State Route 396 Saturn Parkway Extension
Maury CountyTimeline
Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. In an effort to expedite project delivery, the State Route 396 Saturn Parkway Extension will be completed under a Design-Build contract. The Design-Build project delivery method combines all or some portions of the design and construction phases of a project - including design, regulatory permit approvals, utility relocation, and construction – into a single contract.
The following is a reflection of various aspects of the project phases as they have occurred or will occur for the planned Saturn Parkway Extension.
|
|
Design and Permits | Spring 2018 |
Right-of-Way and Utilities | Spring 2018 |
Construction | Spring 2018 thru Summer 2019 |
|
|
Design and Permits | Spring 2018 |
Right-of-Way and Utilities | Spring 2018 |
Construction | Spring 2018 thru Summer 2019 |
|
|
Interchange/Ramps at GM Entrance | |
Design and Permits | Spring 2018 thru Summer 2018 |
Right-of-Way and Utilities | Spring 2018 thru Winter 2018 |
Construction | Fall 2018 thru Fall 2019 |
Widening of Beechcroft Road (remainder) and Extension of Saturn Parkway |
|
Design and Permits | Spring 2018 thru Fall 2018 |
Right-of-Way and Utilities | Spring 2018 thru Winter 2018 |
Construction | Fall 2019 |
|
Fall 2020 |
*All forecasted dates are subject to change.
For more information on the Design-Build process for the Saturn Parkway Extension, visit the Design-Build information page under the Construction Division section of the TDOT website.