Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. Proposed improvements to State Route 34 (US 11E) in Hamblen County consist of three roadway projects. Below is a reflection of each project phase as they have occurred or will occur for each section of SR 34.
SR 34 from SR 32 to Steadman Road (full project length) |
|
EA1 Document Approved | May 2009 |
FONSI2 Document Approved | March 2010 |
from SR 32 (US 25E) to near East Morris Boulevard |
|
ROW Appraisal/Acquisition (26-30 months to complete) | Currently underway |
Construction | Pending ROW acquisition AND funding availability |
from near East Morris Boulevard to west of Old Stagecoach Road |
|
ROW Appraisal/Acquisition | Currently Underway |
Construction | Pending ROW acquisition AND funding availability |
from west of Old Stagecoach Road to Steadman Road |
|
ROW Appraisal/Acquisition | Forecasted for Fiscal Year 2022 |
Construction | Pending ROW acquisition AND funding availability |
*All forecasted dates subject to change.
- EA = Environmental Assessment (required by Federal Highway Administration as part of the National Environmental Policy Act (NEPA) process)
- FONSI = Finding of No Significant Impact (required by Federal Highway Administration as part of the National Environmental Policy Act (NEPA) process)