Skip to Main Content

Interstate 440

Davidson County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. In an effort to expedite project delivery, the I-440 rehabilitation will be completed under a Design-Build contract. The Design-Build project delivery method combines all or some portions of the design and construction phases of a project - including design, regulatory permit approvals, utility relocation, and construction – into a single contract.

The following is a reflection of various aspects of the project phases as they have occurred or will occur for the proposed I-440 improvements.

Initial Survey / National Environmental Policy Act (NEPA) Document Summer 2017
Preliminary Engineering Summer/Fall 2017
Request for Qualifications (RFQ) for Design-Build Advertised August 2017 - October 2017
Shortlist of Qualifying Design-Build Teams November 2017
Issue Request for Proposal (RFP) for Design-Build January 2018
Review of Technical/Pricing Proposals July 2018
Design-Build Contract Award
August 1, 2018
Construction Activities Begin Forecasted for November 2018
Estimated Completion Date August 2020

*All forecasted dates are subject to change.

Design-Build Timeline

Timeline for Design-Build Project Delivery Method

Contract Award

On August 1, 2018, TDOT awarded the contract for the I-440 project to Kiewit Infrastructure South Co. for $152.9 million. The work will be completed in less than two years using traditional construction.

TDOT and the Design-Build team will work to finalize the design and project clearance to allow construction to begin as early as November 2018. The initial schedule of work is as follows.

  • Fall 2018 – Begin installation of fiber optic network and new lighting, construction of seven noise walls, and completion of two small projects to alleviate congestion on the westbound Murphy Road exit ramp and the eastbound Hillsboro Road exit ramp
  • Early 2019 – Begin heavy construction activities to replace concrete pavement, widen the roadway, and remove center raised median
  • Spring 2019 – Begin 24-hour operations, 6 to 7 days/week, heavy nighttime work
  • Fall 2019 – Begin work on I-440 bridge over I-65
  • August 2020 – Estimated Completion Date

Traffic Control

For the duration of the project, two lanes of I-440 will remain open during peak morning and afternoon travel times. Nighttime lane closures will be from 9:00 p.m. to 5:00 a.m. TDOT is also working closely with Metro Nashville Public Works to address signal timing and other issues on local streets in the project area, which are likely to see an increase in traffic once I-440 is under construction.