State Route 115 (US 129) Alcoa Highway Maloney Road to Woodson Drive

Knox County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. Proposed improvements to State Route 115 (US 129/Alcoa Highway), from south of Maloney Road to Woodson Drive, are currently under construction.

Let to Contract: 02/12/2016
Contractor: Charles Blalock & Sons, Inc.
Current Contact Amount: $72,632,055.59
Estimated Completion Date: Winter 2022

Project Update:

July 28, 2022

Final signage installation is taking place.  The contractor has begun moving utilities for ease of access at Wall 14 and 15 at Quiet Side Lane. Temporary soil nail wall is now complete and Wall 15 panels are 80% complete.

July 1, 2022 

Final signage installation is taking place. The contractor has begun moving utilities for ease of access at Wall 14 and 15 @ Quiet Side Lane.

The contractor continues to excavate ahead of Rembco along with the temp soil nail construction. Rembco is onsite and constructing the temporary soil nail wall at Wall 14 and Wall 15.

 May 31, 2022

The contractor is installing final signage. The contractor has begun moving utilities for ease of access at Wall 14 and 15 @ Quiet Side Lane. The contractor started excavation and construction of Wall 14 at Quiet Side Lane.

April 27, 2022

This project has been completed except for final signage installation. The contractor has begun construction on Quiet Side Lane revision. Work has begun on moving utilities for ease of access. The contractor has begun work on the final punchlist.