Skip to Main Content

Interstate 440

Davidson County

Welcome to the Interstate 440 Reconstruction project website!

The latest project information - including news releases, videos, and construction schedule, and lane closure activity - will be provided on this landing page. For other detailed information - including Overview, Timeline, Public Involvement, Frequently Asked Questions, and Contacts - please select the corresponding pages from the dropdown menu for this project.

To view all TDOT-produced I-440 videos, see the links provided below or visit the TDOTnews YouTube Channel, I-440 playlist.

Upcoming Schedule

Schedule information is tentative and subject to change. To check current traffic conditions and/or to view traffic cameras, please visit www.TNsmartway.com.

Weekend Ramp Closure Schedule - Updated November 13, 2019

 

Friday, November 15 at 9PM through Monday, November 18 at 5AM

·         I-65 in both directions to I-440 eastbound

·         I-440 eastbound to I-65 southbound

·         I-440 westbound to Nolensville Pike

·         Nolensville Pike northbound to I-440 westbound

·         I-24 eastbound to I-440 westbound (Friday at 9PM through Sunday at 5AM) 

 

Friday, November 22 at 9PM through Sunday, November 24 at 5AM

·         I-440 eastbound to Nolensville Pike

·         I-440 eastbound to Hillsboro Pike southbound

 

Friday, December 6 at 9PM through Monday, December 9 at 5AM

·         I-440 westbound to I-65 southbound

 

General Construction Activities - Updated November 7, 2019

Selective areas of the corridor have already started to have temporary barrier removed.  Intermittent work will still be taking place in these areas.  The contractor will continue to remove the barrier from the corridor intermittently over the next few months.

 

I-40 to Hillsboro Pike 

 

·         Concrete removals in small areas as ramps are switched onto the permanent alignment.

·         Subgrade Finishing and Cement Treated Base Course (day shift and night shift)

·         Rubblizing Concrete Pavement on both Eastbound and Westbound (day shift)

·         Crushing Concrete Base in the I-40/I-440 yard (day shift)

·         Asphalt Paving Operations (day shift and night shift)

·         Concrete Valley Gutter operations (day shift)

·         Concrete Ramp Work – repairs and installation of new (day shift and night shift)

·         Installation of Roadway lighting and bridge underdeck lighting (day shift)

·         Rockfall Mitigation Work – scaling and shotcrete operations (day shift)

·         Landscaping activities – installation of trees and new vegetation (day shift)

·         Installation of Misc. Roadway Items such as Barrier Wall and Guardrail (day shift and night shift)

 

Hillsboro Pike to I-65 

·         Concrete removals on both Eastbound and Westbound (day shift and night shift)

·         Subgrade Finishing and Cement Treated Base Course (day shift and night shift)

·         Rubblizing Concrete Pavement on both Eastbound and Westbound (day shift)

·         Asphalt Paving Operations (day shift and night shift)

·         Concrete Valley Gutter operations (day shift)

·         Concrete Ramp Work – repairs and installation of new (day shift and night shift)

·         Installation of Roadway lighting and bridge underdeck lighting (day shift)

·         Rockfall Mitigation Work – scaling and shotcrete operations (day shift)

·         Noisewall Repair work – Lealand and Craig Areas Starting in November (day shift)

·         Landscaping activities – installation of trees and new vegetation (day shift)

·         Installation of Misc. Roadway Items such as Barrier Wall and Guardrail (day shift and night shift)

 

I-440 Bridges over I-65

·         Installation of Stay-in-Place metal decking. (day shift and night shift)

·         Installation of Deck Reinforcing steel. (day shift and night shift)

·         The first concrete deck pours are schedule to start the 2nd week of December.

 

I-65 to Nolensville Pike 

·         Concrete removals on both Eastbound and Westbound (day shift and night shift)

·         Storm Drainage excavation and installation on both Eastbound and Westbound (day shift and night shift)

·         Subgrade Finishing and Cement Treated Base Course (day shift and night shift)

·         Rubblizing Concrete Pavement on both Eastbound and Westbound (day shift)

·         Asphalt Paving Operations (day shift and night shift)

·         Concrete Valley Gutter operations (day shift)

·         Concrete Ramp Work – repairs and installation of new (day shift and night shift)

·         Installation of Roadway lighting and bridge underdeck lighting (day shift)

·         Landscaping activities – installation of trees and vegetation (day shift)

·         Installation of Misc. Roadway items such as barrier Wall and Guardrail (day shift and night shift)

 

Nolensville Pike to I-24 

·         Concrete removals on both Westbound (day shift and night shift)

·         Storm Drainage excavation and installation on Westbound (day shift and night shift)

·         Subgrade Finishing and Cement Treated Base Course (day shift and night shift)

·         Rubblizing Concrete Pavement on Westbound (day shift)

·         Crushing Concrete Base in Westbound I-440/I-24 East Yard (day shift)

·         Asphalt Paving Operations (day shift and night shift)

·         Concrete Valley Gutter operations (day shift)

·         Concrete Ramp Work – repairs and installation of new (day shift and night shift)

·         Installation of Roadway lighting and bridge underdeck lighting (day shift)

·         Landscaping activities – installation of trees and vegetation (day shift)

·         Installation of Misc. Roadway items such as barrier wall and Guardrail (day shift and night shift)

 

 
 
 
 

Email Updates

To receive email updates on this project, including lane closure information, fill out and submit the form below.