Interstate 65 Interchange at State Route 109

Robertson and Sumner Counties

Timeline

All scheduled work is tentative and subject to change.

Updated July 2019 

 

Bridge Construction

Feb. 2017:  New SR 109 bridge over I-65 work completed

Dec. 2017: Removal of existing Lake Springs Road bridge over I-65 completed

 

Ramp Construction

Ramps B, D, F and G completed

July 2019 to Nov. 2019: Complete Ramps A, C, E, H, I, J and K (tie-ins to I-65)

 

I-65 Construction

July 2019 to Aug. 2019: Complete preliminary paving of I-65 inside lane to allow traffic switch to I-65 inside lanes

Aug. 2019 to Nov. 2019: Complete outside lane construction

Oct. 2019 to Nov. 2019: Complete preliminary paving on I-65 and open interchange to traffic

Spring 2020: Complete final paving

 

The estimated completion date for this project is May 2020.