Weekly Roadway Activity Report for TDOT Region 2 (Jun. 6 - 12, 2019)

Thursday, June 06, 2019 | 12:33pm

DISTRICT 27

CUMBERLAND COUNTY I-40 Resurfacing from near the parking area (MM 306.34) to east of Exit 311 (MM 311.12): Construction signs have been installed. The contractor has finished paving. Remaining work includes rumble strips, shoulder stone, fog sealing shoulders, delineators, and permanent pavement marking which will require night time lane closures. State trooper assistance will be requested. Working hours will be from 7 PM to 6 AM. During working hours, the speed limit will be reduced from 70 mph to 60 mph using digital speed limit sign assemblies.  Estimated project completion date is August 2019.

[Rogers Group, Inc./Bradley/CNS325]

CUMBERLAND COUNTY Utility Work on SR-28 (S. MAIN ST.) in both directions from LM 13 to LM 9: Intermittent lane closures for utility work along South Main Street from Hayes Street to Wild Plum Lane. Signage and flaggers will be used. Motorists should use caution. Work will take place from 05/31/19 through 06/15/19 between 9 AM to 3 PM.

CUMBERLAND COUNTY SR-101 (Peavine Road) Grading, drainage, and paving from Firetower Road to Westchester/Catoosa Boulevard: As grade work progresses, motorists should be alert for shifts in traffic patterns to allow for construction activities. The posted speed limit has been reduced from 45 mph to 35 mph within the work zone. Temporary lane closures and traffic stoppages may be needed to support ongoing work. Lane and/or road closures may be needed within Fairfield Glade to allow installation of storm drain and relocation of utilities. Motorists should reduce speeds on Peavine Road and be alert for construction personnel/equipment entering and exiting the roadway.  Estimated project completion date is November 2020.

[Rogers Group, Inc./Bradley/CNQ921]

DEKALB AND WHITE COUNTY US-70 (SR-26) Resurfacing from west of Brent Taylor Road (LM 20.26) in DeKalb County to east of Creekside Place (LM 9.82) in White County: The contractor will be installing construction signs and resurfacing during this report period. Motorists should expect temporary lane closures during this time and be alert of all construction personnel while traveling through the work zone. Estimated project completion date is September 2019.

[Rogers Group, Inc./Cookeville/CNT024]

FENTRESS COUNTY SR-28 (US-127) Bridge repair over the Wolf River (LM 29.4): The contractor is scheduled to start work on 06/10/19. The contractor will install a temporary signal system and SR-28 will be reduced to one lane for the duration of the work. Motorists are encouraged to use caution in the work zone and watch for construction equipment. RESTRICTIONS: 10 foot maximum width. Estimated project completion date is August 2019.

[Jamison Construction/Moore/CNT095]

FENTRESS COUNTY SR-52, SR-154 and SR-297 Resurfacing (microsurfacing): The contractor will be on site performing paving operations. During the course of construction the contractor will keep one lane of traffic open at all times and will use flaggers to facilitate traffic flow. The routes covered in the project are SR-52 from east of US-127 (SR-28) (LM 13.60) to SR-296 (LM 17.62), SR-154 from north of Louvaine Road (LM 6.25) to the Pickett County line (LM 13.48), and SR-297 from SR-154 (LM 0.00) to the Scott County line (LM 8.79). Motorists are encouraged to use caution and watch for construction equipment in the roadway.  Estimated project completion date is June 2019.

[Hudson Construction Company/Moore/CNS098]

FENTRESS COUNTY Vines Ridge Road over Big Laurel Creek Bridge Replacement:   Vines Ridge Road remains closed at LM 1.06 and will remain closed until new bridge is constructed and in place. Approximate date for the length of closure is 07/31/19. Motorists should seek alternate route around Vines Ridge Road near location of construction. Estimated project completion date is November 2019.

[Twin K Construction/Moore/CNT901]

FENTRESS AND OVERTON COUNTY SR-85 Emergency slide repairs at various locations: The roadway is closed from LM 18.4 to LM 22.4 in Overton county. SR-85 is also closed in Fentress County between LM 5.75 and 8.00. The contractor is continuing work on this contract in the two areas listed where the roadway is closed. Motorists are encouraged to use caution and seek alternate routes. Estimated project completion date is November 2019.

[Wright Brothers Construction Company, Inc./Moore/CNT154]

JACKSON COUNTY SR-53 Resurfacing from the Smith County line (LM 0) to north of New Salem Road (LM 9.02), including repair of the bridge over Flynn's Creek (LM 7.84): The contractor has scheduled work to begin on 06/10/19. During the course of work, SR-53 over Flynn's Creek will be closed to all traffic for a period of two weeks. Detour route is SR-290 from SR-53 to SR-56.  Estimated project completion date is September 2019.

[Rogers Group, Inc./Moore/CNT031]

PUTNAM COUNTY I-40 near MM 296 Bridge repair on Rocky Point Road over I-40: Rocky Point Road bridge at LM 10.08 over I-40 will be closed due to bridge repairs and re-open in June 2019. A detour is in place to guide motorists around the bridge closure. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.  Estimated project completion date is August 2019.

[Mid-State Construction Company, Inc./Cookeville/CNS355]

PUTNAM COUNTY I-40 WB Resurfacing and bridge repair from Falling Water River (MM 291) to the ramp from US-70N (SR-24) (MM 301): Nightly lane closures will occur Monday through Thursday between 7 PM to 6 AM. The contractor is planning to begin milling operations. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone. Estimated project completion date is August 2019.

[Rogers Group, Inc./Cookeville/CNS328]

PUTNAM COUNTY SR-111 (LM 4.08) at I-40 (MM 288) Signal installation on east and westbound ramps in Cookeville, including grading, drainage and paving: The contractor will be paving SR-111 northbound and southbound and installing new traffic signals. This will result in nightly lane closures from 8 PM to 6 AM each night. New traffic signals will be set to flashing for 7 days after installation. Due to widening of the I-40 westbound off-ramp, right turns from the westbound off-ramp onto SR-111 North are not allowed during construction. Motorists are advised to use an alternate route during this time. If they must travel through this area, they will experience long delays, as the left turn movement will be the only one allowed. Motorists should use caution when traveling through the work zone.  Estimated project completion date is June 2019.

[Rogers Group, Inc./Cookeville/CNS279]

PUTNAM COUNTY TDOT Maintenance on I-40 in both directions from MM 267 to MM 302: TDOT Maintenance will have intermittent single lane closures as required for patching potholes on I-40 both directions from MM 267 to MM 302 from 8 AM until 4 PM 06/10/19 through 06/13/19.

PUTNAM COUNTY Utility Work on SR-136 (N. WASHINGTON AVE.) in both directions from LM 4.5 to LM 5.4: Utility work will take place between 4th St. & 6th St. Signage, barrels, and cones will be present during this work. Motorists should use caution and be aware of flaggers. Work should continue through 06/28/19 between 9 AM and 3 PM.

WHITE COUNTY SR-1 (US-70) Bridge repair over the Calfkiller River (LM 9.35) in Sparta: Calfkiller Bridge in Sparta is in the first of three permanent phases of lane closures. These phases will affect between Wilson Street and Church Street. This first phase will restrict the west bound traffic to one lane, while retaining the left turn lane and two lanes of traffic in the east bound direction. This phase is expected to be completed by mid-June 2019. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone. Estimated project completion date is September 2019.

[Southern Constructors, Inc./Cookeville/CNT110]

 

DISTRICT 28

BLEDSOE COUNTY SR-101 Bridge repair over Bee Creek (LM 8.98): Work on this project is underway. For the safety of the traveling public, the bridge will be reduced to one 10 foot lane and controlled with temporary signals. RESTRICTIONS: 10 foot lane. Estimated project completion date is September 2019.

[Jamison Construction, LLC/Voiles/CNS266]

COFFEE COUNTY I-24 Resurfacing from Bedford County (MM 96) to Noah Fork Creek (MM 101) including bridge deck repair: The contractor has completed the paving process of the roadway surface work and will begin installation of rumble strips, thermo pavement markings and snowplowable markers. Work will continue each Sunday thru Friday from 7 PM to 6 AM each night. There will be lane closures during all work processes. Motorists should use extreme caution. Law enforcement and safety personnel will be present.  Estimated project completion date is August 2019.

[Rogers Group, Inc./Hussein/CNS332]

COFFEE COUNTY Utility Work on SR-53 (WOODBURY HWY.) in both directions from LM 4.23 to LM 8.72: Intermittent lane closures for utility work along Woodbury Hwy from near Gladys Lane to near Pomroy Road. Signage and flaggers will be used. Motorists should use caution. Work will take place from 05/29/19 through 09/05/19 between 9 AM to 3 PM.

GRUNDY COUNTY SR-56 (US-41) Resurfacing from the Marion County line (LM 0) to SR-56 (LM 5.5): During this reporting period, the contractor continues the resurfacing process of the roadway. Temporary lane closures are possible to support these activities.  Estimated project completion date is September 2019.

[Tinsley Asphalt, LLC /Hussein/CNT085]

MARION COUNTY Utility Work on SR-27 (US-HWY. 72) in both directions from LM 4.67 to LM 7.52: Mobile lane closure for aerial work will take place along Hwy 27 between Hwy 41 at East Valley Rd. Motorists should use caution and be aware of flaggers. From 04/23/19 to 07/01/19 between 6 AM and 4 PM

MARION COUNTY SR-156 over Running Water Creek (LM 25.58) bridge rehabilitation: SR-156 is reduced to one 10 foot lane across Running Water Creek Bridge and controlled with a temporary traffic signal while the bridge is repaired. Please use caution when traveling through this area. On Thursday, June 6th and Friday, June 7th the contractor will close the bridge intermittently to set beams. The contractor will have flaggers to control traffic and a detour will be marked. The contractor will only close the bridge for 15 minutes at a time. RESTRICTIONS: 10 foot lane. Estimated project completion date is October 2019.

[Mid-State Construction Company, INC/Voiles/CNS905]

MARION COUNTY US-41 (US-64, US-72, SR-2) Emergency slope stabilization between LM 25.20 and LM 26.40: Work on this project has begun. This project consists of slope stabilization at four separate sites. The contractor will be working on clearing and grubbing in various locations at this time. Traffic signals installed for previous maintenance job remain in the same location until the contractor decides which site they will work on first. Estimated project completion date is November 2019.

[Dement Construction Company, LLC/Hussein/CNT229]

VANBUREN COUNTY SR-111 Resurfacing from south of Connell Road (LM 17.8) to the White County line (LM 19.5): During this reporting period, the contractor will have one lane closed in either the Southbound or Northbound direction to install pavement markings and permanent signage. Estimated project completion date is August 2019.

[Tinsley Asphalt, LLC /Parnham/CNT122]

WARREN COUNTY Utility Work on SR-288 (HENNESSEE BRIDGE RD.) eastbound from LM 1.22 to LM 4.75: Utility work will take place between Chandler Rd. and Old Rock Island Rd. Signage and flaggers will be used. Motorists should use caution. From 05/20/19 through 07/05/19 between 9 AM and 3 PM

WARREN COUNTY SR-288 Construction of a concrete bulb-tee beam bridge over Collins River (LM 4.97), including grading, drainage and paving: The bridge is currently reduced to one 10.5-foot lane to allow the contractor to construct the new bridge. While the bridge is down to one lane, traffic will be maintained and controlled by a temporary signal. Motorists should expect periodic delays and use caution in the work zone. RESTRICTIONS: 10.5-foot max width. Estimated project completion date is September 2019.

[Palmertree Construction Company, LLC/Parnham/CNQ270]

WARREN COUNTY SR-8 over Collins River (LM 8.14) Bridge Repair: The bridge is currently reduced to one 11-ft. lane to allow the contractor to repair the existing bridge. While the bridge is down to one lane, traffic will be maintained and controlled by a temporary signal for the safety of the traveling public. Motorists should expect periodic delays and use caution in the work zone. RESTRICTIONS: 11-ft max width. Estimated project completion date is August 2019.

[Jamison Construction/Parnham/CNS254]

 

DISTRICT 29

BRADLEY AND MCMINN COUNTY SR-306 Miscellaneous safety improvements from SR-60 (LM 0) to the Meigs County line (LM 8.58), and on SR-307 from Burnett Road (LM 2.18) to Old Mount Harmony Road (LM 6.07): During this reporting period, the contractor will be working on SR-306 and SR-307. Intermittent lane closures will be possibly Monday thru Friday 8 AM to 5 PM.  Estimated project completion date is July 2019.

[Superior Pavement Markings, Inc./Cleveland/CNS341]

BRADLEY AND MCMINN COUNTY SR-312 (Bradley Co.) Miscellaneous safety improvements from the Hamilton Co. Line (LM 0.00) to Quill Dr. (LM 5.27); US-11 (SR-2) (McMinn Co.) miscellaneous safety improvements from Sanford Rd. (LM 4.05) to Chapel Rd. (LM 12.32): No work will be performed on this project during this reporting period. Estimated project completion date is June 2019.

[Superior Traffic Control, LLC/Cleveland/CNS287]

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: Crews will continue surveying and spotting utilities at various locations throughout the interchange. Shoulders may be closed at these locations between 9 AM and 3 PM. Additionally, a hauling operation will take place requiring a single left lane closure on I-75 SB at MM 2 and a single left lane closure on I-24 EB at MM 185. These lane closures will occur the following nights: 06/6/19 between 9 PM and 6 AM and 06/9/19 to 06/13/19 between 9 PM and 6 AM. Haul trucks will be entering and exiting the interstate at these locations. Finally, a resurfacing operation on the I-75 SB bridge over I-75 NB to I-24 WB ramp is planned for 06/12/2019 or 06/13/2019. This operation will extend the left lane closure at I-75 SB MM 2 that will already be in place.

[C.W. Matthews Contracting Company, Inc./Chattanooga 2922/DB1801]

HAMILTON COUNTY US-27 (I-124) Widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: Work on this project continues with activities occurring on the west side of southbound US-27. Motorists should be alert for construction vehicles entering and exiting the area along the access ramps for east and westbound M. L. King Boulevard. The speed limit for the access ramp is 35 MPH. The southbound ramp from W. Main St. to southbound US-27 has been temporarily closed and will remain so until further notice. Detours are posted. Motorists should pay close attention to the detour signage posted. The speed limit on US-27 in the construction zone remains 45 MPH. Weather permitting; the contractor may implement temporary lane/shoulder closures on weeknights between the hours of 7 PM and 6 AM. At least one lane will remain open in each direction on US-27. Detours for closures will be posted. RESTRICTIONS: I-124 (US-27)Northbound Exit 1C 4th St Off Ramp: No oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1A-B Martin Luther King Blvd. Off Ramp: No oversized/over dimensional loads; I-124 (US-27) Southbound On Ramps from Martin Luther King Blvd.: No oversized/over dimensional loads. Estimated project completion date is January 2020.

[Dement Construction Company, LLC/Micka/CNP230]

HAMILTON COUNTY TDOT Maintenance on SR-319 (DUPONT PKWY.) northbound from LM 2.0 to LM 2.2: Region 2 Bridge Repair - On Monday 06/10/19, SR-319 will be reduced to one lane for bridge maintenance between the hours of 8:30 AM and 3:30 PM between mile markers 2.0 and 2.2. The north bound lanes of travel will be reduced to one lane. Traffic control will be in place.

HAMILTON COUNTY TDOT Maintenance on SR-319 (DUPONT PKWY.) southbound from LM 2.0 to LM 2.2: Region 2 Bridge Repair - On Tuesday 06/11/19, SR-319 will be reduced to one lane for bridge maintenance between the hours of 8:30 AM and 3:30 PM between mile markers 2.0 and 2.2. The south bound lanes of travel will be reduced by one lane. Traffic control will be in place.

HAMILTON COUNTY SR-111 Bridge repair over SR-29 (US-27): During this report period, the contractor will have one lane closed in each direction of SR-111 while performing bridge repairs. The contractor will also be closing one lane in each direction on SR-29 as it passes under SR-111. One lane in each direction shall remain open at all times.  Estimated project completion date is October 2019.

[Mid-State Construction Company, Inc./Chattanooga 2922/CNT096]

HAMILTON COUNTY Cleaning of the McCallie Tunnel on US-11 (US-64, SR-2), the Stringers Ridge Tunnel on US-127 (SR-8), and the Bachman Tubes on US-41 (US-76, SR-8): No tunnel cleaning this reporting period. Estimated project completion date is June 2019.

[Diamond Specialized, Inc./Micka/CNS206]

HAMILTON COUNTY SR-148 (Scenic Highway) Slide repair between LM 2.3 (Sanders Road) and LM 2.5 (Linear Lane): During this report period, the contractor will have one lane closed while they perform stabilization operations to the slide area. One lane of traffic shall remain open at all times. Estimated project completion date is June 2019.

[Wright Brothers Construction Company, Inc. /Chattanooga 2922/CNT152]

HAMILTON COUNTY SR-58 Miscellaneous safety improvements at the intersection of SR-312 (Birchwood Pike) (LM 15.70): The contractor will be completing various safety improvements at the intersection of SR-58 & Birchwood Pike Monday thru Saturday between 5 AM and 6 PM. No southbound traffic restrictions will be allowed between 5 AM and 9 AM. No northbound traffic restrictions will be allowed between 3 PM and 6 PM. Flaggers will assist with traffic control as needed. Estimated project completion date is June 2019.

[Talley Construction Company, Inc. /Chattanooga 2922/CNS273]

MCMINN COUNTY SR-30, Grading, drainage and paving on SR-30 from Jackson Street to east of Knight Road in Athens: Traffic along SR-30 is in its phase two configuration (all traffic on the former eastbound side, providing one lane in each direction plus turning lanes at critical intersection & businesses.) The intersection of SR-39/SR-30 has a different configuration. The traveling public should be alert. Estimated project completion date is April 2020.

[Talley Construction Company, Inc./Micka/CNR078]

MCMINN COUNTY I-75 Resurfacing from north of County Road 267 (MM 55) to the Monroe County line (MM 60): During this reporting period, the contractor will be working on permanent striping and installation of snowplowable pavement markers. Lane closures will be possible on I-75 from 7 PM to 6 AM Sunday through Thursday. THP will be on site to assist with traffic control. Estimated project completion date is August 2019.

[Rogers Group, Inc./Cleveland/CNS330]

MCMINN COUNTY SR-2 (US-11) Resurfacing from south of Rocky Mount Road (LM 12.18) to north of Haines Road (LM 14.8): During this reporting period, the contractor will have nightly lane closures on SR-2 (US-11) between the hours of 7 PM and 6:30 AM Sunday thru Thursday nights for resurfacing operations. THP will be on site to assist with traffic control. Estimated project completion date is August 2019.

[Wright Brothers Construction Company, Inc./Cleveland/CNT027]

MCMINN COUNTY SR-305 Resurfacing from west of US-11 (SR-2) (LM 2.86) to west of I-75 (LM 5.00): Work on this project is complete. Intermittent traffic disruptions are possible Monday to Friday 8 AM to 5 PM as the contractor removes construction signs in the area. Estimated project completion date is June 2019.

[Rogers Group Inc./Cleveland/CNS187]

MEIGS COUNTY SR-58 Repair of bridge over Hiwassee River (LM 5.22): During this report period, the contractor will have the roadway reduced to one lane and controlled by temporary traffic signals. Additional flaggers will be on site as needed. Estimated project completion date is September 2019.

[Mid-State Construction Company, Inc./Chattanooga 2922/CNT103]

POLK COUNTY TDOT Maintenance on SR-30 both directions at LM 13.5: The road is currently reduced to one lane and controlled with temporary signals due to a roadway settlement.

[Maintenance/MAINT]

POLK COUNTY SR-40 (US-64) Repair of bridges over North Potato Creek (LM 26.93): During this reporting period, the contractor will be working to remove the existing bridge decks on both the eastbound and westbound bridges. SR-40 (US-64) is reduced to one lane in each direction for the duration of this work. RESTRICTIONS: No loads wider than 12 ft. are allowed at LM 26.93 eastbound and westbound. Estimated project completion date is April 2020.

[Jones Bros. Contractors, LLC/Cleveland/CNT062]

POLK COUNTY SR-40 (US-64, US-74) Resurfacing from west of SR-30 (LM 9.8) to near Little Caney Creek Bridge (LM 13): During this reporting period, the contractor will have lane closures on Tuesdays and Wednesdays between 8 AM ad 5:30 PM for the installation of striping and snowplowable pavement markers. Motorists should be aware of flaggers in the work zone assisting with traffic control. Estimated project completion date is June 2019.

[Talley Construction Company, Inc./Cleveland/CNT090]

POLK COUNTY US-64 (SR-40) Construction of a concrete bulb-tee beam bridge over Branch and TOHA Old Line railroad (LM 24.85), including grading, drainage and paving: Intermittent lane closures will be possible Monday thru Friday 8 AM to 5:30 PM as the contractor works on punch list items. Motorists should be aware of flaggers in the roadway assisting with traffic control. Estimated project completion date is June 2019.

[Talley Construction Company, Inc./Cleveland/CNQ900]

RHEA COUNTY TDOT Maintenance on SR-68 (WASSOM MEMORIAL HIGHWAY) in both directions at LM 5.5: The roadway is reduced to one lane and signalized 24/7 due to roadway settlement.

[TDOT Maintenance/Maintenance/MAINT]

RHEA COUNTY SR-30 Grading, drainage and paving from west of New Union Road/White Oak Road (LM 12.6) to Sky Drive (LM 12.9): During this report period, the contractor will be performing grading and drainage operations along SR-30 and New Union Rd. During the initial phase traffic will be maintained on SR-30, White Oak Dr. and New Union Rd. in its current pattern. Flaggers will be on-site to assist with heavy equipment entering & exiting existing roadways.  Estimated project completion date is November 2019.

[Twin K Construction/Chattanooga 2922/CNT073]

RHEA COUNTY SR-30 Miscellaneous safety improvements from near SR-443 (LM 4.1) to Maple Creek Drive (LM 7.75): Possibility of lane or shoulder closures supporting construction along SR-30 (Monday through Friday from 6 AM to 8 PM).  Estimated project completion date is July 2019.

[Superior Traffic Control, LLC/Inc./Micka/CNT075]

 

REGION WIDE

REGION 2 TDOT Maintenance drainage work: There will be possible short-term lane and shoulder closures at various locations in Region 2 in order to clean rock and debris from ditches on an as-needed basis. One lane will be maintained at all times.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 TDOT Maintenance pothole repair and pavement patching: There will be possible short-term emergency lane closures at various locations in Region 2 in order to repair potholes and patch pavement on an as-needed basis. Depending on location and severity these repairs may be done during the day or at night. In addition to performing the work, regional Operations crews will also provide traffic control.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 On-call guardrail repair and new guardrail installation on various interstate and state routes: The contractor may have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly from 7 PM to 6 AM Sundays through Thursdays and daily on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed.  Estimated project completion date is June 2019.

[Cumberland Guardrail, Inc./Parnham/CNS928]

REGION 2 Preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures in order to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. Work hours are 9 AM to 3:30 PM. At least one travel lane will remain open to traffic at all times. Flaggers will assist with traffic control as needed. Estimated project completion date is October 2019.

[NABCO Electric Company, Inc./Chattanooga 2922/CNQ287]

REGION 2 On-call cable barrier repair on various interstate and state routes: The contractor may have short term shoulder closures in order to perform cable rail repair. Both travel lanes will remain open to traffic at all times on the interstate during any work that is performed. Estimated project completion date is December 2019.

[R.D. Construction, LLC/Parnham/CNS282]

REGION 2 Sweeping and drain cleaning on various interstate and state routes: There will be mobile lane closures supporting a sweeping operation along various regional interstates and state routes. Additionally, in Hamilton County there will be lane and shoulder closures supporting a drain cleaning operation along I-24 (MM 171 to 185) and SR-29 (LM 2.4 to LM 29.6). All drain cleaning activity and sweeping will happen at night, Sunday to Thursday (8 PM to 6 AM). Estimated project completion date is February 2020.

[Blevins Enterprises, Inc./Micka/CNS320]

REGION 2 On-call pavement marking and the retracing of pavement markings with spray thermoplastic on various Interstate and State Routes: The contractor will be retracing existing pavement markings in Hamilton, Bradley, and Sequatchie Counties. This will result in nightly mobile lane closures on the following routes in Hamilton County: I-75, SR-58, SR-320, and SR-29; on the following route in Bradley County: SR-311; and on the following route in Sequatchie County: SR-111. Motorists should be alert to all construction equipment and signage when traveling through the work zone. Estimated project completion date is June 2019.

[Tolle Roads, LLC/Cookeville/CNS090]

REGION 2 On-call pavement marking and the retracing of pavement markings with spray thermoplastic on various Interstate and State Routes: The contractor will be retracing existing pavement markings in Hamilton, Marion, and Sequatchie Counties. This will include mobile lane closures the following routes in Hamilton County: SR-2, SR-8, SR-17, SR-27, SR-58, and SR-319; on the following routes in Marion County: SR-2, SR-15, SR-27, SR-28, SR-150, SR-156, and SR-283; and on the following routes in Sequatchie County: SR-8 and SR-111. Motorists should be alert to all construction equipment and signage when traveling through the workzone.  Estimated project completion date is June 2020.

[Central Seal Company/Cookeville/CNT047]

 

RESTRICTIONS

FENTRESS COUNTY - CNT095: 10 foot max width

BLEDSOE COUNTY - CNS266: 10 foot lane max width

MARION COUNTY - CNS905: 10 foot lane max width

WARREN COUNTY - CNQ270: 10.5 foot lane max width

WARREN COUNTY - CNS254: 11 foot lane max width

HAMILTON COUNTY - CNP230: I-124 (US-27)Northbound Exit 1C 4th St Off Ramp: No oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1A-B Martin Luther King Blvd. Off Ramp: No oversized/over dimensional loads; I-124 (US-27) Southbound On Ramps from Martin Luther King Blvd.: No oversized/over dimensional loads

POLK COUNTY - CNT062: No loads wider than 12 ft. are allowed at LM 26.93 eastbound and westbound

                                                                                                                                                                                                                    

Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity.

Information in this report is provided to the Department of Transportation by the contractors. Most work is weather dependent and subject to change due to inclement weather. All times are local.

From your desktop or mobile device, get the latest construction activity and live streaming SmartWay traffic cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any land-line or cellular phone for travel information, or follow us on Twitter at www.twitter.com/TN511 for statewide travel or Chattanooga area alerts @Chattanooga511 or any of TDOT's other Twitter pages. As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for your destination. Drivers should never tweet, text, or talk on a cell phone while behind the wheel.

In 2016, the Tennessee Department of Transportation lost three workers in the line of duty. All three were struck by passing motorists. Those tragedies bring the total number of TDOT lives lost to 112. We don't want to lose another member of our TDOT family. We're asking you to WORK WITH US. To learn more, go to the website at https://www.tn.gov/tdot/work-with-us/.

###