Interstate 75 Interchange at Interstate 24 - Phase II
Hamilton CountyTimeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. In an effort to expedite project delivery, Phase 2 of the Interstate 75 Interchange at Interstate 24 modifications will be completed under a Design-Build contract. The Design-Build project delivery method combines all or some portions of the design and construction phases of a project - including design, regulatory permit approvals, utility relocation, and construction – into a single contract.
The following is a reflection of various aspects of the project phases as they have occurred or will occur for the planned I-75/I-24 Phase 2 Interchange improvements.
RFQ Advertised | 10/25/21 | |
RFP Advertised | 5/27/22 | |
Award | 11/28/22 | |
Completion of Design Plans | Late 2023 | |
Completion Date | Late 2025 |
*All forecasted dates are subject to change.