Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW) and Construction. Proposed improvements to State Route 126 (Memorial Boulevard) consist of two roadway projects. Each project status is listed below.
from East Center Street to east of Cooks Valley Road | |
---|---|
ROW Appraisal/Acquisition | underway |
Construction | Forecasted for FY 2023 (pending funding) |
from east of Cooks Valley Road to Interstate 81 | |
Preliminary Design | underway |
ROW Appraisal/Acquisition | Forecasted for FY 2023 |
Construction | Forecasted for FY 2025 |
*All forecasted dates are subject to change.