Fast Fix 8

  • Project Overview
  • Timeline
  • Details
  • Contacts
  • Videos
  • Fast Fix 8 is finished! On December 4, 2015, Commissioner John Schroer announced the completion of the project, seven months ahead of schedule.

    Originally built in 1968, the I-40 bridges over Herman Street, Clinton Street,  Jo Johnston Avenue and Charlotte Avenue in downtown Nashville need immediate attention. Fast Fix 8 is a $62 million bridge rehabilitation project to replace these four twin bridges using an innovative process called Accelerated Bridge Construction (ABC). ABC requires short-term, total road closures to allow crews the space to do their jobs and the freedom to work around the clock. The closures will also allow construction to be finished in months instead of years. For Fast Fix 8, a portion of the downtown loop will be closed to all traffic for 13 weekends between July 2015 and June 2016. During the scheduled closures, I-40 will be closed from the I-40/I-65 split west of downtown to the I-40/I-65 split south of downtown. The interstate detour will remain the same for all 13 weekends.  Detours on local streets will be dependent upon specific bridge work. Go to the Details section of this project for local detour maps. Bicycle and pedestrian traffic should follow directional signage near the work zone. Detour Map (pdf Document)

    Bridges in the Fast Fix 8 Rehabilitation Project

  • Fast Fix 8 is finished! On December 4, 2015, Commissioner John Schroer announced the completion of the project, seven months ahead of schedule.

    The next set of closures are tentatively scheduled as follows:

    Beginning: July 2015

    Ending: June 2016

    Interstate Closures scheduled for 13 Weekends: July 2015 through June 2016

    All scheduled closures are TENTATIVE, dependent on weather and project progress.

    I-40 at Jo Johnston Avenue

    Friday, July 24 at 8:00 p.m. through Monday, July 27 at 6:00 a.m.

    Friday, July 31 at 8:00 p.m. through Monday, August 3 at 6:00 a.m.

    I-40 at Herman Street

    Friday, September 11 at 8:00 p.m. through Monday, September 14 at 6:00 a.m.

    Friday, September 18 at 8:00 p.m. through Monday, September 21 at 6:00 a.m.

    I-40 at Clinton Street
  • Fast Fix 8 is finished! On December 4, 2015, Commissioner John Schroer announced the completion of the project, seven months ahead of schedule.

    Friday, October 2 at 8:00 p.m. through Monday, October 5 at 6:00 a.m.

    Friday, October 9 at 8:00 p.m. through Monday, October 12 at 6:00 a.m.

    I-40 at Charlotte Avenue

    Friday, October 23 at 8:00 p.m. through Monday, October 26 at 6:00 a.m.

    Friday, October 30 at 8:00 p.m. through Monday, November 2 at 6:00 a.m.

    During all weekend closures, I-40 will be closed from the I-40/I-65 split west of downtown to the I-40/I-65 split south of downtown. Local street closures are dependent on the bridge under construction.

    All scheduled closures are TENTATIVE, dependent on weather and project progress. A final decision for each closure will be made the Wednesday before the scheduled work.

    Fast-Fix-8-Bridges-Aerials  [Adobe Reader Document]

  • Four Twin Bridge Crossings   -   Detour Maps for Local Roads  [Adobe Reader Document]

    I-40 over Herman Street & NWRR - Herman Detours (.pdf)

    » Existing 4 Span Continuous Steel Girder Bridge
    » Three Existing Spans to be Replaced
    » Simple Span Steel & Deck Units
    » "Link-Slab" for Live Load Continuity
    » Construction in Three Weekends

     

    I-40 over Clinton Avenue & CSX Railroad - Clinton Detours (.pdf)

    » Existing 6 Span Bridge
    » Both End Spans to be Filled & Eliminated
    » Two Other Spans to be Filled & Eliminated
    » Existing Span over CSXT to be Replaced
    » Existing Span over Clinton to be Replaced
    » Use Box Beams and Full Depth Deck Panels
    » Construction in Three Weekends



    I-40 over Jo Johnston Avenue

    » Existing 3 Span Bridge
    » Both End Spans to be Filled & Eliminated
    » Existing Span over Jo Johnston to be Replaced
    » Use Box Beams and Full Depth Deck Panels
    » Construction in Three Weekends


    I-40 over Charlotte Avenue - Charlotte Detours (.pdf)

    » Existing 3 Span "K-Frame" Bridge
    » Shortened Single Span to Replace Existing
    » Simple Span Steel & Deck Units
    » Construction in Three Weekends


  • Owner: Tennessee Department of Transportation