State Route 30
Rhea CountyTimeline
Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction, as illustrated below. The proposed improvements for State Route 30, from State Route 29 in Dayton to west of the Tennessee River, are currently in the Environmental phase. This phase must be completed before the project may move on to subsequent phases.

Environmental five-step process illustration
The following is a reflection of various aspects of the development phases as they have occurred or will occur on the SR 30 improvement project.
Project Kickoff | Summer 2014 | ||
Public Meeting | Fall 2014 | ||
Technical Studies | Winter 2014/Spring 2015 | ||
Environmental Assessment (EA) Prepared | Summer/Fall 2015 | ||
Public Hearing | Forecasted for Spring 2016 | ||
Select Preferred Alternative | Forecasted for Spring 2016 | ||
Environmental Assessment (EA) Completed | Forecasted for Summer 2016 |
*Forecasted dates are subject to change.