Skip to Main Content

Find COVID-19 Information and Resources

State Route 332 (Concord Road) Widening

Knox County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. The widening of State Route 332 (Concord Road) is currently in the construction phase.

Let to Contract:            10/5/2018
Contractor:                    SUMMERS-TAYLOR, INC.
Bid Price:                        $10,192,277.64
Est. Completion Date: Fall 2021
 

Update: July 29, 2020

The contractor will be closing a section of Concord Road near the round-a-bout for bridge work. This closure will begin at 7pm and finish at 6am on Wednesday, August 5 and Thursday, August 6, and then again Sunday, August 9 and Monday, August 10. Message boards and detour signage will be in place to inform motorists of this work. 

Monday, July 6, 2020 – Friday, July 31, 2020:

The grading contractor is going to finish grading operations and begin curb and gutter installation from the beginning of the project to Turkey Creek Road. They will also continue grading and paving operations near the First Utility District sewer plant access road. The bridge contractor has poured the bridge deck for Phase 1 construction and will continue bridge work regarding the approach slabs and parapet wall. This work is in preparation of constructing the new western alignment of Concord Road.  

The contractor will also continue installing street light conduit and foundations for both street lights and traffic signals for the project. Out-of-contract communication relocations will be taking place throughout the project site.