Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW) and Construction. Proposed improvements to State Route 126 (Memorial Boulevard) consist of two roadway projects. Each project status is listed below.

from East Center Street to east of Cooks Valley Road
ROW Appraisal/Acquisition underway
Construction Forecasted for FY 2023 (pending funding)
from east of Cooks Valley Road to Interstate 81
Preliminary Design underway
ROW Appraisal/Acquisition Forecasted for FY 2023
Construction Forecasted for FY 2025

*All forecasted dates are subject to change.