Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. The planned modifications for Interstate 24 at US 41 (SR 2/Broad Street) and State Route 58 (Market Street) in Chattanooga, Hamilton County, are currently under construction.

Let to Contract:            06/26/2020
Contractor:                    Wright Brothers Construction Company, Inc.
Bid Price:                        $31,994,789
Est. Completion Date: August 2023

Work is scheduled to begin mid-September. The preliminary schedule shows temporary construction signs to be installed Monday, September 14, 2020, followed by utility relocation. The first five months or so will consist primarily of utility work.