Roadway Activity Report for TDOT Region 2 (Apr. 16 - 22, 2020)

Roadway Activity Report for TDOT Region 2 (Apr. 16 - 22, 2020)
Thursday, April 16, 2020 | 01:12pm

DISTRICT 27

CUMBERLAND COUNTY I-40 Construction of a truck climbing lane eastbound near MM 339, including grading, drainage, and paving: Construction signs, guardrail (westbound), and portable barrier rail (eastbound) have been installed on I-40. The contractor continues grade work and drainage activities in the median behind portable barrier rail. Motorists should use caution and be aware of construction personnel in the work zone and equipment that will be entering/exiting the roadway. Estimated project completion date is September 2020.

[Charles Blalock and Sons, Inc./Bradley/CNS298]

CUMBERLAND COUNTY I-40 Resurfacing from the SR-101 ramp (LM 18) to east of SR-1 (US-70) (LM 24.6): The I-40 eastbound and westbound bridges at MM 326.5 in Cumberland County will be reduced to one lane during the day from 04/20/20 through 04/23/20. The contractor will be milling and paving at the bridge ends. A temporary closure of the westbound rest area will be required while working on the westbound bridge. THP has been requested to assist with traffic control. Estimated project completion date is October 2020.

[Rogers Group, Inc./Bradley/CNT364]

CUMBERLAND COUNTY Utility Work on SR-1 (WEST AVE.) in both directions from LM 14.17 to LM 14.63: Mobile lane closures will occur in both directions between Stanley Street and just beyond Park Street as crews transition the work zone. Signage, cones, and flaggers will be present between 8 AM to 3 PM with an estimated completion of 04/30/20.

CUMBERLAND COUNTY SR-1 (US-70) Emergency slope stabilization near LM 26.6: Construction signs, portable barrier rail, and temporary traffic signals have been installed. SR-1 (US-70) will be reduced to one lane between Godsey Road and Renegade Mountain Parkway while slope stabilization is in process. Motorists should exercise caution and pay attention to temporary traffic signals as they travel through the work zone.

[Twin K Construction/Bradley/CNT234]

CUMBERLAND COUNTY SR-101 (Peavine Road) Grading, drainage, and paving from Firetower Road to Westchester/Catoosa Boulevard: Motorists should use caution while driving along Peavine Road and be alert for shifts in traffic patterns. The posted speed limit has been reduced from 45 MPH to 35 MPH within the work zone. Paving has resumed and temporary lane closures and/or traffic stoppages may be needed as construction activities continue. Motorists should reduce speed on Peavine Road and be alert for construction personnel/equipment entering and exiting the roadway.  Estimated project completion date is November 2020.

[Rogers Group, Inc./Bradley/CNQ921]

DEKALB AND WARREN COUNTY SR-56 Construction of bridges and paving from south of Warren-Dekalb County (LM 24.5) line to East Bryant St (LM 2.9): The contractor will continue installing concrete box culverts and drainage structures. Grade work and utility work on the new roadway alignment are ongoing. No change in traffic patterns, traffic is still using the existing SR-56. Motorists are advised to use caution and watch for construction equipment adjacent to roadway. Flaggers may be present to move equipment across the roadway, unload equipment, or complete utility work.  Estimated project completion date is May 2022.

[Jones Bros. Contractors, LLC/McMinnville/CNT011]

FENTRESS COUNTY SR-52 Resurfacing (microsurfacing) from SR-296 (LM 17.6) to the Morgan County line (LM 27.9), including bridge deck and expansion joint repair; SR-296 resurfacing (microsurfacing) from SR-28 (US-127) (LM 0) to SR-52 (LM 3); and SR-28 (US-127) resurfacing (microsurfacing) from south of Airport Road (LM 13.3) to near the Old US-127S ramp (LM 16.9): Contractor is scheduled to begin work on 04/20/20. Work will begin on SR-52 at LM 27.82 on repairing the bridge over Clear Fork River. SR-52 will be reduced to one lane for this work. Microsurfacing is scheduled to begin on 05/11/20 on SR-52 from LM 17.6 to 27.9 and on SR-296 from LM 0.00 to 3.00. During this work, the contractor will use a mobile operation and will have the roadway reduced to one lane. Flaggers will be used along with a pace vehicle to control the flow of traffic through the work zone. Motorists are encouraged to use caution in the work zone and watch for equipment and personnel in the roadway. Estimated project completion date is September 2020.

[American Pavements, Inc./Moore/CNU031]

FENTRESS AND OVERTON COUNTY SR-85 Emergency slide repairs at various locations: The contractor continues work on the Overton County side of SR-85 and the road remains closed from LM 17.5 to LM 22.2. This closure will remain in effect until the project completion scheduled for 09/30/20. The Fentress County portion of SR-85 remains open to through traffic. A detour route remains in place for Overton SR-85 and motorists are encouraged to continue using the detour route until the road is opened. Estimated project completion date is September 2020.

[Wright Brothers Construction Company, Inc./Moore/CNT154]

OVERTON COUNTY SR-294 Bridge repair over Big Eagle Creek (LM 1.39): The lane closure at LM 1.39 remains in effect and will last until project completion scheduled for 06/15/20. The contractor has begun work on Phase 2 of the project and a temporary signal system remains in place to allow traffic through the work zone. Motorists are encouraged to use caution and move slowly through the work zone when the signal light allows. RESTRICTIONS: Loads wider than 9.5' should seek alternate route.  Estimated project completion date is June 2020.

[W and O Construction Company, Inc./Moore/CNT243]

OVERTON COUNTY S.I.A. Grading, drainage and paving on Oak Hill Road from Rickman Road to near SR-111: Contractor currently has Oak Hill Road closed to through traffic. Road closure is scheduled to remain in place until project completion on 06/30/20. The closure of Oak Hill Road will begin just past the Tanimura Plant entrance and end at first entrance of Fitzgerald's Plant. During this closure, motorists wishing to access Tanimura Plant should do so from SR-111 side; motorists wishing to access Fitzgerald's should do so from Old SR-42/Rickman Road. A detour route will be in place along SR-293 to allow motorists to bypass Oak Hill Road. Estimated project completion date is June 2020.

[Rogers Group, Inc./Moore/CNT017]

PUTNAM COUNTY Utility Work on SR-135 (S. WILLOW AVE.) in both directions from LM 9.7 to LM 8.4: Lane closures will occur between I-40 and State Street with signage, barrels and cones. Motorists should use caution and be aware of personnel and equipment when traveling through the work zones. Traffic may be reduced to a single lane in some locations from 9 AM to 3 PM, Monday through Friday with estimated completion date of 06/30/20.

PUTNAM COUNTY SR-136 Resurfacing from US-70N (SR-24) (LM 4.15) to north of Whiteaker Springs Road (LM 7): The contractor will be working on concrete sidewalks during the day and overnight. This will result in nightly lane closures Sunday through Thursday each week. Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment. Estimated project completion date is June 2020.

[Rogers Group, Inc./Cookeville/CNT920]

WHITE COUNTY Grading, drainage and paving at Airport Rd. leading up to Upper Cumberland Regional Airport: Construction signs and portable barrier wall have been installed throughout the project. The contractor will be working on grading and drainage work along Technology Drive during this period. Temporary traffic stoppages may be needed as construction progresses. Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment. Estimated project completion date is June 2020.

[Rogers Group, Inc./Cookeville/CNT259]

 

DISTRICT 28

BLEDSOE COUNTY SR-28 Slope stabilization in Bledsoe County near LM 28.8: The contractor is working on SR-28 north from LM 28.7 to 28.9. The roadway will be reduced to one lane controlled by a traffic signal. Large trucks heading South on SR-28, down the mountain are encouraged to use extreme caution. Estimated project completion date is April 2020.

[Twin K Construction/Voiles/CNT924]

BLEDSOE AND SEQUATCHIE COUNTY Resurfacing on SR-30 in Bledsoe County and on SR-8 (US-127) and SR-28 (US-127) in Sequatchie County: During this reporting period, the contractor will be performing resurfacing operations. The roadway will be reduced to one lane during the day while this work is ongoing. Motorists are encouraged to use caution in the work zone and watch for equipment and personnel in the roadway. Estimated project completion date is June 2020.

[Rogers Group, Inc./Voiles/CNT918]

FRANKLIN COUNTY Utility Work on SR-127 (AEDC RD.) in both directions from LM 4.1 to LM 4.5: Intermittent lane closures between the Scenic View Golf Course and Paynes Church Rd. Signage and flaggers will be present, motorists should be aware of personnel and equipment between 9 AM and 3 PM with an estimated completion of 04/30/20.

GRUNDY COUNTY SR-108 Repair of the bridge over Branch (LM 28.2): Work continues on phase one of this project. On 4/16/20 there will be intermittent closures to support a bridge deck pour. For local traffic, Johnson Rd can be used as a detour. Flaggers will be used to assist with the closure. The project will continue to have a temporary traffic signal installed reducing the roadway to one, 10 ft. travel lane. The lane closure will remain until project completion scheduled for 05/31/21. Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment. RESTRICTIONS: Loads wider than 10' should seek alternate route.  Estimated project completion date is May 2021.

[Jamison Construction/Hussein/CNT397]

GRUNDY COUNTY SR-56 Slide repair from LM 25.9 to LM 26.1: Traffic will be reduced to one lane on SR-56 with traffic signals in place while roadway repairs are being completed.  Estimated project completion date is May 2020.

[TDOT/Miner/MAINT]

MARION COUNTY TDOT Contractor on SR-2 (US-41) in both directions at LM 30.9: Traffic is reduced to one lane with traffic signals in place for a slide repair.

MARION COUNTY SR-150 in both directions at LM 4.7: Traffic is reduced to one lane with traffic signals in place for a slide repair.

MARION COUNTY Utility Work on SR-150 (US-41) in both directions from LM 2.98 to LM 11.51: Lane closures will occur along SR-150 with signage, flaggers, barrels and cones. Motorists should use caution and be aware of personnel and equipment when traveling through the work zones. Traffic may be reduced to a single lane in some locations for aerial crossings from 8 AM to 2 PM, with estimated completion date of 05/19/20.

MARION COUNTY SR-2 (US-64, US-72, US-41) Emergency slope stabilization between LM 25.20 and LM 26.40: The contractor will continue to maintain one lane of travel open to traffic with the restriction of all wide loads. At this time, traffic signals are installed and will remain in place until the project is complete. Motorists are encouraged to use caution and be alert to construction personnel and equipment. RESTRICTIONS: Restriction of all wide loads will remain in place until project is complete.

[Dement Construction Company, LLC/Hussein/CNT229]

MARION COUNTY SR-27 Emergency slope stabilization near LM 26.6: The contractor is working on SR-27 from LM 25 to 26. The roadway will be reduced to one lane controlled by a traffic signal. Large trucks heading South on SR-27, down the mountain are encouraged to use extreme caution. Estimated project completion date is July 2020.

[Wright Brothers Construction Company, Inc./Voiles/CNT926]

VANBUREN COUNTY SR-30 Slope stabilization near LM 16.1: The contractor is working on SR-30 north from LM 15.9 to 16.3. The roadway will be reduced to one lane controlled by a traffic signal. Large trucks heading West on SR-30, down the mountain are encouraged to use extreme caution. Estimated project completion date is April 2020.

[Twin K Construction/Voiles/CNT924]

WARREN COUNTY SR-288 Construction of a concrete bulb-tee beam bridge over Collins River (LM 4.97), including grading, drainage and paving: Both lanes of the bridge are now open. Motorists should use caution in the work zone and watch for workers. If necessary, flaggers may be present to complete any remaining work. Estimated project completion date is April 2020.

[Palmertree Construction Company, LLC/McMinnville/CNQ270]

 

DISTRICT 29

BRADLEY COUNTY Utility Work on SR-2 (N. LEE HWY.) southbound from LM 14.91 to LM 15.05: A shoulder and single lane closure will occur between Anatole Ln NW and 56th Street NW. Signage and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 3 PM from 03/23/20 through 04/22/20.

BRADLEY COUNTY Utility Work on SR-312 (HARRISON PK.) westbound from LM 8.11 to LM 8.11: A shoulder and single lane closure will occur between James Avenue and Country Club NW at 1301 Harrison Pike. Signage and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 2 PM on 04/17/20.

BRADLEY COUNTY SR-308 Installation of signals at the intersection of Walker Valley Road (LM 6.3): During this reporting period, the contractor will be making final electrical connections and removing construction signs. This work should occur on the shoulders of SR-308 with minimal impact to traffic. Motorists are advised to use caution in the work zone. Estimated project completion date is April 2020.

[Stansell Electric Company, Inc./Wagner/CNT276]

HAMILTON COUNTY I-24 Replacement of Belvoir Ave. bridge over I-24 and I-24 bridges over Germantown Road near MM 183: The contractor will be shifting I-24 EB and WB traffic toward the outside shoulders and shutting down Belvoir Avenue Bridge in preparation for the bridge demo work. Also, crews will be shifting traffic on North and South Terrace Road (merging taper on inside lanes). This work will require double right lane closures in both directions of I-24 EB and WB between MM 182 and MM 184 and single lane closures along North and South Terrace. These lane closures are scheduled for Monday April 20 (I-24 EB), Tuesday April 21 (I-24 WB), Wednesday April 22 (North and South Terrace Avenue's, and Thursday April 23 (I-24 EB inside single lane closure) in order to install remaining median signage. These closures will occur between 9 PM and 6 AM. Additionally, motorists should be aware of construction vehicles entering and leaving near the Exit 182 off ramp and South Terrace at the Germantown Road intersection. The Belvoir Bridge detour will be in place and motorists should be mindful of detour signage along with reduced 45 MPH speed limit reduction throughout the project corridor along I-24. Estimated project completion date is August 2021.

[Bell and Associates Construction, LP/Blevins/CMGC03]

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: Watch for trucks entering and exiting project. Phase 1 traffic shifts have been implemented. Traffic should expect multiple lane shifts traveling through the interchange. Lane closures will occur Sunday nights through Thursday nights between 9 PM and 6 AM at the following locations: I-75 NB MM 1, I-75 SB MM 3 and I-24 EB MM 184.0 Traffic pacing may occur throughout the interchange Sunday nights through Thursday nights between 9 PM and 6 AM. Additionally, there may intermittent shoulder closures at various locations for access to the median and roadside areas. The speed limit has been reduced to 45 MPH throughout the interchange.

[C.W. Matthews Contracting Company, Inc./Blevins/DB1801]

HAMILTON COUNTY TDOT Contractor on I-75 in both directions from MM 4 to MM 6: Starting on 04/20/20 and extending for three to four weeks, geotechnical crews will be conducting drilling operations during daytime hours to evaluate the soil conditions in this area for a future improvement project. A majority of this work will take place off of the roadway but may require some short-term shoulder closures. Worker will be present in this area.
[S and ME/Maintenance/MAINT]

HAMILTON COUNTY US-27 (I-124) Widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: Work on this project continues with activities occurring on the west side of southbound US-27. Motorists should be alert for construction vehicles entering and exiting the area along the access ramps for eastbound and westbound M. L. King Boulevard. The speed limit for the access ramp is 35 MPH. The southbound ramp from W. Main St. to southbound US-27 has been temporarily closed and will remain so until further notice. Detours are posted. Motorists should pay close attention to the detour signage posted. The speed limit on US-27 in the construction zone remains 45 MPH. Weather permitting; the contractor may implement temporary lane/shoulder closures on weeknights between the hours of 7 PM and 6 AM. At least one lane will remain open in each direction on US-27. RESTRICTIONS: I-124 (US-27) Northbound Exit 1C 4th St Off Ramp: No oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1C 4th St Of Ramp: On oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1B East Martin Luther King Blvd. Off Ramp: No oversized/over dimensional loads; I-124 (US-27) Southbound On Ramps from Martin Luther King Blvd.: No oversized/over dimensional loads.

[Dement Construction Company, LLC/Micka/CNP230]

HAMILTON COUNTY TDOT Contractor on I-24 eastbound from MM 179 to MM 171: On 04/16/20 and 04/17/20, surveying crews will have a mobile operation on the shoulder as they perform survey work on I-24.

HAMILTON COUNTY TDOT Contractor on SR-8 (US-127/SIGNAL MOUNTAIN BLVD.) in both directions from LM 14 to LM 16.5: Beginning on 04/01/20, geotechnical contract crews will begin conducting drilling operations to evaluate the roadway for a future improvement project. These operations are estimated to continue on weekdays during daytime hours for approximately five weeks. The contractor will begin work at 9 AM each day and work as long as possible. There are ten sites between SR-27/Suck Creek Rd. to past Shoal Creek Rd. that the contactor will be investigating during this time period. During drilling operations, the roadway will be temporarily reduced to one lane. Drivers are encouraged to be patient and alert as they travel through the work zone. Estimated project completion date is May 2020.

[S and ME/Maintenance/MAINT]

HAMILTON COUNTY TDOT Maintenance on SR-29 (US-27) in both directions at LM 29.4: On Thursday and Tuesday of this reporting period, maintenance crews will have the shoulder and at least one lane closed in each direction

HAMILTON COUNTY TDOT Maintenance on SR-8 (SIGNAL MOUNTAIN BLVD.) in both directions at LM 14.3: Due to the road being washed out, traffic has been reduced to one lane in each direction at this location.

HAMILTON COUNTY Utility Work on SR-2 (BROAD ST.) southbound from LM 6.31 to LM 6.31: A shoulder and single lane closure will occur between W. 32nd Street and Watson Street at 3201 Broad Street. Signage and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 3 PM from 04/13/20 through 04/24/20.

HAMILTON COUNTY Utility Work on SR-319 (HIXSON PK.) in both directions from LM 8.14 to LM 8.14: A shoulder and single lane closure will occur between Gold Crest Drive and Big Ridge Road at 6448 Hixson Pike. Signage and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 3 PM from 04/16/20 through 04/17/20.

HAMILTON COUNTY Utility Work on SR-319 (HIXSON PK.) eastbound from LM 7.16 to LM 7.16: A shoulder and single lane closure will occur between Templeton Lane and Cassandra Smith Road at 59331 Hixson Pike. Signage and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 3 PM from 04/20/20 through 05/01/20.

HAMILTON COUNTY Cleaning of the McCallie Tunnel on SR-2 (US-64, US-11), the Stringers Ridge Tunnel on SR-8 (US-127), and the Bachman Tubes on SR-8 (US-76, US-41): On 04/15/20 (between 8 PM - 6 AM), the McCallie tunnels will be cleaned using a flagging operation. Later that night, the Stringers Ridge tunnels will be cleaned using a signed detour. On 04/16/20 (between 8 PM - 6 AM), there will be a tunnel cleaning operation at the Bachman Tubes (East Ridge tunnels) supported by a signed detour.  Estimated project completion date is June 2020.

[Diamond Specialized, Inc./Micka/CNT196]

HAMILTON COUNTY SR-317 (Apison Pike) Improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: All routes are open with only intermittent flagging for material, equipment, and tree cutting activities. Estimated project completion date is June 2025.

[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]

MCMINN COUNTY SR-30, Grading, drainage and paving on SR-30 from Jackson Street to east of Knight Road in Athens: There will be temporary traffic shifts to accommodate milling and final paving. This will continue for a week or so until paving is complete and traffic is in its final configuration. Motorists should be alert to changing conditions during this paving process. It is expected that the WB SR-30 traffic will be in its final alignment before the end of this reporting period. Eastbound traffic will follow.

[Talley Construction Company, Inc./Micka/CNR078]

MEIGS COUNTY SR-58 Repair of the bridge over Hiwassee River (LM 5.22): During this report period, the contractor will have the roadway reduced to one lane controlled by temporary traffic signals. Additional flaggers will be on site as needed.

[Mid-State Construction Company, Inc./Osbonlighter/CNT103]

POLK COUNTY SR-30 Resurfacing from Greasy Creek Road (LM 13.1) to north of US-64 (US-74, SR-40) (LM 17.17): During this reporting period, the contractor will be working on resurfacing operations on SR-30. Daily lane closures will be in effect on SR-30 from 8 AM to 5 PM. Motorists are advised to expect long delays in the work zone during these times and seek an alternate route when possible.  Estimated project completion date is October 2020.

[Talley Construction Company, Inc./Wagner/CNU022]

POLK COUNTY SR-40 (US-64) Repair of bridges over North Potato Creek (LM 26.93): During this reporting period, the contractor will be working on the installation of a new concrete overlay on the westbound bridge and new approach slabs on the eastbound bridge. Traffic is reduced to one lane in each direction on US-64 for the duration of this work. Motorists are advised to reduce speed and use caution in the work zone due to reduced lane widths. RESTRICTIONS: 12 ft. maximum width LM 26.93 Westbound 14 ft. maximum width LM 26.93 Eastbound.

[Jones Bros. Contractors, LLC/Wagner/CNT062]

POLK COUNTY Boanerges Church Road construction of a bridge over Old Fort Creek: During this reporting period, the contractor will be working to install portions of the new bridge. This work will occur weather permitting. Boanerges Church Road is closed to all traffic for the duration of construction. Detour signs are posted diverting traffic around the closure onto SR-313 and US-411.  Estimated project completion date is October 2020.

[Summers-Taylor, Inc./Wagner/CNT279]

RHEA COUNTY SR-30 Grading, drainage and paving from west of New Union Road/White Oak Road (LM 12.6) to Sky Drive (LM 12.9): During this report period, the contractor will be performing grading & drainage operations along SR-30, New Union Rd & White Oak Dr. During this current phase, a new traffic pattern will be in place at SR-30; SR-30 will be shifting from the current alignment to the new alignment. The intersections of White Oak Drive and New Union Road will be shifted to the new portion of SR-30. Flaggers will be on-site to assist with heavy equipment entering and exiting existing roadways.

[Twin K Construction/Osbonlighter/CNT073]

RHEA COUNTY Grading, drainage, construction of bridges, paving and signals on a S.I.A. route serving Nokian Tyres: There will be a lane shift set up for all NB & SB SR-29 traffic in front of the proposed Nokian Tyres SIA entrance. Additionally, there could be lane closures and/or traffic shifts to support construction at the Manufacturers Rd/SR-29 intersection. Estimated project completion date is October 2022.

[Dement Construction Company, LLC/Micka/CNU014]

 

REGION WIDE

REGION 2 TDOT Maintenance drainage work: There will be possible short-term lane and shoulder closures at various locations in Region 2 in order to clean rock and debris from ditches on an as-needed basis. One lane will be maintained at all times.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 TDOT Maintenance pothole repair and pavement patching: There will be possible short-term emergency lane closures at various locations in Region 2 in order to repair potholes and patch pavement on an as-needed basis. Depending on location and severity these repairs may be done during the day or at night. In addition to performing the work, regional Operations crews will also provide traffic control.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 On-call guardrail repairs and new guardrail installation on various Interstate and State Routes: The contractor may have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly from 7 PM to 6 AM Sundays through Thursdays and daily on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed. Estimated project completion date is June 2020.

[Cumberland Guardrail, Inc./McMinnville/CNT114]

REGION 2 Preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures in order to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. Work hours are 9 AM to 3:30 PM. At least one travel lane will remain open to traffic at all times. Flaggers will assist with traffic control as needed.  Estimated project completion date is January 2023.

[NABCO Electric Company, Inc./Osbonlighter/CNT354]

REGION 2 Sweeping and drain cleaning on various interstate and state routes: There will be a drain cleaning operation in Hamilton County along I-75 (MM 3 -MM 12) that will involve closing the inside lane for one up to mile intervals. Additionally, a sweeping operation supported by mobile lane closures will happen throughout the region on interstates & selected state routes. Both operations will happen Sunday - Thursday (9 PM -6 AM). Estimated project completion date is April 2020.

[Blevins Enterprises, Inc./Micka/CNS320]

REGION 2 On-call cable barrier repair on various Interstate and State Routes: The contractor may have short term shoulder closures in order to perform cable rail repair. Both travel lanes will remain open to traffic at all times on the interstate during any work that is performed. Estimated project completion date is December 2020.

[LU, Inc./McMinnville/CNT292]

 

RESTRICTIONS

OVERTON COUNTY - CNT243: Loads wider than 9.5' should seek alternate route.

GRUNDY COUNTY - CNT397: Loads wider than 10' should seek alternate route.

MARION COUNTY - CNT229: Restriction of all wide loads will remain in place until project is complete.

HAMILTON COUNTY - CNP230: I-124 (US-27) Northbound Exit 1C 4th St Off Ramp: No oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1C 4th St Of Ramp: On oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1B East Martin Luther King Blvd. Off Ramp: No oversized/over dimensional loads; I-124 (US-27) Southbound On Ramps from Martin Luther King Blvd.: No oversized/over dimensional loads.

POLK COUNTY - CNT062: 12 ft. maximum width LM 26.93 Westbound 14 ft. maximum width LM 26.93 Eastbound.

Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity.

Information in this report is provided to the Department of Transportation by the contractors. Most work is weather dependent and subject to change due to inclement weather. All times are local.

From your desktop or mobile device, get the latest construction activity and live streaming SmartWay traffic cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any land-line or cellular phone for travel information, or follow us on Twitter at www.twitter.com/TN511 for statewide travel or Chattanooga area alerts @Chattanooga511 or any of TDOT's other Twitter pages. As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for your destination. Drivers should never tweet, text, or talk on a cell phone while behind the wheel.

In 2016, the Tennessee Department of Transportation lost three workers in the line of duty. All three were struck by passing motorists. Those tragedies bring the total number of TDOT lives lost to 112. We don't want to lose another member of our TDOT family. We're asking you to WORK WITH US. To learn more, go to the website at https://www.tn.gov/tdot/work-with-us/.

###