2019 – May 2021)
  • Sidewalks
  • Paving and Striping
  • Signage
  • Erosion Control


The estimated completion for this project is May 2021.