Skip to Main Content

Interstate 440

Davidson County

Welcome to the Interstate 440 Reconstruction project website!

The latest project information - including news releases, videos, and construction schedule, and lane closure activity - will be provided on this landing page. For other detailed information - including Overview, Timeline, Public Involvement, Frequently Asked Questions, and Contacts - please select the corresponding pages from the dropdown menu for this project.

Upcoming Schedule - Updated 3/14/2019

Schedule information is tentative and subject to change. To check current traffic conditions and/or to view traffic cameras, please visit www.TNsmartway.com.

 

Median Removal and Concrete Rubblization

Anticipated Traffic Shift Schedule:

Friday March 15 through Wednesday March 13 - I-65 to Nolensville Pike

Friday March 22 through Wednesday March 27 - Nolesnville Pike to I-24

Anticipated Traffic Impacts: I-440 reduced to two lanes between 5AM-9PM and reduced one lane between 9PM-5AM. Shoulders will be closed and merge lanes will be shortened. Drivers should expect longer drive times once this work begins.

Other Impacts: Construction operations will be underway 24 hours a day, six days a week. 

 

Ramp Queue Projects

  • 21st Avenue Ramps – 440 Westbound
    • Est.Completion* - April 2019
    • Anticipated Traffic Impacts - traffic shifts, shoulder closures, intermittent ramp closures between 9PM-5AM
  • Murphy Road – 440 Eastbound
    • Est. Completion* - April 2019
    • Anticipated Traffic Impacts - traffic shifts, shoulder closures, intermittent ramp closures between 9PM-5AM

*permanent signal upgrades are tentatively scheduled for fall 2019

Fiber Relocation

  • Throughout 440 Corridor
    • Starting - week of November 26
    • Duration - 5 Months

Lighting

  • Murphy Road to Hillsboro/21st Avenue
    • Est. Completion - March 2019

Email Updates

To receive email updates on this project, including lane closure information, fill out and submit the form below.