State Route 93 from Interstate 81 to State Route 347 (Lone Star Road)

Sullivan and Washington Counties

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW) and Construction. Improvements to State Route 93, between I-81 and SR 347 (Lone Star Road), consist of three sections. Below is a reflection of each project phase as they have occurred or will occur for each section of SR 93.

Environmental Studies (all sections) Completed Spring 2015
Section 1 (Fall Branch Area)  
ROW Plans Completed Fall 2015
ROW Appraisals/Acquisition Finalizing acquisitions
Construction Forecasted for completion on or before August 31, 2021
Section 2 (Horse Creek Area)  
ROW Plans Completed Fall 2015
ROW Appraisals/Acquisition Completed
Construction Late 2021/Early 2022 (pending available funding)
Section 3 (Industrial Access Area)
 
ROW Plans Completed Spring 2016
ROW Appraisals/Acquisition Finalizing acquisitions
Construction Not yet identified for construction in TDOT's 3 year work program

*Forecasted dates are subject to change.

NOTE: During the ROW phase, TDOT contracts with independent licensed appraisers to appraise affected property within the project limits. Prior to acquisition, TDOT staff will hold a ROW meeting with affected property owners to discuss the process and answer any questions. The timeframe for the ROW phase can vary from one project to another depending upon the number of properties affected.