Skip to Main Content

Interstate 440

Davidson County

Welcome to the Interstate 440 Reconstruction project website!

The latest project information - including news releases, videos, and construction schedule, and lane closure activity - will be provided on this landing page. For other detailed information - including Overview, Timeline, Public Involvement, Frequently Asked Questions, and Contacts - please select the corresponding pages from the dropdown menu for this project.

Upcoming Schedule - Updated 1/16/2019

Schedule information is tentative and subject to change. To check current traffic conditions and view traffic cameras, please visit https://smartway.tn.gov/.

Current Work

Noise Wall Construction

The Grove at Whitworth –440 Eastbound, East of West End Avenue

  • Starting the week of November 26
  • Est. Completion week of January 28
  • Anticipated Traffic Impacts Shoulder closures

Linmar Avenue - 440 Eastbound, West of Hillsboro Rd/21st Avenue

  • Starting the week of November 26
  • Est. Completion mid-February
  • Anticipated Traffic Impacts Shoulder and auxiliary lane closures

Battlefield Drive – 440 Eastbound, West of I-65 Interchange

  • Starting the week of December 10
  • Est. Completion mid-February
  • Anticipated Traffic Impacts Shoulder and auxiliary lane closures

South Lyle Lane, DeSoto Drive, Dodge Drive – 440 Eastbound, West of I-24 Interchange

  • Starting the week of December 10
  • Est. Completion late February
  • Anticipated Traffic Impacts Shoulder closures

Ramp Queue Projects

21st Avenue Ramps – 440 Westbound

  • Starting the week of November 26
  • Est.Completion* early February
  • Anticipated Traffic Impacts Traffic shifts, shoulder closures, intermittent ramp closures between 9PM-5AM

Murphy Road – 440 Eastbound

  • Starting the week of December 17
  • Est. Completion* early February
  • Anticipated Traffic Impacts Traffic shifts, shoulder closures, intermittent ramp closures between 9PM-5AM

*permanent signal upgrades are tentatively scheduled for summer 2019

Fiber Relocation – Throughout 440 Corridor

  • Starting the week of November 26
  • Duration 5 Months
  • Anticipated Traffic Impacts Shoulder closures, lane closures between 9PM-5AM, auxiliary lane closures

Lighting – From Murphy Road to Hillsboro/21st Avenue

  • Starting the week of December 10
  • Duration 12 Weeks
  • Anticipated Traffic Impacts Shoulder closures, lane closures between 9PM-5AM, auxiliary lane closures

 

Look Ahead

Median Removal and Concrete Rubblization

Traffic shifts for median removal operations tentatively scheduled for late February 2019

Anticipated Traffic Impacts 440 reduced to two lanes between 5AM-9PM and one lane between 9PM-5AM

 

News Releases

I-440 Reconstruction Project Update - October 12, 2018 

TDOT Awards I-440 Reconstruction Project - August 1, 2018

 

Email Updates

To receive email updates on this project, including lane closure information, fill out and submit the form below.