State Route 60 from North of I-75 to State Route 306 (Eureka Road)

Bradley County

Timeline

Transportation projects are developed in three phases: Preliminary Engineering, Right-of-Way (ROW) and Construction. Due to the significant size of the State Route 60 (Georgetown Road) project, the proposed construction improvements have been separated into three phases for this project.

Let to Contract:  9/11/2021
Contractor:          Summers-Taylor, Inc.
Bid Price:             $53,992,362.20
Est. Completion:  August 2025

All scheduled traffic phases are TENTATIVE, dependent on weather and project progress.

PHASE 1 – October 2020 to May 2023

  • SR 60 (Georgetown) – Two travel lanes (one lane in each direction) will remain open, but lanes will be shifted to allow for roadway construction and installation utility work.
  • Davis Circle – North end access to SR 60 will be closed. Access to SR 60 will require all traffic to use the south end of Davis Circle.
  • Eveningside Drive – North end access to SR 60 will be closed. Access to SR 60 will require all traffic to use the south end of Eveningside Drive.
  • Detour will be in place for Old Georgetown Street and Ann Lane realignment. Access provided by Gregory Lane.
  • Freewill Road/Eureka Road (SR 306) intersection realignment. Flagging operations and traffic shifts.

PHASE 2 – May 2023 to November 2024

  • R 60 (Georgetown) – Two travel lanes (one lane in each direction) will remain open, but lanes will be shifted to allow for roadway construction and installation utility work.
  • Davis Circle – North end access to SR 60 will be closed. Access to SR 60 will require all traffic to use the south end of Davis Circle.
  • Campbell Drive – Reconstruction activities will be performed with flagging operation to allow traffic ingress and egress.
  • Weston Hills Drive – Reconstruction activities will be performed with flagging operation to allow traffic ingress and egress.
  • Villa Drive – Realignment of the intersection will require flagging operations and traffic shifts.
  • Kimberly Drive - Reconstruction activities will be performed with flagging operation to allow traffic ingress and egress.
  • Lenox Drive - Reconstruction activities will be performed with flagging operation to allow traffic ingress and egress.
  • andies Creek Lane - Reconstruction activities will be performed with flagging operation to allow traffic ingress and egress.
  • Gregory Lane – Realignment and construction activities will require this intersection to be closed and detoured through Ann Lane.
  • ·  Lilac Drive – Closed for reconstruction activities April 2024 thru May 2024 with posted detour routed through Georgetown Drive.
  • Carnation Avenue – Closed for reconstruction activities. Traffic will be detoured through Georgetown Drive.
  • Georgetown Drive – Closed for reconstruction activities. Traffic will be detoured through Carnation Avenue.
  • Hopewell Drive – Reconstruction activities will be performed with flagging operation to allow traffic ingress and egress.
  • Hopewell Place - Reconstruction activities will be performed with flagging operation to allow traffic ingress and egress.

PHASE 3 – November 2024 to August 2025

Final paving, pavement markings and signs will be installed. Traffic will encounter flagging operations, and traffic shifts while these activities are taking place.