Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur on the improvement of SR 112 (Clarksville Highway).

Bat Survey Completed Summer 2015  
Approval of Final Environmental Document Completed Summer 2015  
Funding for ROW Appraisals Only Approved September 2015  
Funding for ROW Acquisition Approved February 2016  
Construction Contract Letting Scheduled for October 2019  