Skip to Main Content

Find COVID-19 Information and Resources

State Route 109 - US 70 to Cumberland River

Wilson County

Timeline

Transportation projects are developed in three phases: Preliminary Engineering, Right-of-Way (ROW) and Construction. The proposed improvements for State Route 109, between US 70 and the Cumberland River, are currently under construction.

Let to Contract:  12/08/2017
Contractor:          Vulcan Construction Materials, LLC
Bid Price:              $50,924,616
Est. Completion: November 2020*

JULY 2020 UPDATE: TDOT and the contractor are currently in negotiations regarding a time extension due to previous utility delays on the project. Widening work is still underway as negotiations continue. At this time, TDOT anticipates construction will continue through late 2021. Once an agreement has been reached regarding the time extension, a new schedule will be provided.

All scheduled phases are TENTATIVE, dependent on weather and project progress.

 
Preliminary Work February 2018 to Summer 2018
  • Clearing
 
Phase I February 2018 to Summer 2019
  • Traffic Control
  • Erosion Control
  • Academy Road Intersection
  • Construct Detour Road
    • Detour Traffic Control
    • Detour Erosion Control
  • Road and Drainage
    • Excavation
    • Paving and Striping
  • Construct West Side of Spencer Creek Bridge
  • Construct East Side of Spencer Creek Bridge
  • Box Culverts (7)
 
Phase II Summer 2019 to November 2020*
  • Traffic Control
  • Erosion Control
  • Remove Detour
  • Road and Drainage
    • Excavation
    • Paving and Striping
  • Construct East side of Spencer Creek Bridge
  • Construct West side of Dry Fork Branch Bridge
  • Box Culverts (7)
  • Erosion Control/Landscaping
  • Permanent Signage
 

*An updated schedule will be provided once an agreement on a time extension has been reached.