State Route 332 (Concord Road) Widening

Knox County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. The widening of State Route 332 (Concord Road) is currently in the construction phase.

Let to Contract:            10/5/2018
Contractor:                    SUMMERS-TAYLOR, INC.
Bid Price:                        $10,192,277.64
Est. Completion Date: Fall 2021
 

Project Updates:

December 7, 2020

Bridgepoint has laid out the storm drainage system for Phase 2, and Whaley has begun pipe and structure install. The signal and lighting subcontractor began installing decorative lighting along the western alignment. Demolition for the existing structure over the Norfolk-Southern railroad continued. Whaley is within a foot of final sub-grade for the proposed roadway for Phase 2. A plans revision was received and sent to the contractor to change the footer from predrilled piles to 4 drilled shafts for Bent 1, Phase 2.

November 10, 2020

Traffic was switched on to the recently constructed Phase 1 of Concord Road on the night of Wednesday, October 7. The signal and lighting subcontractor has continued installing conduit and light pole foundations throughout the project. Demolition for the existing structure over the Norfolk Southern railroad has begun. A plans revision was received and sent to the contractor to change the footer from predrilled piles to four drilled shafts for Bent 1, Phase 2.

October 7, 2020

The contractor has recently completed work on Phase 1 of the construction of the bridge over the Norfolk Southern Railway as well as grading, utility relocations and drainage for Phase 1 construction.  The traffic shift onto the recently constructed Phase 1 of Concord Road will take place the night of Wednesday, October 7th from 8:00 pm to 6:00 am the following morning. The signal and lighting subcontractor has continued installing conduit and light pole foundations throughout the project.

September 10, 2020

The contractor has recently completed work on Phase 1 of the construction of the bridge over the Norfolk Southern Railway as well as grading, utility relocations and drainage for Phase 1. Paving for the remainder of Phase1 will begin this month.  KUB redesigned a portion of their gas line from the beginning of the project to Turker Creek from a 4" line to an 8" line to accomodate future growth. This change was fully funded by the utility.  In excavation for Bent 1, the contractor encountered fissured rock. Excavating below the rock caused a shift in the rock and an unstable back slope. Due to the location and fragile state of a 24" FMS, plans were revised to include a drilled pole footing. The Phase 2 footing is currently being designed to avoid the utility. The new design is planned to utilize 4' drilled shaft piers. 

July 29, 2020

The contractor will be closing a section of Concord Road near the round-a-bout for bridge work. This closure will begin at 7pm and finish at 6am on Wednesday, August 5 and Thursday, August 6, and then again Sunday, August 9 and Monday, August 10. Message boards and detour signage will be in place to inform motorists of this work. 

Monday, July 6, 2020 – Friday, July 31, 2020:

The grading contractor is going to finish grading operations and begin curb and gutter installation from the beginning of the project to Turkey Creek Road. They will also continue grading and paving operations near the First Utility District sewer plant access road. The bridge contractor has poured the bridge deck for Phase 1 construction and will continue bridge work regarding the approach slabs and parapet wall. This work is in preparation of constructing the new western alignment of Concord Road.  

The contractor will also continue installing street light conduit and foundations for both street lights and traffic signals for the project. Out-of-contract communication relocations will be taking place throughout the project site.