Skip to Main Content

INFORMATION ABOUT THE ONGOING NOVEL CORONAVIRUS OUTBREAK

Interstate 440

Davidson County

Welcome to the Interstate 440 Reconstruction project website!

The latest project information - including news releases, videos, and construction schedule, and lane closure activity - will be provided on this landing page. For other detailed information - including Overview, Timeline, Public Involvement, Frequently Asked Questions, and Contacts - please select the corresponding pages from the dropdown menu for this project.

March 1, 2020, marked one year of heavy construction for the I-440 Reconstruction Project.
The above video highlights the work completed over the last year.
The entire project is expected to be completed in August 2020.

To view all TDOT-produced I-440 videos, see the links provided below or visit the TDOTnews YouTube Channel, I-440 playlist.

Upcoming Schedule

Schedule information is tentative and subject to change. To check current traffic conditions and/or to view traffic cameras, please visit www.TNsmartway.com.

Friday, April 3 at 8PM through Monday, April 6 at 6AM, The ramp from I-65 northbound to I-440 westbound will be closed for concrete replacement. This closure is weather dependent.

General Construction Activities - Updated March 26, 2020

 

·       Traffic switches from phase I to phase II have been completed for the project, including over the recently completed widening of the I-65 flyover bridge.

 

·       Most major on-ramp/off-ramp switches have been completed.  Minor adjustments may continue to be made to facilitate the work.

 

·       The majority of the remaining temporary barrier will continue to be removed from the corridor over the course of the next couple of weeks.

 

·       Focus will shift corridor wide to preparing for and starting final surface of asphalt.

 

I-40 to Hillsboro Pike

·       Asphalt Paving Operations (day shift or night shift).

·       Miscellaneous Grading, Slope Finishing and Stabilization Operations (day shift).

·       Concrete Valley Gutter operations (day shift).

·       Concrete Pavement Grinding of Ramps (night shift).

·       Installation of Roadway lighting and bridge underdeck lighting (day shift).

·       Landscaping activities – installation of trees and new vegetation (day shift).

·       Installation of Misc. Roadway Items such as Barrier Wall and Guardrail (day shift and night shift).

 

Hillsboro Pike to I-65

·       Asphalt Paving Operations (day shift or night shift).

·       Miscellaneous Grading, Slope Finishing and Stabilization Operations (day shift).

·       Concrete Valley Gutter operations (day shift).

·       Concrete Pavement Grinding of Ramps (night shift).

·       Installation of Roadway lighting and bridge underdeck lighting (day shift).

·       Landscaping activities – installation of trees and new vegetation (day shift).

·       Installation of Misc. Roadway Items such as Barrier Wall and Guardrail (day shift or night shift).

 

I-440 Bridges over I-65

·       Removal of Existing Concrete Pavement.

·       Installation of new Storm Drainage and miscellaneous Grading activities.

·       Placement of Cement Treated Base Course.

·       Asphalt Paving Operations (day shift or night shift).

·       Miscellaneous Grading, Slope Finishing and Stabilization Operations (day shift).

 

I-65 to Nolensville Pike

·       Asphalt Paving Operations (day shift or night shift).

·       Miscellaneous Grading, Slope Finishing and Stabilization Operations (day shift).

·       Concrete Valley Gutter operations (day shift).

·       Concrete Pavement Grinding of Ramps (night shift).

·       Installation of Roadway lighting and bridge underdeck lighting (day shift).

·       Landscaping activities – installation of trees and vegetation (day shift).

·       Installation of Misc. Roadway items such as barrier Wall and Guardrail (day shift or night shift).

 

Nolensville Pike to I-24

·       Asphalt Paving Operations (day shift or night shift).

·       Concrete Valley Gutter operations (day shift).

·       Concrete Placement of Median Ditch (day shift).

·       Installation of Roadway lighting and bridge underdeck lighting (day shift).

·       Landscaping activities – installation of trees and vegetation (day shift).

·       Installation of Misc. Roadway items such as barrier wall and Guardrail (day shift or night shift).

 

 
 

Email Updates

To receive email updates on this project, including lane closure information, fill out and submit the form below.