Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. Proposed improvements to State Route 34 (US 11E) in Hamblen County consist of three roadway projects. Below is a reflection of each project phase as they have occurred or will occur for each section of SR 34.

SR 34 from SR 32 to Steadman Road (full project length)
 
EA1 Document Approved May 2009
FONSI2 Document Approved March 2010
from SR 32 (US 25E) to near East Morris Boulevard
 
ROW Appraisal/Acquisition (26-30 months to complete) Currently underway
Construction Pending ROW acquisition AND funding availability
from near East Morris Boulevard to west of Old Stagecoach Road
 
ROW Appraisal/Acquisition Currently Underway
Construction Pending ROW acquisition AND funding availability
from west of Old Stagecoach Road to Steadman Road
 
ROW Appraisal/Acquisition Forecasted for Fiscal Year 2022
Construction Pending ROW acquisition AND funding availability

*All forecasted dates subject to change.

  1. EA = Environmental Assessment (required by Federal Highway Administration as part of the National Environmental Policy Act (NEPA) process)
  2. FONSI = Finding of No Significant Impact (required by Federal Highway Administration as part of the National Environmental Policy Act (NEPA) process)