Proposed Kirby Parkway

Shelby County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. The proposed Kirby Parkway project is in the Environmental phase. The following is a reflection of various aspects of the development phases as they have occurred or will occur on the Kirby Parkway project.

Final Environmental Impact Statement (FEIS) Approved August 1991
Record of Decision (ROD) Issued November 11, 1991
Environmental Re-evaluation Approved March 2001
Draft Supplemental Environmental Impact Statement (DSEIS) Approved October 17, 2007
Public Hearing December 13, 2007
Supplemental Final Environmental Impact Statement (SFEIS) Approved January 30, 2012
NEPA Public Hearing September 24, 2013
Record of Decision (ROD) Issued  
   

*Forecasted dates are subject to change.