SR 63 Bridge Construction and Paving

 

Project Updates

February 27, 2023

The clearing and grubbing is 100% complete. There have been 24 box culvert extensions put into place. Water & fiber relocation are currently underway. Excavation & fill operations underway. Phase 1 milling & paving completed with new traffic pattern.

 November 28, 2022

The clearing and grubbing is 100% complete. There have been 23 box culvert extensions put into place. Water & fiber relocation are currently underway. Excavation & fill operations are underway. Phase 1 milling and paving is complete.  

September 26, 2022

The clearing and grubbing is 100% complete. There have been 16 box  culvert extensions put into place. There is currently water & fiber relocation underway. Excavation & fill operations have begun. Phase 1 milling & paving completed with new traffic pattern.  

August 28, 2022

The clearing and grubbing is 100% complete . There have been 12 box culvert extensions put into place. Water & fiber relocation are underway. Excavation & fill operations have begun. Phase 1 Milling & paving completed with new traffic pattern.

July 28, 2022

The clearing and grubbing is 95% complete. There have been 9 box culvert extensions put into place. There is currently water & fiber relocation underway. Excavation & Fill operations have begun. Milling & Paving completed with new traffic pattern.

July 1, 2022

The clearing and grubbing is 95% complete.  Six box culvert extensions have been completed. Fiber relocation is currently underway. Excavation & fill operations have begun. Milling & paving is to begin  soon.

May 31, 2022

The clearing and grubbing has started. There have been four box culvert extensions put into place. There is currently fiber relocation underway. Temporary slope stabilization has also taken place.  Stripping topsoil from excavation areas.

April 27, 2022

The clearing and grubbing has started. There have been four box culvert extensions put into place.  There is currently fiber relocation underway.· Temporary slope stabilization has also taken place.

 

Timeline

1.  Phase 1

  • SR63 Northbound (Left) side Campbell and Claiborne
    • Grading-> utility relocates -> drainage features construction -> filling -> paving
    • Beginning March 2022 until October 2023

2. Phase 2

  • SR63 Southbound (right) side Campbell and Claiborne 
    • Utility relocates -> drainage features
      • Beginning April 2022 until October 2023
         
    • Traffic switch -> grading -> drainage features -> paving
      • October 2023 until July 2025
         
    • Final Dmix and striping
      • July 2025 until September 2025