Interstate 65 Buckner Road Interchange

Williamson County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. In an effort to expedite project delivery, the I-65 Interchange at Buckner Road project will be completed under a Design-Build contract. The Design-Build project delivery method combines all or some portions of the design and construction phases of a project - including design, regulatory permit approvals, utility relocation, and construction – into a single contract.

The following is a reflection of various aspects of the project phases as they have occurred or will occur for the planned I-65 Interchange at Buckner Road.

Request for Qualification (RFQ) January 2020
Request for Proposals (RFP) July 2020
Award of Contract January 2021
Completion of Design Plans June 2022
Construction Begins  February 2022
Bridge Construction Begins  August 2022
Construction Complete Spring 2023

*All forecasted dates are subject to change.

Image of Design-Build Project Delivery Method

Timelline for Design-Build Project Delivery Method

For more information on the Design-Build process for this project, visit the Design-Build I-65 Interchange at Buckner Road information page under the Construction Division section of the TDOT website.

Contract

On Monday, January 4, 2021, TDOT officially awarded the contract for the I-65 Interchange at Buckner Road to Bell & Associates Construction, LLC at a cost of $54,258,650.

Using the Design-Build project delivery method, design and construction will be completed in less than three years.

Following the contract award, the design will be finalized, and the necessary right-of-way and permits will be acquired. Utility relocations will begin shortly thereafter, with construction expected between spring 2022 and spring 2023. Once activity begins in the project area, every effort will be made to minimize impacts to drivers near the work zone.