Transportation projects are developed in three phases: Preliminary Engineering, Right-of-Way (ROW) and Construction. Due to the significant size of the State Route 317 (Apison Pike) project, the proposed improvements have been separated into four smaller sections or phases. Below is a summary of the current status of each section.

LOCATION PHASE DATES
I-75 to Old Lee Highway
Completed February 2012
Old Lee Highway to SR 321 (Ooltewah Ringgold Road) Completed September 2017
SR 321 (Ooltewah Ringgold Road) to Layton Lane Construction Estimated Completion Date -- June 2025
Layton Lane to East Brainerd Road Preliminary Engineering Forecasted for ROW -- Fall 2021

*All forecasted dates are subject to change.