State Route 109 - US 70 to Cumberland River
Wilson CountyTimeline
Transportation projects are developed in three phases: Preliminary Engineering, Right-of-Way (ROW) and Construction. The proposed improvements for State Route 109, between US 70 and the Cumberland River, are currently under construction.
Let to Contract: 12/08/2017
Contractor: Vulcan Construction Materials, LLC
Bid Price: $50,924,616
Est. Completion: November 2021
OCTOBER 2020 UPDATE: A contract extension has been been approved to account for utility delays. The new contract completion date is November 2021.
All scheduled phases are TENTATIVE, dependent on weather and project progress.
Preliminary Work | February 2018 to Summer 2018 |
|
|
Phase I | February 2018 to Summer 2020 |
|
|
Phase II | Summer 2020 to November 2021 |
|